Question

1) Determine the P.W and A.E values for the life of the project shown below (N = 20). Would you consider investing in this Bu2) What would happen to the P.W of the problem explained above, if the machine that was initially bought for $22,000 could be

1) Determine the P.W and A.E values for the life of the project shown below (N = 20). Would you consider investing in this Business startup? (Please note in addition to the positive flows, you have three negative flows occurring at N = 7,8,9) (i =5%) $4,800 $1,000 0 20 1 $22,000 $400
2) What would happen to the P.W of the problem explained above, if the machine that was initially bought for $22,000 could be salvaged at the end of the project's life (N= 20) with the following outcomes and possibilities: (i = 5%) Probability of happening Salvage value Outcome 50% $2,400 $3,200 2 50%
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answes fuon at the valu the lite the p.w and A.E TIojeut shaas below (N-20) osltive flows ou haus Tyto0tPP ocutiong at threeau 1000 a 1200 C3 400 ay 1600 Coste 4800 -- + 90h t 1900 062 l05 06 -22000 105 l-05 -y00 (2.03a) 32159 89- R 2 000 - oo ( 2-0Huon that () the machine that 81 wa In Could be Sal ueage d at the En d 1000 the hojeed ste twhere.N20) td-th lollan outcomes32159 89 lo 55 30 22000 400(2.032) 10402 39 saluagy added notameu Ex0cted Duo to NPu has Incieased tsom 9 347.05 vauo new loy

Add a comment
Know the answer?
Add Answer to:
1) Determine the P.W and A.E values for the life of the project shown below (N...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exhibit 128.1 Present Value of a Single Amount* n/i 1% 2% 3% 4% 5% 6% 7%...

    Exhibit 128.1 Present Value of a Single Amount* n/i 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 12% 14% 16% 18% 20% 25% 30% 10.99010 0.98039 0.97087 0.96154 0.95238 0.94340 0.93458 0.92593 0.91743 0.90909 0.89286 0.87719 0.86207 0.84746 0.83333 0.80000 0.76923 2 0.98030 0.96117 0.94260 0.92456 0.90703 0.89000 0.87344 0.85734 0.84168 0.82645 0.79719 0.76947 0.74316 0.71818 0.69444 0.64000 0.59172 3 0.97059 0.94232 0.91514 0.88900 0.86384 0.83962 0.81630 0.79383 0.77218 0.75131 0.71178 0.67497 0.64066 0.60863 0.57870 0.51200 0.45517 4...

  • As you know from Project 4, McCormick & Company is considering building a new factory in...

    As you know from Project 4, McCormick & Company is considering building a new factory in Largo, Maryland. McCormick & Company decided to offer $4,424,000 to obtain the land for this project. The new factory will require an initial investment of $350 million to build the new plant and purchase equipment. You have been asked to continue your work from project 4 with a full analysis of the proposed factory, including the start-up costs, the projected net cash flows from...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT