Samtech Manufacturing purchased land and building for $4
million. In addition to the purchase price, Samtech made the
following expenditures in connection with the purchase of the land
and building:
Title insurance | $ | 21,000 | |
Legal fees for drawing the contract | 7,500 | ||
Pro-rated property taxes for the period after acquisition | 41,000 | ||
State transfer fees | 4,500 | ||
An independent appraisal estimated the fair values of the land and
building, if purchased separately, at $3.9 and $1.1 million,
respectively. Shortly after acquisition, Samtech spent $87,000 to
construct a parking lot and $45,000 for landscaping.
Required:
1. Determine the initial valuation of each asset
Samtech acquired in these transactions.
2. Determine the initial valuation of each asset,
assuming that immediately after acquisition, Samtech demolished the
building. Demolition costs were $300,000 and the salvaged materials
were sold for $8,500. In addition, Samtech spent $84,000 clearing
and grading the land in preparation for the construction of a new
building.
1 | Value to be Capitalized | = | $40,00,000 + $21,000 + $7,500 + $4,500 | ||
= | $ 40,33,000 | ||||
Assets | Fair Value (a) | Percentage (b) = [(a)/ Total] | Proportional Value (b X Total) | ||
Land | $ 39,00,000 | 78% | $ 31,45,740 | ||
Building | $ 11,00,000 | 22% | $ 8,87,260 | ||
Total | $ 50,00,000 | $ 40,33,000 | |||
Land | = | $ 31,45,740 | |||
Building | = | $ 8,87,260 | |||
Land Improvements | = | ($87,000 + $45,000) | |||
= | $ 1,32,000 | ||||
2 | Computation of Cost of Land: | ||||
Purchase Price | = | $ 40,00,000 | |||
Title Insurance | = | $ 21,000 | |||
Legal fees | = | $ 7,500 | |||
State transfer fees | = | $ 4,500 | |||
Demolition cost | = | $ 3,00,000 | |||
Cleaning and grading cost | = | $ 84,000 | |||
Salvage value of material | = | $ -8,500 | |||
Cost of Land | = | $ 44,08,500 | |||
Land | = | $ 44,08,500 | |||
Building | = | 0 | |||
Land Improvements | = | ($87,000 + $45,000) | |||
= | $ 1,32,000 |
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance Legal fees for drawing the contract Pro-rated property taxes for the period after acquisition State transfer fees $26,000 5,000 46,000 5,000 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.2 and $1.8 million, respectively. Shortly after acquisition, Samtech spent $92,000...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 34,000 Legal fees for drawing the contract 9,000 Pro-rated property taxes for the period after acquisition 54,000 State transfer fees 5,800 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.5 and $1.5 million, respectively. Shortly after acquisition, Samtech spent...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 25,000 Legal fees for drawing the contract 9,500 Pro-rated property taxes for the period after acquisition 45,000 State transfer fees 4,900 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3 and $2 million, respectively. Shortly after acquisition, Samtech spent...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance Legal fees for drawing the contract Pro-rated property taxes for the period after acquisition State transfer fees $ 19,000 6,500 39,000 4,300 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.7 and $1.3 million, respectively. Shortly after acquisition, Samtech spent...
Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 23,000 Legal fees for drawing the contract 8,500 Pro-rated property taxes for the period after acquisition 43,000 State transfer fees 4,700 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3 and $2 million, respectively. Shortly after acquisition, Samtech spent...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance $ 31,000 Legal fees for drawing the contract 7,500 Pro-rated property taxes for the period after acquisition 51,000 State transfer fees 5,500 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.5 and $1.5 million, respectively. Shortly after acquisition, Samtech spent...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance$20,000Legal fees for drawing the contract7,000Pro-rated property taxes for the period after acquisition40,000State transfer fees4,400 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.2 and $1.8 million, respectively. Shortly after acquisition, Samtech spent $86,000 to construct a parking lot and $44,000 for landscaping. Required:1. Determine...
1 Samtech Manufacturing purchased land and building for $3 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: 1 Title insurance $30,000 7,000 50,000 5,400 points Legal fees for drawing the contract Pro-rated property taxes for the period after acquisition State transfer fees еВook An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3 and $1 million, respectively. Shortly after...
Check my work Samtech Manufacturing purchased land and building for $5 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance Legal fees for drawing the contract Pro-rated property taxes for the period after acquisition State transfer fees $28,000 6,000 48,000 5,200 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3.6 and $2.4 million, respectively. Shortly after acquisition,...
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: Title insurance$25,000Legal fees for drawing the contract9,500Pro-rated property taxes for the period after acquisition45,000State transfer fees4,900 An independent appraisal estimated the fair values of the land and building, if purchased separately, at $3 and $2 million, respectively. Shortly after acquisition, Samtech spent $91,000 to construct a parking lot and $49,000...