Question

Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 21,000 toy action figures t

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Data for resource variance

Particulars

Standard

Actual

Quantity

Rate

Total Cost

Quantity

Rate

Total Cost

Material

47,750 pounds

$ 0.70 per pound

$ 33,425

49,143 pounds

$ 0.70 per pound

34400

Labour

1,337 labour hours

$ 12.00 per labour hour

$ 16,044

1,375 labour hours

$ 12.00 per labour hour

16500

Answer 1)

Material Quantity Variance = (Standard Quantity– Actual Quantity) X Standard Price per unit of input

                                            = (47,750 pounds – 49,143 pounds) X $ 0.70 per pound

                                            = $ 975 (Unfavourable)

Therefore Material Quantity variance is $ 975 (Unfavourable)

Working Notes:

Calculation of Actual price per pound of raw material

Material Price Variance = (Standard Price per pound – Actual Price per pound) X Actual Quantity of material consumed

Since there is no direct material price variance, it is implied that the standard price per pound of raw material (i.e. $ 0.70 per pound) is equal to its actual price per pound.

Therefore actual price of raw material is $ 0.70 per pound.

Calculation of Actual quantity of raw material consumed in production of 19,100 units of output

Actual Quantity consumed = Total Actual cost of raw material/ Actual cost per pound of raw material

                                                  = $ 34,400/ $ 0.70 per pound

                                                  = 49,143 pounds (approximately)

Therefore actual quantity of raw material consumed in production of 19,100 units of output is 49,143 pounds.

Calculation of Standard quantity of raw material consumed for standard production of 21,000 units of output

Standard Quantity consumed = Total Standard cost of raw material/ Standard cost per pound of raw material

                                                  = $ 36,750/ $ 0.70 per pound

                                                  = 52,500 pounds

Therefore standard quantity of raw material consumed in production of 21,000 units of output is 52,500 pounds.

Calculation of Standard quantity of raw material required for actual production of 19,100 units of output

Standard quantity of raw material required for actual output = (Standard quantity of raw material for standard output/ Standard output) X Actual output

                                                   = (52,500 pounds/ 21,000 units) X 19,100 units

                                                   = 47,750 pounds

Therefore standard quantity of raw material required for actual output of 19,100 units is 47,750 pounds

Answer 2)

Labour time Variance = (Standard Labour hours– Actual Labour hours) X Standard labour rate per labour hour

                                            = (1,337 Labour hours – 1,375 Labour hours) X $ 12.00 per Labour hour

                                            = $ 456 (Unfavourable)

Therefore Labour time variance is $ 456 (Unfavourable)

Working Notes:

Calculation of Actual rate per labour hour

Labour Rate Variance = (Standard labour rate per hour – Actual labour rate per hour) X Actual labour hours consumed

Since there is no labour price variance, it is implied that the standard rate per labour hour (i.e. $ 12.00) is equal to its actual rate per labour hour.

Therefore actual rate of labour is $ 12.00 per labour hour

Calculation of Actual labour hours consumed in production of 19,100 units of output

Actual labour hours consumed = Total Actual Direct labour cost/ Actual rate per labour hour

                                                  = $ 16,500/ $ 12.00 per labour hour

                                                  = 1,375 labour hours

Therefore actual labour hours consumed in production of 19,100 units of output are 1,375.

Calculation of Standard labour hours consumed for standard production of 21,000 units of output

Standard labour hours consumed= Total Standard direct labour cost/ Standard rate per direct labour hour

                                                  = $ 17,640/ $ 12.00 per direct labour hour

                                                  = 1,470 labour hours

Therefore standard labour hour consumed in production of 21,000 units of output are 1,470.

Calculation of Standard labour hours required for actual production of 19,100 units of output

Standard labour hours required for actual output = (Standard labour hours for standard output/ Standard output) X Actual output

                                                   = (1,470 labour hours/ 21,000 units) X 19,100 units

                                                   = 1,337 labour hours

Therefore standard labour hours required for actual output of 19,100 units are 1,337.

Add a comment
Know the answer?
Add Answer to:
Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 21,000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 23,000...

    Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 23,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $24,150 Direct labor 10,120 Total $34,270 The standard materials price is $0.70 per pound. The standard direct labor rate is $11.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $22,900 Actual...

  • Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 12,000...

    Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 12,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $25,200 Direct labor 10,080 Total $35,280 The standard materials price is $0.60 per pound. The standard direct labor rate is $12.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $22,500 Actual...

  • Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 13,000...

    Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 13,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $19,500 Direct labor 11,830 Total $31,330 The standard materials price is $0.50 per pound. The standard direct labor rate is $13.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: $18,200 Actual direct materials Actual...

  • Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 26,000...

    Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 26,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $36,400 Direct labor 15,600 Total $52,000 The standard materials price is $0.40 per pound. The standard direct labor rate is $15.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $32,600 Actual...

  • 3 Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted...

    3 Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 14,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $14,000 Direct labor 13,720 Total $27,720 The standard materials price is $0.50 per pound. The standard direct labor rate is $14.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $13,300...

  • Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 24,000 toy action fig...

    Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 24,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $42,000 15,840 Direct labor Total $57,840 The standard materials price is $0.50 per pound. The standard direct labor rate is $11.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials Actual direct...

  • Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 24,000...

    Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 24,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $25,200 Direct labor 25,200 Total $50,400 The standard materials price is $0.70 per pound. The standard direct labor rate is $15.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $22,800 Actual...

  • Direct Materials and Direct Labor Variances At the beginning of June, Bezco Toy Company budgeted 20,000...

    Direct Materials and Direct Labor Variances At the beginning of June, Bezco Toy Company budgeted 20,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $49,000 Direct labor 15,400 Total $64,400 The standard materials price is $0.70 per pound. The standard direct labor rate is $11.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $46,400 Actual...

  • At the beginning of June, Kimber Toy Company budgeted 24,000 toy action figures to be manufactured...

    At the beginning of June, Kimber Toy Company budgeted 24,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $18,000 Direct labor 14,400 Total $32,400 The standard materials price is $0.50 per pound. The standard direct labor rate is $15.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $16,700 Actual direct labor 13,300 Total $30,000 There...

  • At the beginning of June, Kimber Toy Company budgeted 24,000 toy action figures to be manufactured...

    At the beginning of June, Kimber Toy Company budgeted 24,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $30,000 Direct labor 18,480 Total $48,480 The standard materials price is $0.50 per pound. The standard direct labor rate is $11.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $28,500 Actual direct labor 17,500 Total $46,000 There...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT