Question

Question 7 Partially correct Mark 0.38 out of 1.00 P Flag questi Materials Variances Assume that Pearle Vision uses standard
0 0
Add a comment Improve this question Transcribed image text
Answer #1

* Assume that @ flexible budget cost: 136800 (6) Actual material cost incurred Total materice variance $170975 6025 TOT Varia

Add a comment
Know the answer?
Add Answer to:
Question 7 Partially correct Mark 0.38 out of 1.00 P Flag questi Materials Variances Assume that...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Materials Variances Assume that Pearle Vision uses standard costs to control the materials in its made-to-order...

    Materials Variances Assume that Pearle Vision uses standard costs to control the materials in its made-to-order sunglasses. The standards call for 2 ounces of material for each pair of lenses. The standard cost per ounce of material is $16.25. During July, the Santa Clara location produced 5,200 pairs of sunglasses and used 9,800 ounces of materials. The cost of the materials during July was $17.00 per ounce, and there were no beginning or ending inventories. Required a. Determine the flexible...

  • Question 13 Partially correct Mark 0.58 out of 1.00 P Flag question Computation of Variable Cost...

    Question 13 Partially correct Mark 0.58 out of 1.00 P Flag question Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A $2.00 per unit 1 unit of material B $3.00 per unit Direct labor 3 hours $8.00 per hour Activity for September Materials purchased Material A 3,400 units * $2.05 per unit Material B 800 units x...

  • eBook Print Question 6 Partially correct Mark 0.50 out of 1.00 P Pag question Materials Variances...

    eBook Print Question 6 Partially correct Mark 0.50 out of 1.00 P Pag question Materials Variances North Wind manufactures decorative weather vanes that have a standard materials cost of two pounds of raw materials at $1.50 per pound. During September 8.000 pounds of raw materials costing 51.59 per pound were used in making 3.900 weather vanes. Determine the materials price and quantity variance. Materials price variance 5 0 X U. Materials quantity variances O X U Check

  • Question 14 Partially correct Mark 0.62 out of 1.00 P Hag question Variance Computations and Explanations...

    Question 14 Partially correct Mark 0.62 out of 1.00 P Hag question Variance Computations and Explanations Outdoor Company manufactures camping tents from a lightweight synthetic fabric. Each tent has a standard materials cost of $21, consisting of 4 yards of fabricat $5.25 per yard. The standards call for 2 hours of assembly at $10 per hour. The following data were recorded for October, the first month of operations: Fabric purchased 0,000 yards x 55.00 per yard Fabric used in production...

  • Question 5 Partially correct Mark 1.00 out of 15.00 P Flag question Computing Percentage-of-Completion Revenues Bartov...

    Question 5 Partially correct Mark 1.00 out of 15.00 P Flag question Computing Percentage-of-Completion Revenues Bartov Corporation agreed to build a warehouse for $3,000,000. Expected and actual) costs for the warehouse follow: 2016, $500,000 2017, $1,400,000 and 2018, $600,000. The company completed the warehouse in 2018. Compute revenues, expenses, and income for each year 2016 through 2018 using the percentage-of-completion method. Round percentages to the nearest whole percent. Use rounded percentages to calculate subsequent answers. Year Costs incurred % of...

  • Question 9 Partially correct Mark 0.50 out of 1.00 Prag question Variable Overhead Variances Assume that the best c...

    Question 9 Partially correct Mark 0.50 out of 1.00 Prag question Variable Overhead Variances Assume that the best cost driver that Sony has for variable factory overhead in the assembly department is machine hours. During April, the company budgeted 480,000 machine hours and 54,000,000 for its Texas plant's assembly department. The actual variable overhead incurred was 54.180,000, which was related to 500.000 machine hours Do not round until your final answers. Round your answers to the nearest dollar. (a) Determine...

  • CLUCK HERE TO REVIEW LEARNING OBJECTIVES QUESTION 1 Partially correct Mark 0.20 out of 2.00 Flag...

    CLUCK HERE TO REVIEW LEARNING OBJECTIVES QUESTION 1 Partially correct Mark 0.20 out of 2.00 Flag question Schedule of Cost of Goods Manufactured and Sold At December 31, 2016, the end of its fiscal year, Lederman Manufacturing Corporation collected the following data for 2016: $25,000 15,000 30,000 Work in process inventory, December 3141,000 51,000 Finished goods inventory, December 31 36,000 Net delivered cost of materials purchased 125,000 148,000 12,000 37,000 10,000 65,000 21,000 62,000 Materials inventory. lanuary 1 Materials inventory,...

  • Question 2 Partially correct Mark 1.00 out of 3.00 P Flag question Payback Period and NPV:...

    Question 2 Partially correct Mark 1.00 out of 3.00 P Flag question Payback Period and NPV: Taxes and Straight-Line Depreciation Assume that United Technologies is evaluating a proposal to change the company's manual design system to a computer-aided design (CAD) system. The proposed system is expected to save 10,000 design hours per year; an operating cost savings of $40 per hour. The annual cash expenditures of operating the CAD system are estimated to be $200,000. The CAD system requires an...

  • eBook Question 1 Partially correct Mark 0.29 out of 1.00 P Flag question Activity-Based Budget Macon...

    eBook Question 1 Partially correct Mark 0.29 out of 1.00 P Flag question Activity-Based Budget Macon Industries has the following budget information available for February Units manufactured 20,000 Factory administration $45.000 Assembly 0.5 hour per unit X $8 Direct materials 2 pounds per unit X $3 Inspection $200 per batch of 1,000 units Manufacturing overhead $3 per unit Product development $15,000 Setup cost $10 per batch of 1,000 units Use activity based costing to prepare a manufacturing cost budget for...

  • Problem 3 (Textbook Reference: 8-6) - Compute materials and labor variances Based on standard volume of...

    Problem 3 (Textbook Reference: 8-6) - Compute materials and labor variances Based on standard volume of 96,000 units per month, the standard cost of the product manufactured by Tahoe Company consists of Direct materials (0.25 pounds x 58 per pound) S 2.00 Direct labor (0.5 hours x 57.60 per hour) $ 3,80 Variable manufacturing overhead per unit S 250 Fixed manufacturing overhead ($144,000 in total) S 1.50 $ 9,80 A total of 25.200 pounds of materials was purchased at $8.40...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT