Payback period is the time period in which the initial investment is recovered
Since it is 2.5 hours, 375000+X+500000/2 = 1,075,000
X = $450,000
Henc, cash flow in year 2 = $450,000
NPV = Present value of cash inflows – present value of cash outflows
= 375000*PVF(8%, 1 year) + 450,000*PVF(8%, 2 years)+500,000*PVF(8%, 3 years) + 450,000*PVF(8%, 4 years) – 1,075,000
= 375000*0.926 + 450,000*0.857 + 500,000*0.794 + 450,000*0.735 – 1,075,000
= 385,650
Suppose you are evaluating a project with the expected future cash inflows shown in the following...
Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $325,000 Year 2 $450,000 Year 3 Year 4 $500,000 $500,000 If the project's weighted average cost of capital (WACC) is 10%, the project's NPV...
Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. Year Year 1 Year 2 Year 3 Year 4 Cash Flow $375,000 $425,000 $450,000 $475,000 If the project's weighted average cost of capital (WACC) is 7%, the project's NPV...
Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $300,000 Year 2 $450,000 Year 3 $400,000 Year 4 $450,000 If the project's weighted average cost of capital (WACC) is 7%, the project's NPV...
Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $325,000 Year 2 $450,000 Year 3 $425,000 Year 4 $400,000 If the project's weighted average cost of capital (WACC) is 8%, the project's NPV...
Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. If the project's ~WACC~ is 7%, the project's NPV (rounded to the nearest dollar) is: Year Cash Flo Year 1 $300,000 Year 2 $450,000 Year 3 $450,000 Year 4...
Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $275,000 Year 2 $475,000 Year 3 $400,000 Year 4 $450,000 If the project’s weighted average cost of capital (WACC) is 10%, the project’s NPV...
Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $275,000 Year 2 $425,000 Year 3 $475,000 Year 4 $450,000 If the project’s weighted average cost of capital (WACC) is 10%, the project’s NPV...
What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. Year Year 1 Year 2 Year 3 Year 4 Cash Flow $300,000 $450,000 $400,000 $450,000 If the project's weighted average cost of...
What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. If the project's ~WACC is 9%, the project's NPV (rounded to the nearest dollar) is: Year Year 1 Year 2 Year 3...
Suppose you are evaluating a project with the cash inflows shown in the following table. Your boss has asked you to calculate the project's net present value (NPV). You don't know the project's initial cost, but you do know the project's regular, or conventional, payback period is 2.50 years. The project's annual cash flows are: Year Cash Flow Year 1 $300,000 Year 2 400,000 Year 3 Year 4 400,000 475,000 If the project's desired rate of return is 7.00%, the...