A report for the company's Assembly Department for the month of March follows:

Assembly Department
Cost Report
For the Month Ended March 31
Actual Results Planning Budget Variances
Machine-hours 15,000 20,000
Variable costs:
Supplies $ 9,900 $

10,500

$ 600 F
Scrap 35,000 37,500 2,500 F
Indirect materials 101,000 120,000 19,000 F
Fixed costs:
Wages and salaries 79,900 75,000 4,900

U

Equipment depreciation 105,000 105,000
Total cost $ 330,800 $ 348,000 $ 17,200 F


After receiving a copy of this cost report, the supervisor of the Assembly Department stated, “These reports are super. It makes me feel really good to see how well things are going in my department. I can’t understand why those people upstairs complain so much about the reports.”

For the last several years, the company’s marketing department has chronically failed to meet the sales goals expressed in the company’s monthly budgets.

Required:

1. The company’s president is uneasy about the cost reports, identify at least two reasons.

2. What kind of reports should be used to give better insight into how well departmental supervisors are controlling costs?

3. Complete the new performance report for the quarter, based on Flexible Budget Performance approach.

4. Were costs well controlled in March?

1 0
Add a comment Improve this question Transcribed image text
Answer #1
1) cost reports are ineffective since budgeted costs at one level of
activity are compared to acutal costs at another level of
activity.
cost reports show whether fixed costs are controlled and do not
show whether variable costs are controlled
2) flexible budget performance report should be used
3)                                   Flexible Budget Performance Report            
Actual Spending variance Flexible Activity variance Planning
results Budget Budget
Machine hours 15,000 0 15,000 20,000
supplies 9,900 2,025 U 7875 2,625 F 10,500
Scrap 35,000 6,875 U 28125 9,375 F 37,500
indirect materials 101,000 11,000 U 90000 30,000 F 120,000
Wages and salaries 79,900 4,900 U 75,000 0 N 75,000
Equipment Depreciation 105,000 0 U 105,000 0 N 105,000
total 330,800 24,800 U 306000 42,000 F 348,000
(here wages & salaires and Equipment depreciation are fixed costs)
Flexible budget = planning budget cost/20000*15000
4) costs were not well controlled
Add a comment
Know the answer?
Add Answer to:
Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning Budget Variances Machine-hours 25,000 30,000 Variable costs: Supplies $ 7,200 $ 7,800 $ 600 F...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning Budget Variances Machine-hours 15,000 20,000 Variable costs: Supplies $ 11,400 $ 12,000 $ 600 F...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning Budget Variances Machine-hours 25,000 30,000 Variable costs: Supplies $ 8,400 $ 9,000 $ 600 F...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: See bottom of question After receiving a copy of this cost report, the supervisor of the Assembly Department stated, “These reports are super. It makes me feel really...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: eBook Assembly Department Cost Report For the Month Ended March 31 Actual Planning Results Budget Machine-hours 25,000 30,eee Variances Print References 7,200 $ 22,400 68,689 7,800 $ 600...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Planning Results Budget 25,000 30,000 Variances Machine-hours $ 6,000 $ 16,800 54,200 6,600 $ 600 F 18,000...

  • HELP WITH REQUIREMENT 3 Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning...

    HELP WITH REQUIREMENT 3 Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning Budget Variances Machine-hours 15,000 20,000 Variable costs: Supplies $ 8,700 $...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Variances Assembly Department Cost Report For the Month Ended March 31 Actual Planning Results Budget Machine-hours 35,000 40,000 Variable costs: Supplies $ 29,700 $ 32,000 Scrap 19,500 20,000...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Variances Assembly Department Cost Report For the Month Ended March 31 Actual Planning Results Budget Machine-hours 35,000 40,000 Variable costs: Supplies $ 29,700 $ 32,000 Scrap 19,500 20,000...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Planning Results Budget 25,000 30,000 Variances Machine-hours $ 5,700 $ 15,400 50,600 6,300 16,500 57,000 $ 600...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT