Question

Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system.

A report for the company's Assembly Department for the month of March follows:

Assembly Department
Cost Report
For the Month Ended March 31
Actual Results Planning Budget Variances
Machine-hours 25,000 30,000
Variable costs:
Supplies $ 7,200 $

7,800

$ 600 F
Scrap 22,400 24,000 1,600 F
Indirect materials 68,600 79,500 10,900 F
Fixed costs:
Wages and salaries 69,100 66,000 3,100

U

Equipment depreciation 96,000 96,000
Total cost $ 263,300 $ 273,300 $ 10,000 F


After receiving a copy of this cost report, the supervisor of the Assembly Department stated, “These reports are super. It makes me feel really good to see how well things are going in my department. I can’t understand why those people upstairs complain so much about the reports.”

For the last several years, the company’s marketing department has chronically failed to meet the sales goals expressed in the company’s monthly budgets.

Required:

1. The company’s president is uneasy about the cost reports, identify at least two reasons.

2. What kind of reports should be used to give better insight into how well departmental supervisors are controlling costs?

3. Complete the new performance report for the quarter, based on Flexible Budget Performance approach.

4. Were costs well controlled in March?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Westmont corporation
Answer 1- Cost reports are ineffective since budgeted costs at one level of activity are compared to
actual costs at another level of activity .
Cost reports show whether FC are controlled and do not show whether VC are controlled.
Point 1 and Point 2 are the required answer.
Answer 2-
Flexible Budget performance reports must be used.
Answer 3-
Flexible Budget Performance Reoprt
Actual Results ( 25000 Machine hours ) spending Variances Flexible budget (25000 machine hours) Calculation for flexible budget Activity varaince Planning Budget (30000 machine hours )
Expenses :
Supplies 7,200 700 U 6500 7800 * 25000 /30000 -1300 F 7800
Scraps 22,400 2,400 U 20000 24000 * 25000 / 30000 -4000 F 24000
Indirect material 68,600 2,350 U 66250 79500 * 25 / 30 -13250 F 79500
W and S 69,100 3,100 U 66000 0 66000
Depreciation 96,000 0 U 96000 0 96000
Total expense 2,63,300 8,550 U 2,54,750 -18,550 F 2,73,300
Answer 4-
Costs were not well controlled as there is negative spending variance of $ 8550.
Add a comment
Know the answer?
Add Answer to:
Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: eBook Assembly Department Cost Report For the Month Ended March 31 Actual Planning Results Budget Machine-hours 25,000 30,eee Variances Print References 7,200 $ 22,400 68,689 7,800 $ 600...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning Budget Variances Machine-hours 15,000 20,000 Variable costs: Supplies $ 9,900 $ 10,500 $ 600 F...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning Budget Variances Machine-hours 15,000 20,000 Variable costs: Supplies $ 11,400 $ 12,000 $ 600 F...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning Budget Variances Machine-hours 25,000 30,000 Variable costs: Supplies $ 8,400 $ 9,000 $ 600 F...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: See bottom of question After receiving a copy of this cost report, the supervisor of the Assembly Department stated, “These reports are super. It makes me feel really...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Planning Results Budget 25,000 30,000 Variances Machine-hours $ 6,000 $ 16,800 54,200 6,600 $ 600 F 18,000...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Variances Assembly Department Cost Report For the Month Ended March 31 Actual Planning Results Budget Machine-hours 35,000 40,000 Variable costs: Supplies $ 29,700 $ 32,000 Scrap 19,500 20,000...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Variances Assembly Department Cost Report For the Month Ended March 31 Actual Planning Results Budget Machine-hours 35,000 40,000 Variable costs: Supplies $ 29,700 $ 32,000 Scrap 19,500 20,000...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Planning Results Budget 25,000 30,000 Variances Machine-hours $ 5,700 $ 15,400 50,600 6,300 16,500 57,000 $ 600...

  • Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While...

    Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the Information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Planning Budget Results Variances Machine-hours 15,000 20,000 Variable costs: Supplies Зeкар Indirect materials $ 10.200 $ 10,e00...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT