Part a | |||||
Total cost(a) | $1,140,000 | ||||
Total machine hours(b) | 40000 | hours | |||
Cost per machine hours(a/b) | $28.50 | ||||
Component 3F5 | Component T76 | ||||
Machine hours allocated | 1,000 | 10,000 | |||
Cost per machine hours | $28.50 | $28.50 | |||
Total Overhead cost allocated | $28,500 | $285,000 | |||
No. of units produced | 500 | 5000 | |||
Overhead cost per unit | $57.00 | $57.00 | |||
Part b | |||||
Overhead Assigned | Activity driver | Activity Rate | Activity variable | Total Overhead cost | |
Component 3F5 | |||||
Product assembly cost | Machine hours | $15.00 | 1000 | $15,000.00 | |
Machine setup and calibration | No. of setups | $160.00 | 40 | $6,400.00 | |
Product inspection | No. of batches | $60.00 | 20 | $1,200.00 | |
Raw material storage | Pounds | $0.26 | 10000 | $2,600.00 | |
Total Overhead Cost | $25,200.00 | ||||
No. of units produced | $500.00 | ||||
Overhead cost per unit | $50.40 | ||||
Overhead Assigned | Activity driver | Activity Rate | Activity variable | Total Overhead cost | |
Component T76 | |||||
Product assembly cost | Machine hours | $15.00 | 10000 | $150,000.00 | |
Machine setup and calibration | No. of setups | $160.00 | 20 | $3,200.00 | |
Product inspection | No. of batches | $60.00 | 10 | $600.00 | |
Raw material storage | Pounds | $0.26 | 10000 | $2,600.00 | |
Total Overhead Cost | $156,400 | ||||
No. of units produced | $5,000 | ||||
Overhead cost per unit | $31.28 | ||||
Note:Activity Rate =Estimated Overhead cost / Total of expected activity | |||||
Exercise 7-10 Eric Parker has been studying his department's profitability reports for the past six months....
Exercise 7-10 Eric Parker has been studying his department's profitability reports for the past six months. He has just completed a managerial accounting course and is beginning to question the company's approach to allocating overhead to products based on machine hours. The current department overhead budget of $1,140,000 is based on 40,000 machine hours. In an initial analysis of overhead costs, Eric has identified the following activity cost pools. Cost Pool Expected Cost Expected Activities Product assembly $ 600,000 40,000...
Eric Parker has been studying his department’s profitability
reports for the past six months. He has just completed a managerial
accounting course and is beginning to question the company’s
approach to allocating overhead to products based on machine hours.
The current department overhead budget of $1,140,000 is based on
40,000 machine hours. In an initial analysis of overhead costs,
Eric has identified the following activity cost pools.
Cost Pool
Expected Cost
Expected
Activities
Product assembly
$
600,000
40,000
Machine hours...
Exercise 7-7
Eric Parker has been studying his department’s profitability
reports for the past six months. He has just completed a managerial
accounting course and is beginning to question the company’s
approach to allocating overhead to products based on machine hours.
The current department overhead budget of $930,230 is based on
44,500 machine hours. In an initial analysis of overhead costs,
Eric has identified the following activity cost pools.
Cost Pool
Expected
Cost
Expected Activities
Product assembly
$
400,500
44,500...
ignment CALCULATOR FULL SCREEN PRINTER VERSION BACK NEXT Exercise 7-9 Your answer is partially correct. Try again. Eric Parker has been studying his department's profitability reports for the past six months. He has just completed a managerial accounting course and is beginning to question the company's approach to allocating overhead to products based on machine hours. The current department overhead budget of $810,495 is based on 38,500 machine hours. In an initial analysis of overhead costs, Eric Parker has identified...
Windsor Company uses an activity-based costing system. It has the following manufacturing activity areas, related drivers used as allocation bases, and cost allocation rates: Cost Allocation Rate $ 40 0.4 Cost Driver Number of setups Number of parts Machine hours Direct labour hours Number of finished units Activity Machine setup Material handling Machining Assembly Inspection During the month, 100 units were produced, requiring 2 setups. Each unit consisted of 21 parts and used 1.4 direct labour hours and 1.25 machine...
7. A company has two products: Basic and Deluxe. It uses activity-based costing and has prepared the following analysis showing budgeted costs and activities. 16,000 units, Annual production of Basic is 28.00 Annual production of Deluxe is - 12,000 units. Product Basie Product Deluxe Total Activity Cost Pool Budgeted Overhead Cost $ 170,000 Machining 600 Machine hours 1400 Machine Hours 800 Machine Hours 600 setups 800 setups 1400 Setups S 145,000 Setups 450 Batches 1100 Batches 650 Batches $ 160,000...
Exercise 7-6 Smith Machining makes three products. The company's annual budget includes $1,000,000 of overhead. In the past, the company allocated overhead based on expected capacity of 40,000 direct labor hours. The company recently implemented an activity-based costing system and has determined that overhead costs can be broken into four overhead pools: order processing, setups, milling, and shipping. The following is a summary of company information: Order processing Setups Milling Shipping Expected Cost $ 175,000 160,000 410,000 255,000 $ 1,000,000...
Activity Based Costing Activity Based Costing Help Save & Exit Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Tabor $320,000 Indirect Materials Other Overhead Part 2 of 3 Production Activity Grinding Polishing Product modification Providing power System calibration $135,000 600,000 $255,000 500,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power Systen calibration 1,500 engineering hours 17,000 direct...
Weisman, Inc. uses activity-based costing as the basis for information to set prices for its six lines of seasonal coats Estimated Overhead Expected Uuse of Cost Drivers per Activity Activity Cost Pools Designing Sizing and cutting Stitching and trimming Wrapping and packing $443,000 14,800 designer hours 3,960,000 164,000 machine hours ,420,000 81,500 labor hours 330,000 31,500 finished units Compute the activity-based overhead rates using the following budgeted data for each of the activity cost pools. (Round answers to 2 decimal...
Weisman, Inc. uses activity-based costing as the basis for
information to set prices for its six lines of seasonal
coats.
Activity Cost Pools
Estimated
Overhead
Expected Use of
Cost Drivers per Activity
Designing
$455,000
14,000
designer hours
Sizing and cutting
3,950,000
168,000
machine hours
Stitching and trimming
1,480,000
78,500
labor hours
Wrapping and packing
333,000
30,000
finished units
Compute the activity-based overhead rates using the following
budgeted data for each of the activity cost pools.
(Round answers to 2 decimal...