Krypton Ltd.’s budgeted information relating to the manufacture of two of its products is presented below:
# of times driver used |
||||
Activity |
Cost |
Driver |
Product A |
Product B |
Setup |
$56501 |
# of batches |
30 |
10 |
Engineering |
$121204 |
# of engineering hours |
6657 |
9224 |
Machine Maintenance |
$89140 |
# of machine hours |
7000 |
12000 |
Direct labour cost |
$11/hour |
$352180 |
$528909 |
|
Direct materials |
$126718 |
$96026 |
What would be the pre-determined overhead rate under a traditional costing model, with overhead allocated based on direct labour hours?
Select one:
a. $0.30
b. $1.20
c. $16.80
d. $3.33
Waymire Ltd. currently uses a traditional costing system based on direct labour hours to allocate overhead. This year, the company has budgeted to produce 1602 units of one of its products. Each unit requires 3 hours of direct labour.
For the coming year, the company is considering changing to an activity based costing system by allocating overhead based on 3 activities. The following are the activities, budgeted total cost and cost drivers per activity for the upcoming year:
Activity |
Cost driver |
Cost |
Cost Base Volume |
Processing |
machine hours |
$866307 |
20619 |
Assembly |
direct labour hours |
$414317 |
114556 |
Inspection |
# of inspections |
$700768 |
40869 |
Waymire Ltd. has estimated the consumption of each of the
activities for this product: 1988 machine hours and 2987
inspections.
What is the product’s overhead cost per unit if Waymire continues to allocate overhead using the current costing system?
Select one:
a. $94.96
b. $10.85
c. $51.89
d. $17.30
Krypton Ltd.’s budgeted information relating to the manufacture of two of its products is presented below:...
Krypton Ltd.'s budgeted information relating to the manufacture of two of its products is presented below: # of times driver used Cost Product A Driver Activity Product B Setup $61111 # of batches Engineering $121374 of engineering 6134 9761 hours Machine 579587 # of machine hours 7000 12000 Maintenance Direct labour cost $11/hour Direct materials $348243 $128626 5529565 $95449 What would be the pre-determined overhead rate under a traditional costing model, with overhead allocated based on direct labour hours?! Select...
2 sweredthe company has budgeted to produce 1718 units of one of its products. Each unit requires 2 hours of direct labour ut of Waymire Ltd. currently uses a traditional costing system based on direct labour hours to allocate overhead. This year For the coming year, the company is considering changing to an activity based costing system by allocating overhead based on 3 activities. The following are the activities, budgeted total cost and cost drivers per activity for the upcoming...
Waymire Ltd. manufactures two products and currently allocates overhcad based on direct labour hours. For the coming year, the company is considering changing to an activity based costing system by allocating overhead based on 3 activities. The estimated amount of overhead traceable to the 3 activities for the coming year are given below Activity Purchase orders Maintenance Machine Cost driver Cost #oforders $873069 347 Product I Product 2 599 19282 2198 $448164 18218 hours Inspection #of S704819 1736 inspections Total...
Coronado Company produces two products: MB-R and MB-X. Currently, Coronado allocates overhead based on direct labour hours. Overhead is estimated at $436,800. The cost accountant realizes that there are some differences in how resources are being used in producing these two components and is considering the use of ABC to allocate overhead. She determines that overhead is caused by testing and inspections, $112,000; machine setup, $84,000; machine stamping, $200,000; and plant maintenance, $40,800. Coronado estimates the following activities related to...
(a) Phoenix Corporation has 4 departments in its factory consisting of two service departments, Human Resources (HR) and Information System (IS), and two production departments, Machining and Assembly. Each of the production departments produce a single product. The current costs of each department are: $60,000 $2,400,000 $8,756,000 S12,542,000 HR IS Machining Assembly The distribution and consumption of departments' services is given as follows: Service provided to: Machining Assembly HR IS Services provided by: 40% 35% HR 25% 10% IS 30%...
Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing system. The following are the activities, budgeted total cost and cost drivers per activity for the year 20x9: Activity Budgeted Cost Cost Base Cost Base Volume Assembly $877831 # of DL hours 37167 Inspection $668988 # of units 20830 Shipping $339555 # of batches 186 Plaid Manufacturing has budgeted to produce 3,000 units of M1. M1 is manufactured in batches of 80 units and...
Please show work. Thanks Group Problem 2 SU Company makes two products: Standard and Unique. The Standard product line is a high volume line and the Unique line is a low volume, specialized product. Assume the overhead costs from service departments have gone through a stage 1 allocation. SU currently uses a machine hour basis to allocate indirect manufacturing costs to its product line, but is curious about Activity Based Costing. There current cost management system already provides the following...
c. assigns activity cost pools to products and services, then allocates overhead back to the activity cost pools. d. allocates overhead directly to products and services based on activity levels e. none of these answers are correct. 21. Which of the following has the weakest linkage between activity and cost driver? Activity Machine setup Machine maintenance Lighting on shop floor Quality control Manual cloth making Cost Driver Number of setups Book value of machines Number of kilowatt-bours Square feet of...
Question 2 Grafton Ltd produces three products: X, Y and Z. The company has been using a single direct labour cost percentage to allocate overhead costs to products. Recently, managers of Grafton have noticed that, due to increasing overbeads and loss of market share, the current costing system is in need of replacement. A specific team has been charged with the responsibility of developing a new system of costing based on activities. Production information is as follows: Production volume Selling...
[The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Odds Ends Production quantity 1,000 units 5,000 units Direct material $ 40 $ 60 Direct labor (not including setup time) 30 (2 hr. at $15) 45 (3 hr. at $15) Manufacturing overhead 96 (2 hr. at $48) 144 (3 hr. at $48) Total cost...