Question

Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the timeline below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%.

0 1 2 3 4
Project A -1,140 620 390 210 260
Project B -1,140 220 325 360 710

What is Project A's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.

$  

What is Project B's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.

$  

If the projects were independent, which project(s) would be accepted?

-Select- Neither Project A Project B Both projects A and B

If the projects were mutually exclusive, which project(s) would be accepted?

Please show your work so I will know how to work the problem!!

0 0
Add a comment Improve this question Transcribed image text
Answer #1

NPV = -initial investment + PV of future cash flows

Present value = Future value/(1+i)^n

i = interest rate per period

n= number of periods

=>

NPV of A = -1140 + 620/1.08 + 390/1.08^2 + 210/1.08^3 + 260/1.08^4

= 126.25

NPV of B = -1140 + 220/1.08 + 325/1.08^2 + 360/1.08^3 + 710/1.08^4

= 149.99

Both projects, Since NPV of A and B are positive

Project B , when mutually exclusive, since it has higher NPV

Add a comment
Know the answer?
Add Answer to:
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects after tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC 7. Project A -910 620 335 270 320...

  • Quantitative Problemi Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problemi Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects after-tax cash flows are shown on the timeline below. Depreciation, salvage values, met operating working capital requirements, and tax effects are linduded in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 7% Project A Project -1,190 -1,190 700 300 350 2...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC IS 7% 320 Project A Project B -1,120 -1,120...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 10%. 690 320 Project A Project B -1,100...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 7%. 3 Project A -1,020 670 310 240...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 7%. 1 2 4. Project A Project B...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%. 0 1 2 3 4 Project A...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 9%. 0 1 2 3 4 Project A...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 7%. 0 1 2 3 4 Project A...

  • Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...

    Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%. 0 2 3 4 190 240 Project...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT