Question

Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the...

Problem 10-14 Measures of Internal Business Process Performance [LO10-3]

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations.

Month
1 2 3 4
Throughput time (days) ? ? ? ?
Delivery cycle time (days) ? ? ? ?
Manufacturing cycle efficiency (MCE) ? ? ? ?
Percentage of on-time deliveries 91 % 86 % 83 % 79 %
Total sales (units) 3,210 3,072 2,915 2,806

Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:

Average per Month (in days)
1 2 3 4
Move time per unit 0.4 0.3 0.4 0.4
Process time per unit 2.1 2.0 1.9 1.8
Wait time per order before start of production 16.0 17.5 19.0 20.5
Queue time per unit 4.3 5.0 5.8 6.7
Inspection time per unit 0.6 0.7 0.7 0.6


Required:

1-a. Compute the throughput time for each month.

1-b. Compute the delivery cycle time for each month.

1-c. Compute the manufacturing cycle efficiency (MCE) for each month.

2. Evaluate the company’s performance over the last four months.

3-a. Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE.

3-b. Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Ans. Throughput Time Delivery Cycle Manufacturing Cycle
Months Time Efficiency
1 7.4 days 23.4 days 28.4%
2 8 days 25.5 days 25.00%
3 8.8 days 27.8 days 21.59%
4 9.5 days 30 days 18.95%
*Calculations for 1 a, b, c are shown below:
Ans. 1 a Throughput time = Move time + Process time + Queue time + Inspection time
Months
Particulars 1 2 3 4
Move time per unit 0.4 0.3 0.4 0.4
Process time per unit 2.1 2 1.9 1.8
Inspection time per unit 0.6 0.7 0.7 0.6
Queue time 4.3 5 5.8 6.7
Total (Throughput Time) 7.4 days 8 days 8.8 days 9.5 days
Ans. 1 b Manufacturing cycle efficiency = Process time or value added time / Throughput time * 100
Months
1 2.1 / 7.4 * 100 28.4%
2 2 / 8 * 100 25.00%
3 1.9 / 8.8 * 100 21.59%
4 1.8 / 9.5 * 100 18.95%
Ans. 1 c Delivery cycle time = Throughput time + Wait time per order before start of production
Months
1 7.4 + 16 23.4 days
2 8 + 17.5 25.5 days
3 8.8 + 19 27.8 days
4 9.5 + 20.5 30 days
Ans. 2 Throughput time Favorable trends
Manufacturing cycle efficiency Unfavorable trends
Delivery cycle time Favorable trends
*Throughput time and delivery cylce time are increasing every month, so these are favorable trends and
Manufacturing cycle efficiency is an unfavorable trend as it is decreasing every month.
Ans. 3 Month 5 Month 6
Throughput time 2.8 days 2.2 days
Manufacturing cycle efficiency (MCE) 64.29% 81.82%
*Calculations:
Ans. 3 a Month 5 :
Throughput time:
Move time per unit 0.4
Process time per unit 1.8
Inspection time per unit 0.6
Total 2.8 days
MCE (manufacturing cycle efficiency) = Process time / Throughput time * 100
1.8 / 2.8 * 100
64.29%
Ans. 3 b Month 6 :
Throughput time:
Move time per unit 0.4
Process time per unit 1.8
Total 2.2 days
MCE (manufacturing cycle efficiency) = Process time / Throughput time * 100
1.8 / 2.2 * 100
81.82%
Add a comment
Know the answer?
Add Answer to:
Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the...

    Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations....

  • Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the...

    Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations....

  • Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the...

    Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations....

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations, Month 34 Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month ? Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 ? Throughput time (days) Delivery...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • JUST QUESTION #3 PLEASE DataSpan, Inc., automated its plant at the start of the current year...

    JUST QUESTION #3 PLEASE DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month m n Throughput time...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT