will thumbs up please show all work Please draw the AON diagram using the dependency matrix below Predecessor activity (upstream) Successor activity (downstream)
A large playground for the new town square in Celebration, Florida, is in the planning stages. Here are the six activities to be completed. Activity Hours Needed Immediate Predecessor(s) Planning(A) 20 - Buying Supplies(B) 60 Planning(A) Digging/Grading(C ) 100 Planning(A) Sawing lumber(D) 30 Buying Supplies(B) Placing lumber(E ) 20 ...
4. Draw network for the following activities. Calculate EET and LET for all the events Activity PrecedingNil activi Duration BC&E D & F 10 ays 5. A construction project involves the following activities. Draw the network diagram. Mark the critical path. Calculate all the event times, activity times and the floats Activity PrecedingNil activi Duration Nil BC,DE 18 12 ays
a. Draw the network diagram.b. Calculate the slack for each activity and determine the critical path. How long will the project take?
Draw an Activity diagram and Sequence diagram for Sending a Complaint {Trigger: The use-case will be initialized when the user presses the “File a Complaint” button in the account page. Normal Flow: 1- The user indicates that they want to file a complaint. 2- The user writes the ID of the order and the description of their complaint. 3- The user...
NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the total project duration. Feel free to verify your answer using MS Project or a similar tool. Activity Dependency Activity Duration (weeks) A B None None AB B F G H 8 9 DE F, G, HI 7 8 5 Draw the Network Diagram using...
How does lift change with altitude if a constant AOA and airspeed are held? (provide specific examples) How does lift change with airspeed if a constant AOA and altitude are held? (provide specific examples)
93 Question 47 2.75 points Save Answer Exhibit 14.3 The following questions are based on the information below. An investor is considering 4 investments, A, B, C and leaving his money in the bank. The payoff from each investment is a function of the economic climate over the next 2 years. The economy can expand or decline. The following payoff...
The following info is available for drawing a PERT network using AOA. *(More than one answer may be selected)* Activity Immediate Predecessors Activity Duration (days) A -- 10 B -- 13 C A 12 D B 15 E A 13 F C 16 G D,E 10 H G,F 5 a. the critical path includes: B, D, G, and H. b....
1. Draw the network diagram Precedences and Durations for a Seven Activity Project Activity Description Predecessors Duration Preliminary design Evaluation of design Contract negotiation Preparation of fabrication plantC Final design Fabrication of Product D B, C D, E 12 G Shipment of Product to ownerF