Problem

The developer of a 40-story high-rise office building desires the shortest possible constr...

The developer of a 40-story high-rise office building desires the shortest possible construction time. What delivery method would be best?

a. Design/bid/build

b. Design/build

c. Construction project management

d. All of the above

e. Choices b and c only