Problem

Data Screen Corporation is a highly automated manufacturing firm. The vice president of fi...

Data Screen Corporation is a highly automated manufacturing firm. The vice president of finance has decided that traditional standards are inappropriate for performance measures in an automated environment. Labor is insignificant in terms of the total cost of production and tends to be fixed, material quality is considered more important than minimizing material cost. and customer satisfaction is the number one priority. As a result. production and delivery performance measures have been chosen to evaluate performance. The following information is considered typical of the time involved to complete and ship orders.

Waiting time:

 

From order being placed to start of production.

8.0 days

From start of production to completion

7.0 days

Inspection time

1.5 days

Processing time

3.0 days

Move time

2.5 days

Required:

1. Calculate the manufacturing cycle efficiency.

2. Calculate the delivery cycle time.

Step-by-Step Solution

Request Professional Solution

Request Solution!

We need at least 10 more requests to produce the solution.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the solution will be notified once they are available.
Add your Solution
Textbook Solutions and Answers Search