A drainage basin has a time of concentration of 8 hr and produces a peak Q of 4,032 cfs for a 10-hr storm with a net intensity of 2 in./hr. Determine the peak flow rate and the time base (duration) of the direct surface runoff for a net rain of 4 in./hr lasting (a) 12 hr, (b) 8 hr, and (c) 4 hr. State any assumptions used.