Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost. (i.e., Calculate the minimum direct cost when project is finished in 13 days, 12 days, 11 days, as well as 10 days.)
Note: Choose B instead of C and E (equal costs) because it is usually smarter to crash early rather than late AND one activity instead of two activities
Summary
Step | Duration | Activity rashed (days crash) | Direct cost |
0 | 13 | - | 1000 |
1 | 12 | D(1) | 1040 |
2 | 11 | B(1) | 1140 |
3 | 10 | C(1), E(1) | 1240 |
Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what acti...
Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost. (i.e., Calculate the minimum direct cost when project is finished in 13 days, 12 days, 11 days, as well as 10 days.) Note: Choose B instead of C and E (equal costs) because it is usually smarter to...
Use the information below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point or the best cost value for this network. For each move identify what activity(s) should be crashed and the adjusted total cost. Total direct cost is $1000, total indirect cost is $800 and each time-unit reduction (cost gain) is $50. Activity Crash Cost per unit-time) Normal Normal Maximum time cost Crash Time 100 150 200 200...