Question

Use the information below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach
Activity Normal Maximum Normal cost 100 I crash Crash Cost per unit-time) 110 150 200 200 200 190 Total Direct Cost Activitie
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Step 1: Identify the alternative paths and Critical path. Critical path is the path of longest duration in the network A-B-D-

Normal Time = 13

Total Direct Cost =1000

1)

Time = 12

Total Direct Cost =1050

Activities Changed: C

2)

Time = 11

Total Direct Cost =1120

Activities Changed: E

3)

Time = 10

Total Direct Cost =1210

Activities Changed: F

4)

Time = 9

Total Direct Cost =1340

Activities Changed: D, E

Add a comment
Know the answer?
Add Answer to:
Use the information below to compress one-time unit per move using the least cost method. Reduce...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use the information contained below to compress one time unit per move using the least cost...

    Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost. (i.e., Calculate the minimum direct cost when project is finished in 13 days, 12 days, 11 days, as well as 10 days.) Note: Choose B instead of C and E (equal costs) because it is usually smarter to...

  • Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what acti...

    Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost. (i.e., Calculate the minimum direct cost when project is finished in 13 days, 12 days, 11 days, as well as 10 days.)Note: Choose B instead of C and E (equal costs) because it is usually smarter to crash...

  • Chapter 9 Reducing Project Durarion 327 7. Use the information contained below to compress one time...

    Chapter 9 Reducing Project Durarion 327 7. Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is $2.000 and there is a savings of $100 per time unit reduced. Calculate the total direct, indirect, an graph. What is the optimum cost-time schedule for the project? Note: The correct normal project duration and total direct cost are provi ded. Normal Cost 200 1000 800 1000...

  • Assume that Indirect project costs are $75,000 per week Crash the network (one week at a time) un...

    Assume that Indirect project costs are $75,000 per week Crash the network (one week at a time) until you reach the optimum cost-time point. Document your crashes clearly. d. What is the project length at the optimum point? MGMT 4143 Ch 9 HomeworkDue 3/27, 9pm NOTE due date is changed All work must be done in Excel Put each problem on a separate worksheet tab Label the worksheet tabs, put your name on each worksheet. Note: Crash the networks as...

  • A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr...

    A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr 3 1 А B с D E 7 3 6 3 2 $300 $250 $400 $200 $300 4 2 1 ive the crash cost per day per activity. (5 points) Search 36_WA_Homework_EV_Problems_v1 (1) - Protected View - Saved References Mailings Review View Help PROBLEM 1 Use the network diagram below and the additional information provided to answer the corresponding questions. (10 points) B E...

  • Problem #3 (25 points) For the construction project whose network diagram is shown below, a time-cost...

    Problem #3 (25 points) For the construction project whose network diagram is shown below, a time-cost optimization procedure is required to determine the shortest duration and its corresponding lowest cost. Activity ID ES Darwin EF LS UF 1. Fill in values for the normal cost and crashed cost in the table below. Activities A and B already have costs associated with them. For activities through I do not use the same costs for any activity 2. Calculate the slope and...

  • 5. Imagine that you are in charge of planning a short course for executives wishing to...

    5. Imagine that you are in charge of planning a short course for executives wishing to upgrade their Operations Research skills. The following list of activities is involved: Cost Per ImmediateNormal DescriptionPredecessors (days) Crash Time (days)Reduction Day of Time Activity A Develop course outline 4 S50 Arrange speakers $100 Identify potential locations $150 Choose location 4 $150 Arrange travel for B, D speakers Final confirmation of $200 eakers Advertise course B, D Take rescrvations Arrange welcome party F, H $100...

  • 15. Given the following project (all times are in days): Pre- Normal Normal Crash Crash Activity...

    15. Given the following project (all times are in days): Pre- Normal Normal Crash Crash Activity decessor Time Cost Time Cost $50 200 160 a, c a, c 290 100 180 (a) Draw the network and find the critical path, time, and (b) Calculate the crash cost-per-day (all activities may be (c) Find the optimal way of getting an 18-day delivery (d) Find the optimal way of getting a 16-day delivery (e) Calculate the shortest delivery time for the project....

  • Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days....

    Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days. Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost A None 4 3 202 383 B A 5 3 303 601 C A 1 1 190 285 D B and C 5 4 509 543 E D 4 2 502 898 What is the total time of this project? Please give your answer in days What are the total normal cost of...

  • If you would like to reduce the overall completion time of the project by 1 day,...

    If you would like to reduce the overall completion time of the project by 1 day, which activity (A, B, C, D, E, F, G, or H) should be crashed? The list of activities of a data analysis project, their precedence relationships, and their activity times (in number of days) are given in the table below. Activity ID Predecessors Activity Time (Days) A 3 B А 4 с B 2 D с 5 E B 7 F с 2 G...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT