Question

A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr 3 1 А B с D E 7 3 6 3 2 $300 $250 $400 $200 $300 4
Search 36_WA_Homework_EV_Problems_v1 (1) - Protected View - Saved References Mailings Review View Help PROBLEM 1 Use the netw
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answers are attached below

Answer (a) Statement showing Crash Cost per day per Activity Crash Time Normal Time Crash Cost - Crash Time per day f = (d-e)Crash Activity B by 1 day Crashing No 2 Common Activity Other than Common E Activity, Crash Cost is $250 per day Activity A b

Answerc Cost of the Project after Crashing Activity Normal Cost A 2,100 B 500 С 2,400 D 600 E 300 Normal Cost 5,900 Crash Cos

Add a comment
Know the answer?
Add Answer to:
A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Path A -> B -> F C-> D -> E ----^ Activity Normal Time Crash Time...

    Path A -> B -> F C-> D -> E ----^ Activity Normal Time Crash Time Crash Cost per day A 6 6 --- B 10 8 $100 C 5 4 $300 D 4 1 $700 E 9 7 $500 F 2 1 $650 a.     Determine which activities should be crashed to shorten the project by 3 days. b.     What is the associated crash cost?

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • Lecture Exercise #13 Project Crashing Time (weeks) Cost Activity Predecessori s) Normal Crash Normal Crash A...

    Lecture Exercise #13 Project Crashing Time (weeks) Cost Activity Predecessori s) Normal Crash Normal Crash A None 3 2 1000 1600 B None 2 1 2000 2700 C None 1 1 300 300 D A 7 3 1300 1600 E B 6 3 850 1000 F с 2 1 4000 5000 D, E 2000 G 4 2 1500 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity...

  • 15. Given the following project (all times are in days): Pre- Normal Normal Crash Crash Activity...

    15. Given the following project (all times are in days): Pre- Normal Normal Crash Crash Activity decessor Time Cost Time Cost $50 200 160 a, c a, c 290 100 180 (a) Draw the network and find the critical path, time, and (b) Calculate the crash cost-per-day (all activities may be (c) Find the optimal way of getting an 18-day delivery (d) Find the optimal way of getting a 16-day delivery (e) Calculate the shortest delivery time for the project....

  • Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None...

    Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None None B Cost Normal Crash 1000 1600 2000 2700 300 300 1300 1600 2 1 С 1 1 D A 7 3 E 6 3 B с 1000 5000 F 2 850 4000 1500 NA G D. E 4 2000 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity should you...

  • For the following project: Normal Time Crash Time Normal Cost Crash Cost Immediate (weeks 4. Activity...

    For the following project: Normal Time Crash Time Normal Cost Crash Cost Immediate (weeks 4. Activity Predecessor (weeks) $2,600 $2,800 $2,000 $2,200 $500 $2,300 $900 $3,000 $500 $2,600 $1,200 $4,200 $1,400$2,000 4 D, E How long will the project take? What is the total cost to complete the project in normal time? If the project is to be shortened by 1 week, which activity will be reduced and how much will the cost be increased? What is the maximum time...

  • If you would like to reduce the overall completion time of the project by 1 day,...

    If you would like to reduce the overall completion time of the project by 1 day, which activity (A, B, C, D, E, F, G, or H) should be crashed? The list of activities of a data analysis project, their precedence relationships, and their activity times (in number of days) are given in the table below. Activity ID Predecessors Activity Time (Days) A 3 B А 4 с B 2 D с 5 E B 7 F с 2 G...

  • Question 6 - 8 Activity Depends on А B C D E F G A A...

    Question 6 - 8 Activity Depends on А B C D E F G A A А B C,D D, E, F Duration (Days) Normal Crash 5 4 7 5 8 5 11 8 6 4 4 3 7 5 Cost ($) Normal Crash 500 620 350 500 800 920 1000 1300 600 750 420 500 700 1000 6. Draw the node network for the above project using the following template. For each activity, show the computed value of early...

  • QUESTION 27 What is the cost of crashing the project represented in the table below, by...

    QUESTION 27 What is the cost of crashing the project represented in the table below, by 3 days? Immediate Normal Crash Normal Crash Activity Predecessors Time/Days Time/Days Cost Cost А 3 2 $200 $500 B А 3 2 $350 $550 С А 2 1 $300 $250 D B&C 3 $500 $550 E С 2 $500 $900 F D&E . $500 $1,000 NN $150 $450 $550 $2450 $2750 QUESTION 1 According to Michael Porter, the primary activities in a value chain...

  • What is the minimum cost of crashing the following project that Roger Solano manages at Slippery...

    What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4​ days? A)By how many days should each activity be crashed to reduce the project completion time by 4​ days? Fill in the table below. ​(Enter your responses as whole numbers.​) B) The total cost of crashing the project by 4 days is $. (Enter your response as a whole number.) Normal Crash Time Normal Total Cost Activity Time (days) (days)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT