Solution:
The below table shows about listing allowable Crash time and Crash cost per unit time:
Act.ID | Predecess | Normal time | Normal cost |
Maximum crash time |
Crash cost (slope) |
ES | LS | EF | LF | Slack | Successor | Crash time remaining |
---|---|---|---|---|---|---|---|---|---|---|---|---|
A | 2 | $ 200 | 0 | $ 0 | 0 | 0 | 2 | 2 | 0 | B | 0 | |
B | A | 4 | $ 1,000 | 1 | $ 50 | 2 | 2 | 6 | 6 | 0 | C,D | 0 |
C | B | 5 | $ 800 | 2 | $ 200 | 6 | 6 | 11 | 11 | 0 | E | 0 |
D | B | 5 | $ 1,000 | 2 | $ 200 | 6 | 6 | 11 | 11 | 0 | E | 0 |
E | C,D | 3 | $ 800 | 1 | $ 100 | 11 | 11 | 14 | 14 | 0 | F,G | 0 |
F | E | 5 | $ 1,000 | 1 | $ 40 | 14 | 14 | 19 | 19 | 0 | H | 1 |
G | E | 4 | $ 1,000 | 1 | $ 40 | 14 | 15 | 18 | 19 | 1 | H | 1 |
H | F,G | 1 | $ 200 | 0 | $ 0 | 19 | 19 | 20 | 20 | 0 | 0 | |
total=6,000 |
POSSIBLE PATHS |
DURATION | |
A-B-C-E-F-H | 20 | <-Critical path |
A-B-C-E-G-H | 19 | |
A-B-D-E-F-H | 20 | <-Critical path |
A-B-D-E-G-H | 19 |
Normal Time = 20
Total Direct cost = $ 6,000
saving/Time unit reduced = $ 100
Project crashing using least cost method:
Iteration |
Activity Crashed |
Crash Time |
Path-1 A-B-C-E-F-H |
Path-2 A-B-C-E-G-H |
Path-3 A-B-D-E-F-H |
Path-4 A-B-D-E-G-H |
Project Duration | Activity crash cost | Cumulative crash | Total Direct cost | Indirect cost | Total Cost |
---|---|---|---|---|---|---|---|---|---|---|---|---|
0 | 20 | 19 | 20 | 19 | 20 | 6,000 | 2,000 | 8,000 | ||||
1 | F | 1 | 19 | 19 | 19 | 19 | 19 | 40 | 40 | 6,040 | 1,900 | 7,940 |
2 | B | 1 | 18 | 18 | 18 | 18 | 18 | 50 | 90 | 6,090 | 1,800 | 7,890 |
3 | E | 1 | 17 | 17 | 17 | 17 | 17 | 100 | 190 | 6,190 | 1,700 | 7,890 |
4 | C | 2 | 15 | 15 | 17 | 17 | 17 | 400 | 590 | 6,590 | 1,700 | 8,290 |
5 | D | 2 | 15 | 15 | 15 | 15 | 15 | 400 | 990 | 6,990 | 1,500 | 8,490 |
Optimum Cost - Time Schedule for the Project is:17 ,here both time and cost are lowest.
Time Period = 17
Total Cost = 7,890
Chapter 9 Reducing Project Durarion 327 7. Use the information contained below to compress one time...
Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost. (i.e., Calculate the minimum direct cost when project is finished in 13 days, 12 days, 11 days, as well as 10 days.) Note: Choose B instead of C and E (equal costs) because it is usually smarter to...
Use the information below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point or the best cost value for this network. For each move identify what activity(s) should be crashed and the adjusted total cost. Total direct cost is $1000, total indirect cost is $800 and each time-unit reduction (cost gain) is $50. Activity Crash Cost per unit-time) Normal Normal Maximum time cost Crash Time 100 150 200 200...
4. Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15 time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is this cost? Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost WNUNUNAW OWLOI- 100 60 200 200 $730 Initial project...
Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost. (i.e., Calculate the minimum direct cost when project is finished in 13 days, 12 days, 11 days, as well as 10 days.)Note: Choose B instead of C and E (equal costs) because it is usually smarter to crash...
Q.3. Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are S410 (19 time units), S360 (18), S310 (17), and $260 (16), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is this cost? Activity Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost 20 60 50 60 70 50 100 90 50 S470 10...
Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1. If the indirect costs for each duration is as follows, compute the direct and total cost for each duration. What is the optimum cost-time schedule? Indirect cost 27 weeks – RM 350 26 weeks – RM 270 25 weeks – RM 160 24 weeks – RM 100 12 weeks – RM 70 (12...
Assume that Indirect project costs are $75,000 per week Crash the network (one week at a time) until you reach the optimum cost-time point. Document your crashes clearly. d. What is the project length at the optimum point? MGMT 4143 Ch 9 HomeworkDue 3/27, 9pm NOTE due date is changed All work must be done in Excel Put each problem on a separate worksheet tab Label the worksheet tabs, put your name on each worksheet. Note: Crash the networks as...
Question 1: I)-What is the normal cost of this project? II)-What is the cost of the project after 2 days shortening? III)-What is the crashing cost per day for activity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 3 1.8 12. 19 10,13 B 7 1,8 13.20 0,1 1,7 8.15 20,25 15.20 F...
what is the normal cost of this project? what is the cost of the project after 2 days shortening? what is the crashing cost per day for avtivity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...
Question 16 4 points Save Answe The following provides information about a project, including a list of activities and precedence relationships, activity durations (normal and "crash" times), direct activity costs (normal and "crash"), indirect costs for the project, as well as calculated crash costs/day and the maximum amount that each activity can be shortened (crashed) by. There are no penalty costs for this project. Total project cost (using normal times), a network diagram, and the four paths and durations have...