Question

Chapter 9 Reducing Project Durarion 327 7. Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is $2.000 and there is a savings of $100 per time unit reduced. Calculate the total direct, indirect, an graph. What is the optimum cost-time schedule for the project? Note: The correct normal project duration and total direct cost are provi ded. Normal Cost 200 1000 800 1000 800 1000 1000 200 Normal Time Act. Crash Cost (Slope)Maximum Crash Time 50 200 200 100 40 40 Project duration 20 HDirect cost 6,000 Indirect cost 2000 Total cost8000

1 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

The below table shows about listing allowable Crash time and Crash cost per unit time:

Act.ID Predecess Normal time Normal cost

Maximum

crash time

Crash cost

(slope)

ES LS EF LF Slack Successor Crash time remaining
A 2 $ 200 0 $ 0 0 0 2 2 0 B 0
B A 4 $ 1,000 1 $ 50 2 2 6 6 0 C,D 0
C B 5 $ 800 2 $ 200 6 6 11 11 0 E 0
D B 5 $ 1,000 2 $ 200 6 6 11 11 0 E 0
E C,D 3 $ 800 1 $ 100 11 11 14 14 0 F,G 0
F E 5 $ 1,000 1 $ 40 14 14 19 19 0 H 1
G E 4 $ 1,000 1 $ 40 14 15 18 19 1 H 1
H F,G 1 $ 200 0 $ 0 19 19 20 20 0 0

total=6,000

POSSIBLE PATHS

DUR​ATION
A-B-C-E-F-H 20 <-Critical path
A-B-C-E-G-H 19
A-B-D-E-F-H 20 <-Critical path
A-B-D-E-G-H 19

Normal Time = 20

Total Direct cost = $ 6,000

saving/Time unit reduced = $ 100

Project crashing using least cost method:

Iteration

Activity

Crashed

Crash Time

Path-1

A-B-C-E-F-H

Path-2

A-B-C-E-G-H

Path-3

A-B-D-E-F-H

Path-4

A-B-D-E-G-H

Project Duration Activity crash cost Cumulative crash Total Direct cost Indirect cost Total Cost
0 20 19 20 19 20 6,000 2,000 8,000
1 F 1 19 19 19 19 19 40 40 6,040 1,900 7,940
2 B 1 18 18 18 18 18 50 90 6,090 1,800 7,890
3 E 1 17 17 17 17 17 100 190 6,190 1,700 7,890
4 C 2 15 15 17 17 17 400 590 6,590 1,700 8,290
5 D 2 15 15 15 15 15 400 990 6,990 1,500 8,490

Optimum Cost - Time Schedule for the Project is:17 ,here both time and cost are lowest.

Time Period = 17

Total Cost = 7,890

Add a comment
Know the answer?
Add Answer to:
Chapter 9 Reducing Project Durarion 327 7. Use the information contained below to compress one time...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use the information contained below to compress one time unit per move using the least cost...

    Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost. (i.e., Calculate the minimum direct cost when project is finished in 13 days, 12 days, 11 days, as well as 10 days.) Note: Choose B instead of C and E (equal costs) because it is usually smarter to...

  • Use the information below to compress one-time unit per move using the least cost method. Reduce...

    Use the information below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point or the best cost value for this network. For each move identify what activity(s) should be crashed and the adjusted total cost. Total direct cost is $1000, total indirect cost is $800 and each time-unit reduction (cost gain) is $50. Activity Crash Cost per unit-time) Normal Normal Maximum time cost Crash Time 100 150 200 200...

  • 4. Given the data and information that follow, compute the total direct cost for each project...

    4. Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15 time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is this cost? Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost WNUNUNAW OWLOI- 100 60 200 200 $730 Initial project...

  • Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what acti...

    Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost. (i.e., Calculate the minimum direct cost when project is finished in 13 days, 12 days, 11 days, as well as 10 days.)Note: Choose B instead of C and E (equal costs) because it is usually smarter to crash...

  • Q.3. Assume the network and data that follow. Compute the total direct cost for each project...

    Q.3. Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are S410 (19 time units), S360 (18), S310 (17), and $260 (16), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is this cost? Activity Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost 20 60 50 60 70 50 100 90 50 S470 10...

  • Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity...

    Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1. If the indirect costs for each duration is as follows, compute the direct and total cost for each duration. What is the optimum cost-time schedule? Indirect cost 27 weeks – RM 350 26 weeks – RM 270 25 weeks – RM 160 24 weeks – RM 100 12 weeks – RM 70 (12...

  • Assume that Indirect project costs are $75,000 per week Crash the network (one week at a time) un...

    Assume that Indirect project costs are $75,000 per week Crash the network (one week at a time) until you reach the optimum cost-time point. Document your crashes clearly. d. What is the project length at the optimum point? MGMT 4143 Ch 9 HomeworkDue 3/27, 9pm NOTE due date is changed All work must be done in Excel Put each problem on a separate worksheet tab Label the worksheet tabs, put your name on each worksheet. Note: Crash the networks as...

  • Question 1: I)-What is the normal cost of this project? II)-What is the cost of the...

    Question 1: I)-What is the normal cost of this project? II)-What is the cost of the project after 2 days shortening? III)-What is the crashing cost per day for activity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 3 1.8 12. 19 10,13 B 7 1,8 13.20 0,1 1,7 8.15 20,25 15.20 F...

  • what is the normal cost of this project? what is the cost of the project after...

    what is the normal cost of this project? what is the cost of the project after 2 days shortening? what is the crashing cost per day for avtivity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...

  • Question 16 4 points Save Answe The following provides information about a project, including a list...

    Question 16 4 points Save Answe The following provides information about a project, including a list of activities and precedence relationships, activity durations (normal and "crash" times), direct activity costs (normal and "crash"), indirect costs for the project, as well as calculated crash costs/day and the maximum amount that each activity can be shortened (crashed) by. There are no penalty costs for this project. Total project cost (using normal times), a network diagram, and the four paths and durations have...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT