Question

QUESTION 9 A process of examining the differences between actual and budgeted costs and describing them in terms of the amoun
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Option E is the answer

Cost variance analysis is the management control system which finds and corrects the differences between the actual and budgeted costs.

Comment if you face any issues

Add a comment
Know the answer?
Add Answer to:
QUESTION 9 A process of examining the differences between actual and budgeted costs and describing them...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A Variance A. is the difference between variable cost value, or standard, and the indirect (realized)...

    A Variance A. is the difference between variable cost value, or standard, and the indirect (realized) value. Variance analysis examines differences between last years and actual amounts with the goal of finding out why things went either badly or well. B. between unit price and variable cost rate, or per unit revenue minus per unit variable cost. Thus, contribution margin is the per unit dollar amount available to cover an organization’s fixed costs and then to contribute to profit. C....

  • Question 17 )The sales volume variance is the differernc between the ? A) Actual results and...

    Question 17 )The sales volume variance is the differernc between the ? A) Actual results and the expected results in the flexible budget for the actual units sold B)Expected results in the flexible budget for the actual units sold and the static budget c)Static budget and actual amounts due to differences in sales price d)flexible budget and static budget due to differences in fixed costs Question 18 )Generals Co.can further process Product B to Product product A. product B currently...

  • Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...

    Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 70,000 units of product were as follows: Standard Costs Actual Costs Direct materials 189,000 lbs. at $6.00 187,100...

  • 4. A flexible budget performance report compares the differences between: a. Actual performance and budgeted performance...

    4. A flexible budget performance report compares the differences between: a. Actual performance and budgeted performance based on actual sales volume. b. Actual performance over several periods. c. Budgeted performance over several periods. d. Actual performance and budgeted performance based on budgeted sales volume. e. Actual performance and standard costs at the budgeted sales volume.

  • You have been assigned for reviewing the actual and budgeted figures of the variable manufacturing overhead...

    You have been assigned for reviewing the actual and budgeted figures of the variable manufacturing overhead of straight umbrellas at Ombrelloni Felici (OF). The management at OF argues there are no evident issues with the variable manufacturing overhead budget as the static-budget variance is often favourable, which proves the budgeting process works quite well. The management at OF also argues the employees at the production line of straight umbrellas are always highly efficient because of the consistently favourable efficiency variances....

  • Question 17 )The sales volume variance is the differernc between the ? A) Actual results and...

    Question 17 )The sales volume variance is the differernc between the ? A) Actual results and the expected results in the flexible budget for the actual units sold B)Expected results in the flexible budget for the actual units sold and the static budget c)Static budget and actual amounts due to differences in sales price d)flexible budget and static budget due to differences in fixed costs

  • Question 17 )The sales volume variance is the differernc between the ? A) Actual results and...

    Question 17 )The sales volume variance is the differernc between the ? A) Actual results and the expected results in the flexible budget for the actual units sold B)Expected results in the flexible budget for the actual units sold and the static budget c)Static budget and actual amounts due to differences in sales price d)flexible budget and static budget due to differences in fixed costs

  • Question 17 )The sales volume variance is the differernc between the ? A) Actual results and the expected results in t...

    Question 17 )The sales volume variance is the differernc between the ? A) Actual results and the expected results in the flexible budget for the actual units sold B)Expected results in the flexible budget for the actual units sold and the static budget c)Static budget and actual amounts due to differences in sales price d)flexible budget and static budget due to differences in fixed costs Question 18 )Generals Co.can further process Product B to Product product A. product B currently...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • Comparison of Actual and Budgeted Operating Income EXHIBIT 14.1 SCHMIDT MACHINERY COMPANY Analysis of Operating Income...

    Comparison of Actual and Budgeted Operating Income EXHIBIT 14.1 SCHMIDT MACHINERY COMPANY Analysis of Operating Income For October 2019 (1) (2) (3) Variances Actual Operating Income Master (Static) Budget 220U Units 780 1,000 $ 160,400U 100% $639,600 100% Sales $800,000 Variable costs 99.050F 350,950 55 450.000 56 $350,000 Contribution margin $288,650 45% 44% $ 61,350U 150.000 *** 160.650 Fixed costs 25 19 10.650U $128,000 20% $ Operating income $200,000 25% 72,000U *U denotes an unfavorable effect on operating income. *F...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT