Question

Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The con4. Now, ignoring the ABC results, calculate the plantwide overhead rate, based on oven hours. Round to the nearest cent. $ 17

0 0
Add a comment Improve this question Transcribed image text
Answer #1
2) Overhead to be assigned to Fudge
Setting up cost ($42 per hour *7200 hours ) $          3,02,400
Other Overhead ($165 per hour *7000 hours ) $       11,55,000
Total $       14,57,400
3) Unit overhead cost assigned
= total overhead assigned / total units
=$1457400/8000 units
=$182.18
4) Plantwide overhead rate
= Total Overheads / total oven hours
=($378000+9240000)/(7000+49000)
=$171.75 per hour
5) total overhead to be assigned to fudge
=$171.75*7000 hour
=$1202250
6a) different treatment for setup
b differece in total overhead assigned
=$1457400-1202250
=$255150
Kindly give a positive rating if you are satisfied with this solution and please ask if you have any queres.
Add a comment
Know the answer?
Add Answer to:
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...

    Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $230,000 Other overheard $1,240,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 4,000 1,000 Oven hours 1,000 7,000 Required: Round your answers to the...

  • Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...

    Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $420,000 Other overheard $6,400,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 5,600 1,400 Oven hours 5,000 35,000 Required: Round your answers to the...

  • Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...

    Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $754,000 Other overheard $2,912,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 10,400 2,600 Oven hours 2,600 18,200 Required: Round your answers to the...

  • eBook Calculator Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC)....

    eBook Calculator Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $572,000 Other overheard $5,600,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 445,000 8,000 10,400 Setup hours 2,600 Oven hours 5,000 35,000 Required: Round your answers...

  • eBook Calculator Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC)....

    eBook Calculator Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $986,000 Other overheard $6,264,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 13,600 3,400 Oven hours 5,800 40,600 Required: Round your answers...

  • Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs:...

    Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $1,026,000 Other overheard $4,104,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 15,200 3,800 Oven hours 3,800 26,600 Required: Round your answers to the nearest whole dollar, unless otherwise directed. 1....

  • OBJEC Exercise 5-39 Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing...

    OBJEC Exercise 5-39 Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $ 432,000 Other overhead 1,440,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. (Continued) Wellington produces two products, Fudge and Cookies. Information on each prode as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 6,400 1,600 Oven hours 1,600 8,000 Required: (Note:...

  • PLEASE GIVE STEPS FOR EACH ANSWER! THANK YOU!!! Comparing ABC and Plantwide Overhead Cost Assignments The...

    PLEASE GIVE STEPS FOR EACH ANSWER! THANK YOU!!! Comparing ABC and Plantwide Overhead Cost Assignments The Sabroso Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $270,000 Other overhead $900,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Sabroso produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 5,000 25,000 Setup hours 4,000 1,000 Oven...

  • Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs:...

    Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment Other overheard $840,000 $5,400,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Units produced Setup hours Oven hours Fudge 8,000 12,000 5,000 Cookies 145,000 3,000 35,000 How much Total Overhead is assigned to the Product Line - Fudge? Do...

  • Setting up equipment $680,000 Other overheard $4,488,000 Setting up equipment is based on setup hours, and...

    Setting up equipment $680,000 Other overheard $4,488,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 13,600 3,400 Oven hours 3,400 23,800 Required: Round your answers to the nearest whole dollar, unless otherwise directed. 1. Calculate the activity rate for (a) setting up equipment and (b) other overhead. a. Setting up...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT