Comparing ABC and Plantwide Overhead Cost Assignments
Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs:
Setting up equipment | $754,000 |
Other overheard | $2,912,000 |
Setting up equipment is based on setup hours, and other overhead
is based on oven hours.
Wellington produces two products, Fudge and Cookies. Information on
each product is as follows:
Fudge | Cookies | ||||
Units produced | 8,000 | 445,000 | |||
Setup hours | 10,400 | 2,600 | |||
Oven hours | 2,600 | 18,200 |
Required:
Round your answers to the nearest whole dollar, unless otherwise directed.
1. Calculate the activity rate for (a) setting up equipment and (b) other overhead.
a. Setting up equipment | $ per setup hour |
b. Other overhead | $ per oven hour |
2. How much total overhead is assigned to Fudge
using ABC?
$
3. What is the unit overhead assigned to Fudge
using ABC? Round to the nearest cent.
$per unit
4. Now, ignoring the ABC results, calculate the
plantwide overhead rate, based on oven hours.
$ per oven hour
5. How much total overhead is assigned to Fudge
using the plantwide overhead rate?
$
6a. The difference in the total overhead assigned to Fudge is different under the ABC system and non–ABC system because different treatment of setup costs. .
6b. What is the difference in total overhead assigned to fudge under the two methods?
$
Requirement 1 : | ||||
Activity |
Overhead | Driver | Expected Activity | Activity Rate |
Setting up equipment | $ 754,000.00 | Set Up Hours | 13000 | $ 58.00 |
Other overhead | $ 2,912,000.00 | Oven Hours | 20800 | $ 140.00 |
Requirement 2 : | ||||
Total Overhead assigned to fudge using ABC | ||||
Particulars | Amount | |||
Setting up equipment (10400*58) | $ 603,200.00 | |||
Other Overhead (2600*140) | $ 364,000.00 | |||
Total | $ 967,200.00 | |||
Requirement 3 : | ||||
Unit Overhead assigned to fudge using ABC | ||||
Particulars | Amount | |||
Setting up equipment (10400*58) | $ 603,200.00 | |||
Other Overhead (2600*140) | $ 364,000.00 | |||
Total | $ 967,200.00 | |||
Number of units | 13000 | |||
Per unit cost | $ 74.40 | |||
Requirement 4 : | ||||
Plantwide overhead rate | ||||
Total Overhead | $ 3,666,000.00 | |||
Oven Hours | 20800 | |||
Plant wide overhead rate | $ 176.25 | |||
Requirement 5 : | ||||
Total Overhead assigned to fudge using plantwide overhead rate | ||||
Particulars | Amount | |||
Oven hours | 2600 | |||
Plant wide overhead rate | $ 176.25 | |||
Total Overhead | $ 458,250.00 | |||
Requirement 6 : | ||||
Difference in overhead assigned | ||||
Overhead using ABC | $ 967,200.00 | |||
Overhead using plantwide overhead rate | $ 458,250.00 | |||
Difference in overhead assigned | $ 508,950.00 | |||
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $230,000 Other overheard $1,240,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 4,000 1,000 Oven hours 1,000 7,000 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $420,000 Other overheard $6,400,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 5,600 1,400 Oven hours 5,000 35,000 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $378,000 Other overheard $9,240,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 7,200 1,800 Oven hours 7,000 49,000 Required: Round your answers to the...
eBook Calculator Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $572,000 Other overheard $5,600,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 445,000 8,000 10,400 Setup hours 2,600 Oven hours 5,000 35,000 Required: Round your answers...
eBook Calculator Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $986,000 Other overheard $6,264,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 13,600 3,400 Oven hours 5,800 40,600 Required: Round your answers...
Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $1,026,000 Other overheard $4,104,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 15,200 3,800 Oven hours 3,800 26,600 Required: Round your answers to the nearest whole dollar, unless otherwise directed. 1....
OBJEC Exercise 5-39 Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $ 432,000 Other overhead 1,440,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. (Continued) Wellington produces two products, Fudge and Cookies. Information on each prode as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 6,400 1,600 Oven hours 1,600 8,000 Required: (Note:...
Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment Other overheard $840,000 $5,400,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Units produced Setup hours Oven hours Fudge 8,000 12,000 5,000 Cookies 145,000 3,000 35,000 How much Total Overhead is assigned to the Product Line - Fudge? Do...
PLEASE GIVE STEPS FOR EACH ANSWER! THANK YOU!!! Comparing ABC and Plantwide Overhead Cost Assignments The Sabroso Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $270,000 Other overhead $900,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Sabroso produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 5,000 25,000 Setup hours 4,000 1,000 Oven...
Setting up equipment $680,000 Other overheard $4,488,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 13,600 3,400 Oven hours 3,400 23,800 Required: Round your answers to the nearest whole dollar, unless otherwise directed. 1. Calculate the activity rate for (a) setting up equipment and (b) other overhead. a. Setting up...