Question

Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing...

Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing system. The following are the activities, budgeted total cost and cost drivers per activity for the year 20x9:

Activity

Budgeted Cost

Cost Base

Cost Base Volume

Assembly

$864585

# of DL hours

36772

Inspection

$664181

# of units

20927

Shipping

$349574

# of batches

189

Plaid Manufacturing has budgeted to produce 3,000 units of G1. G1 is manufactured in batches of 73 units and requires 16196 hours of direct labour.

What is the overhead cost per unit for product G1?

Select one:

a. $203.68

b. $626.11

c. $153.04

d. $184.01

Question 3

Not yet answered

Marked out of 1.00

Flag question

Question text

Barker Inc. has identified the following overhead costs and cost drivers fore the upcoming year:

Overhead Item

Expected Cost

Cost Driver

Expected Quantity

Setup costs

$191997

Number of setups

451

Ordering costs

117974

Number of orders

3162

Maintenance

354369

Machine hours

3677

Power

49146

Kilowatt hours

91356


The following are two of the jobs completed during the year:

Job 400

Job 401

Direct materials

$854

$1535

Direct labour

$689

$2850

Direct labour hours

48

66

Number of setups

2

5

Number of orders

5

4

Machine hours

19

26

Kilowatt hours

28

52

The company’s normal activity is 4003 direct labour hours.

If Barker used activity based costing, the total cost of Job 401 would be:

Select one:

a. $ 9197

b. $ 6663

c. $ 9019

d. $ 9169

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Question 1

Correct answer--------------a. $203.68

Working

Calculation of Activity rates
Activity Cost Pool Activity driver Overhead Cost (A) Expected Activity (B) Activity rate (A/B)
Assembly Number of DL hour $     8,64,585.00 36772 $             23.51 Per DL hour
Inspection Number of unit $     6,64,181.00 20927 $             31.74 Per unit
Shipping Number of batch $     3,49,574.00 189 $       1,849.60 Per batch

.

Cost assigned to G1
Activity name Activity Rates Activity ABC Cost
(A) (B) (A x B)
Assembly $           23.51                16,196.00 $      3,80,801.12
Inspection $           31.74                  3,000.00 $         95,213.98
Shipping $     1,849.60                        73.00 $      1,35,020.65
Total Overheads assigned $      6,11,035.74
Production               3,000.00
Overhead cost per unit $ 203.68

Question 2

Correct answer--------------a. $ 9197

Working

Direct material $                    1,535
Direct labor   $                    2,850
Overheads $                    4,812
Total Cost $                    9,197

.

Calculation of Activity rates
Activity Cost Pool Activity driver Overhead Cost (A) Expected Activity (B) Activity rate (A/B)
Setup cost Number of setup $     1,91,997.00 451 $          425.71 Per setup
Ordering cost Number of order $     1,17,974.00 3162 $             37.31 Per order
Maintenance Number of Machine hour $     3,54,369.00 3677 $             96.37 Per Machine hour
power Number of Kilowatt hour $        49,146.00 91356 $               0.54 Per Kilowatt hour

.

Cost assigned to Job 401
Activity name Activity Rates Activity ABC Cost
(A) (B) (A x B)
Setup cost $        425.71                           5.00 $           2,128.57
Ordering cost $           37.31                           4.00 $              149.24
Maintenance $           96.37                        26.00 $           2,505.74
power $             0.54                        52.00 $ 27.97
Total Overheads assigned $           4,811.52
Add a comment
Know the answer?
Add Answer to:
Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing...

    Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing system. The following are the activities, budgeted total cost and cost drivers per activity for the year 20x9: Activity Budgeted Cost Cost Base Cost Base Volume Assembly $891922 # of DL hours 34289 Inspection $657733 # of units 23317 Shipping $322225 # of batches 182 Plaid Manufacturing has budgeted to produce 3,000 units of G1. G1 is manufactured in batches of 72 units and...

  • Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing...

    Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing system. The following are the activities, budgeted total cost and cost drivers per activity for the year 20x9: Activity Budgeted Cost Cost Base Cost Base Volume Assembly $877831 # of DL hours 37167 Inspection $668988 # of units 20830 Shipping $339555 # of batches 186 Plaid Manufacturing has budgeted to produce 3,000 units of M1. M1 is manufactured in batches of 80 units and...

  • Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing...

    Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing system. The following are the activities, budgeted total cost and cost drivers per activity for the year 20x9 Activity Assembly Inspection Shipping Budgeted Cost $884406 $655248 S347388 Cost Base # of DL hours # of units # of batches Cost Base Volume 32830 22650 182 Budgeted data relating to the production of M1 for 20x9 is given below: Number of units Units per batch...

  • The following data regarding the activity-based costing system at the Company Co. is available: Base Activity...

    The following data regarding the activity-based costing system at the Company Co. is available: Base Activity Pool Machine set Budgeted Activity 2839 Budgeted Cost $23322 of setups up Orders Shipping # of orders Hours of shipping time 968 2121 $88985 $40914 In addition, prior to adopting an activity based costing system. Company Co, applied Overhead based on direct labour hours. The budgeted total labour hours for the year was 46474 If one job required 400 direct labour hours, 42 setups,...

  • The following data regarding the activity-based costing system at the Company Co. is available: Activity Pool...

    The following data regarding the activity-based costing system at the Company Co. is available: Activity Pool Base Budgeted Activity Budgeted Cost Machine set up # of setups 2867 $26651 Orders # of orders 924 $80603 Shipping Hours of shipping time 2081 $40657 In addition, prior to adopting an activity based costing system, Company Co. applied overhead based on direct labour hours. The budgeted total labour hours for the year was 50450. If one job required 427 direct labour hours, 41...

  • Question 1 Goodie Inc. manufactures premium quality industrial components. The company adopts job order costing and...

    Question 1 Goodie Inc. manufactures premium quality industrial components. The company adopts job order costing and uses normal costing with activity-based costing to allocate its manufacturing overhead. The annual total overhead costs for the year is broken down into activity cost pools and their respective cost drivers for each cost pool are tabled below. Budgeted Cost (S) Cost Driver Budgeted Activity Overhead Cost Pool Setup Costs Purchasing Costs 240 2,000 60,000 Number of Setups 40,000 Number of Purchases 120,000 Maintenance...

  • 7. A company has two products: Basic and Deluxe. It uses activity-based costing and has prepared...

    7. A company has two products: Basic and Deluxe. It uses activity-based costing and has prepared the following analysis showing budgeted costs and activities. 16,000 units, Annual production of Basic is 28.00 Annual production of Deluxe is - 12,000 units. Product Basie Product Deluxe Total Activity Cost Pool Budgeted Overhead Cost $ 170,000 Machining 600 Machine hours 1400 Machine Hours 800 Machine Hours 600 setups 800 setups 1400 Setups S 145,000 Setups 450 Batches 1100 Batches 650 Batches $ 160,000...

  • Activity Based Costing Activity Based Costing Help Save & Exit Craft Pro Machining produces machine tools...

    Activity Based Costing Activity Based Costing Help Save & Exit Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Tabor $320,000 Indirect Materials Other Overhead Part 2 of 3 Production Activity Grinding Polishing Product modification Providing power System calibration $135,000 600,000 $255,000 500,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power Systen calibration 1,500 engineering hours 17,000 direct...

  • Goodwin Co, manufactures two products: R and W. The company uses activity-based costing to apply manufacturing...

    Goodwin Co, manufactures two products: R and W. The company uses activity-based costing to apply manufacturing overhead costs to products. The cost pools and related estimated overhead costs for 20x3 are as follows: Activity Cost Activity measure Overhead cost Pool Assembly Number of direct labour $33289 hours Inspection Number of inspections 153569 Product support Number of engineers 247332 The expected activity measures for the manufacturing of product R in 20x3 are: 135 direct labour hours, 4548 inspections, and 2 engineer(s)....

  • 2. Determining job costs using activity-based costing. Julio Manufacturing Company uses activity-based costing. The factory overhead...

    2. Determining job costs using activity-based costing. Julio Manufacturing Company uses activity-based costing. The factory overhead budget for the coming period is $500,000, consisting of the following: . . $150,000 200,000 Cost Pool Budgeted Amount Direct labor support.... Machine support....... Machine setups ......... Design changes ............. Total ......................... 100,000 50,000 $500,000 The potential allocation bases and their estimated amounts were as follows: Cost Pool Budgeted Amount Number of design changes 50 Number of setups.... 200 Machine hours ....................................... 10,000 Direct...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT