Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing system. The following are the activities, budgeted total cost and cost drivers per activity for the year 20x9:
Activity |
Budgeted Cost |
Cost Base |
Cost Base Volume |
Assembly |
$864585 |
# of DL hours |
36772 |
Inspection |
$664181 |
# of units |
20927 |
Shipping |
$349574 |
# of batches |
189 |
Plaid Manufacturing has budgeted to produce 3,000 units of G1. G1 is manufactured in batches of 73 units and requires 16196 hours of direct labour. |
What is the overhead cost per unit for product G1? |
Select one:
a. $203.68
b. $626.11
c. $153.04
d. $184.01
Question 3
Not yet answered
Marked out of 1.00
Flag question
Question text
Barker Inc. has identified the following overhead costs and cost drivers fore the upcoming year:
Overhead Item |
Expected Cost |
Cost Driver |
Expected Quantity |
|
Setup costs |
$191997 |
Number of setups |
451 |
|
Ordering costs |
117974 |
Number of orders |
3162 |
|
Maintenance |
354369 |
Machine hours |
3677 |
|
Power |
49146 |
Kilowatt hours |
91356 |
The following are two of the jobs completed during the year:
Job 400 |
Job 401 |
||
Direct materials |
$854 |
$1535 |
|
Direct labour |
$689 |
$2850 |
|
Direct labour hours |
48 |
66 |
|
Number of setups |
2 |
5 |
|
Number of orders |
5 |
4 |
|
Machine hours |
19 |
26 |
|
Kilowatt hours |
28 |
52 |
The company’s normal activity is 4003 direct labour hours.
If Barker used activity based costing, the total cost of Job 401 would be:
Select one:
a. $ 9197
b. $ 6663
c. $ 9019
d. $ 9169
Question 1
Correct answer--------------a. $203.68
Working
Calculation of Activity rates | |||||
Activity Cost Pool | Activity driver | Overhead Cost (A) | Expected Activity (B) | Activity rate (A/B) | |
Assembly | Number of DL hour | $ 8,64,585.00 | 36772 | $ 23.51 | Per DL hour |
Inspection | Number of unit | $ 6,64,181.00 | 20927 | $ 31.74 | Per unit |
Shipping | Number of batch | $ 3,49,574.00 | 189 | $ 1,849.60 | Per batch |
.
Cost assigned to G1 | |||
Activity name | Activity Rates | Activity | ABC Cost |
(A) | (B) | (A x B) | |
Assembly | $ 23.51 | 16,196.00 | $ 3,80,801.12 |
Inspection | $ 31.74 | 3,000.00 | $ 95,213.98 |
Shipping | $ 1,849.60 | 73.00 | $ 1,35,020.65 |
Total Overheads assigned | $ 6,11,035.74 | ||
Production | 3,000.00 | ||
Overhead cost per unit | $ 203.68 |
Question 2
Correct answer--------------a. $ 9197
Working
Direct material | $ 1,535 |
Direct labor | $ 2,850 |
Overheads | $ 4,812 |
Total Cost | $ 9,197 |
.
Calculation of Activity rates | |||||
Activity Cost Pool | Activity driver | Overhead Cost (A) | Expected Activity (B) | Activity rate (A/B) | |
Setup cost | Number of setup | $ 1,91,997.00 | 451 | $ 425.71 | Per setup |
Ordering cost | Number of order | $ 1,17,974.00 | 3162 | $ 37.31 | Per order |
Maintenance | Number of Machine hour | $ 3,54,369.00 | 3677 | $ 96.37 | Per Machine hour |
power | Number of Kilowatt hour | $ 49,146.00 | 91356 | $ 0.54 | Per Kilowatt hour |
.
Cost assigned to Job 401 | |||
Activity name | Activity Rates | Activity | ABC Cost |
(A) | (B) | (A x B) | |
Setup cost | $ 425.71 | 5.00 | $ 2,128.57 |
Ordering cost | $ 37.31 | 4.00 | $ 149.24 |
Maintenance | $ 96.37 | 26.00 | $ 2,505.74 |
power | $ 0.54 | 52.00 | $ 27.97 |
Total Overheads assigned | $ 4,811.52 |
Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing...
Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing system. The following are the activities, budgeted total cost and cost drivers per activity for the year 20x9: Activity Budgeted Cost Cost Base Cost Base Volume Assembly $891922 # of DL hours 34289 Inspection $657733 # of units 23317 Shipping $322225 # of batches 182 Plaid Manufacturing has budgeted to produce 3,000 units of G1. G1 is manufactured in batches of 72 units and...
Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing system. The following are the activities, budgeted total cost and cost drivers per activity for the year 20x9: Activity Budgeted Cost Cost Base Cost Base Volume Assembly $877831 # of DL hours 37167 Inspection $668988 # of units 20830 Shipping $339555 # of batches 186 Plaid Manufacturing has budgeted to produce 3,000 units of M1. M1 is manufactured in batches of 80 units and...
Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing system. The following are the activities, budgeted total cost and cost drivers per activity for the year 20x9 Activity Assembly Inspection Shipping Budgeted Cost $884406 $655248 S347388 Cost Base # of DL hours # of units # of batches Cost Base Volume 32830 22650 182 Budgeted data relating to the production of M1 for 20x9 is given below: Number of units Units per batch...
The following data regarding the activity-based costing system at the Company Co. is available: Base Activity Pool Machine set Budgeted Activity 2839 Budgeted Cost $23322 of setups up Orders Shipping # of orders Hours of shipping time 968 2121 $88985 $40914 In addition, prior to adopting an activity based costing system. Company Co, applied Overhead based on direct labour hours. The budgeted total labour hours for the year was 46474 If one job required 400 direct labour hours, 42 setups,...
The following data regarding the activity-based costing system at the Company Co. is available: Activity Pool Base Budgeted Activity Budgeted Cost Machine set up # of setups 2867 $26651 Orders # of orders 924 $80603 Shipping Hours of shipping time 2081 $40657 In addition, prior to adopting an activity based costing system, Company Co. applied overhead based on direct labour hours. The budgeted total labour hours for the year was 50450. If one job required 427 direct labour hours, 41...
Question 1 Goodie Inc. manufactures premium quality industrial components. The company adopts job order costing and uses normal costing with activity-based costing to allocate its manufacturing overhead. The annual total overhead costs for the year is broken down into activity cost pools and their respective cost drivers for each cost pool are tabled below. Budgeted Cost (S) Cost Driver Budgeted Activity Overhead Cost Pool Setup Costs Purchasing Costs 240 2,000 60,000 Number of Setups 40,000 Number of Purchases 120,000 Maintenance...
7. A company has two products: Basic and Deluxe. It uses activity-based costing and has prepared the following analysis showing budgeted costs and activities. 16,000 units, Annual production of Basic is 28.00 Annual production of Deluxe is - 12,000 units. Product Basie Product Deluxe Total Activity Cost Pool Budgeted Overhead Cost $ 170,000 Machining 600 Machine hours 1400 Machine Hours 800 Machine Hours 600 setups 800 setups 1400 Setups S 145,000 Setups 450 Batches 1100 Batches 650 Batches $ 160,000...
Activity Based Costing Activity Based Costing Help Save & Exit Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Tabor $320,000 Indirect Materials Other Overhead Part 2 of 3 Production Activity Grinding Polishing Product modification Providing power System calibration $135,000 600,000 $255,000 500,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power Systen calibration 1,500 engineering hours 17,000 direct...
Goodwin Co, manufactures two products: R and W. The company uses activity-based costing to apply manufacturing overhead costs to products. The cost pools and related estimated overhead costs for 20x3 are as follows: Activity Cost Activity measure Overhead cost Pool Assembly Number of direct labour $33289 hours Inspection Number of inspections 153569 Product support Number of engineers 247332 The expected activity measures for the manufacturing of product R in 20x3 are: 135 direct labour hours, 4548 inspections, and 2 engineer(s)....
2. Determining job costs using activity-based costing. Julio Manufacturing Company uses activity-based costing. The factory overhead budget for the coming period is $500,000, consisting of the following: . . $150,000 200,000 Cost Pool Budgeted Amount Direct labor support.... Machine support....... Machine setups ......... Design changes ............. Total ......................... 100,000 50,000 $500,000 The potential allocation bases and their estimated amounts were as follows: Cost Pool Budgeted Amount Number of design changes 50 Number of setups.... 200 Machine hours ....................................... 10,000 Direct...