a) Predetermine overhead rate = estimated overhead/Estimated machine hour = 12000000/10000000 = 1.20 per machine hour

b) Predetermine overhead rate = estimated overhead/estimated labor cost = 12000000/6000000 = 200% of labor cost

Add a comment
Know the answer?
Add Answer to:
Marine Components produces parts for airplanes and ships. The parts are produced to specification by their...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Marine Components produces parts for airplanes and ships. The parts are produced to specification by their...

    Marine Components produces parts for airplanes and ships. The parts are produced to specification by their customers, who pay either a fixed price (the price does not depend directly on the cost of the job) or price equal to recorded cost plus 1 and client 2). The work done for client 1 will all be done under fixed-price contracts while the work done for client 2 will all be done under cost-plus contracts. The controller fixed fee (cost plus). For...

  • Marine Components produces parts for airplanes and ships. The parts are produced to specification by their...

    Marine Components produces parts for airplanes and ships. The parts are produced to specification by their customers, who pay either a fixed price (the price does not depend directly on the cost of the job) or price equal to recorded cost plus a fixed fee (cost plus). For the upcoming year (year 2), Marine expects only two clients (client 1 and client 2). The work done for client 1 will all be done under fixed-price contracts while the work done...

  • 1. Turco Products uses a job order cost system. The following debits (credits) appeared in Work-in-Process...

    1. Turco Products uses a job order cost system. The following debits (credits) appeared in Work-in-Process Inventory for September: Description Amount September 1 Balance $ 27,300 For the month Direct materials 162,900 For the month Direct labor 101,600 For the month Factory overhead 77,216 For the month To finished goods ( 318,200 ) Turco applies overhead to production at a predetermined rate of 76 percent based on direct labor cost. Job 9-27, the only job still in process at the...

  • Tiger Furnishings produces two models of cabinets for home theater components, the Basic and the Dominator....

    Tiger Furnishings produces two models of cabinets for home theater components, the Basic and the Dominator. Data on operations and costs for March follow: Basic Dominator Total Units produced 950 400 1,350 Machine-hours 3,100 2,700 5,800 Direct labor-hours 3,000 2,000 5,000 Direct materials costs $ 8,400 $ 4,100 $ 12,500 Direct labor costs 55,700 33,800 89,500 Manufacturing overhead costs 164,720 Total costs $ 266,720 Required: Compute the predetermined overhead rate assuming that Tiger Furnishings uses machine-hours to allocate overhead costs....

  • Question 4 Marine Components manufactures two products: JZ500 and XR800. The company operates in a competitive...

    Question 4 Marine Components manufactures two products: JZ500 and XR800. The company operates in a competitive market and has recently seen a decline in market share of XR 800 to aggressive competitors. Marine Components is reviewing its costing and pricing strategies to see if improvements can be made. Currently Marine Components uses a traditional costing system to assign overheads to nraduction usine direct labour hours and sets selling prices by adding 40% to a producte total cost. The budgeted overhead...

  • please help!! Western, Inc. is a technology consulting firm focused on Web site development and integration...

    please help!! Western, Inc. is a technology consulting firm focused on Web site development and integration of Internet business applications. The president of the company expects to incur $640,000 of indirect costs this year, and she expects her firm to work 4.000 direct labor hours. Western's systems consultants provide direct labor at a rate of $280 per hour Clients are billed at 160% of direct labor cost. Last month, Western's consultants spent 170 hours on Halbert's engagement Requirements 1. Compute...

  • Please answer all parts! Thank you! Problem 2-19 Multiple Predetermined Overhead Rates; Applying Overhead (LO2-1, LO2-2,...

    Please answer all parts! Thank you! Problem 2-19 Multiple Predetermined Overhead Rates; Applying Overhead (LO2-1, LO2-2, LO2-4) High Desert Potteryworks makes a variety of pottery products that it sells to retailers. The company uses a job-order costing system in which departmental predetermined overhead rates are used to apply manufacturing overhead cost to jobs. The predetermined overhead rate in the Molding Department is based on machine-hours, and the rate in the Painting Department is based on direct labor- hours. At the...

  • Job Costing #3 Burlington Corporation uses a job-order costing system and a predetermined overhead rate based...

    Job Costing #3 Burlington Corporation uses a job-order costing system and a predetermined overhead rate based on machine hours. At the beginning of the year, the company estimated manufacturing overhead for the year would be $3,200,000 and 4,000 machine hours would be used. Labor was estimated at $200/hour. The following information pertains to December of the current year: Job No. Job No. Job No. Job No. 206 207 208 209 Work in process, December 1 $28,000 $30,000 $22,000 $10,000 December...

  • all parts and how was it calculated plz Review Problem #1 Abbott Company bases its predetermined...

    all parts and how was it calculated plz Review Problem #1 Abbott Company bases its predetermined overhead rate on estimated machine-hours for the upcoming year. Data for the upcoming year appears below: Direct Materials Wage Rate Estimated Direct Labor Hours Actual Direct Labor Hours Estimated Machine Hours Actual Machine Hours Estimated Fixed Manufacturing Overhead Estimated Variable Manufacturing Overhead Actual Manufacturing Overhead $250,000 $15 per direct labor hour 15,000 12,500 5,000 4,000 $150,000 $5.00 per machine hour $130,000 Please answer the...

  • Tiger Furnishings produces two models of cabinets for home theater components, the Basic and the Dominator....

    Tiger Furnishings produces two models of cabinets for home theater components, the Basic and the Dominator. Data on operations and costs for March follow: Basic Dominator Total Units produced 900 300 1,200 Machine-hours 4,500 2,100 6,600 Direct labor-hours 3,000 2,300 5,300 Direct materials costs $ 9,700 $ 3,750 $ 13,450 Direct labor costs 56,500 39,600 96,100 Manufacturing overhead costs 184,440 Total costs $ 293,990 Required: Compute the predetermined overhead rate assuming that Tiger Furnishings uses direct labor-hours to allocate overhead...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT