If Toyota Motor Company receives an order on May 3, begins production on May 14, and ships the order on May 16 immediately following production, then what is the manufacturing cycle efficiency (MCE) ratio?
Manufacturing cycle efficiency ratio is equal to percentage of time spent for value added activities (i.e. process time).
Value added time or process time is from May 14 to May 16 (i.e. total 3 days).
Inspection and queue time is from May 3 to May 13 (i.e. total 11 days).
Manufacturing cycle time = Inspection and queue time+Process time
= 11 days+3 days = 14 days
Manufacturing cycle efficiency ratio = (Process time/Manufacturing cycle time)*100
= (3 days/14 days)*100 = 21.43% (rounded off)
Therefore the manufacturing cycle efficiency (MCE) ratio is 21.43%.
If Toyota Motor Company receives an order on May 3, begins production on May 14, and...
If Toyota Motor Company receives an order on May 3, begins production on May 14, and ships the order on May 16 immediately following production, then what is the manufacturing cycle efficiency (MCE) ratio?
If Toyota Motor Company receives an order on May 3, begins production on May 20, and ships the order on May 26 immediately following production, then what is the manufacturing cycle efficiency (MCE) ratio? Manufacturing cycle efficiency (MCE) ratio
If Toyota Motor Company receives an order on May 1, begins production on May 13, and ships the order on May 15 immediately following production, then what is the manufacturing cycle efficiency (MCE) ratio? Manufacturing cycle efficiency (MCE) ratio
13 Homework (Managerial) * Saved If Toyota Motor Company receives an order on May 5, begins production on May 18, and ships the order on May 22 immediately following production, then what is the manufacturing cycle efficiency (MCE) ratio? Manufacturing cyce efficiency (MCE) ratio < Prev 2 of 6 Next >
CON AFCC WEBSITE Property management Suggested Sites - Web Slice Gallery- cers 11 and 13 Homework (Managerial) Seved if Toyota Motor Company receives an order on May 5, begins production on May 18, and ships the order on May 22 immediately following production, then what is the manufacturing cycle efficiency (MCE) ratio? Manufacturing de efficiency (MCE) ratio to search Prev 2 of 6 Next >
Check my work mode: This shows what is correct or incorrect for the work you have completed so far. It does not indicate compler Wiliams Inc. Produces A Single Product A Part Us If Toyota Motor Company receives an order on May 5, begins production on May 18, and ships the order on May 22 immediately following production, then what is the manufacturing cycle efficiency (MCE) ratio? Answer is complete but not entirely correct. Manufacturing cycle efficiency (MCE) ratio 00:43:03...
Check my w Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 15.4 days 3.2 days 0.9 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.)...
Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases. Process time Inspection time Move time Wait time 70 days 1.8 days 4. 3 days 13.0 days Required: 1. Compute the company's manufacturing cycle time 2. Compute the company's manufacturing cycle efficiency 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques. Compute the company's manufacturing cycle efficiency assuming...
Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations....
Problem 10-14 Measures of Internal Business Process Performance [LO10-3] DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations....