Question

If Toyota Motor Company receives an order on May 3, begins production on May 20, and ships the order on May 26 immediately fo

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Manufacturing Cycle Efficiency = Value added time / Throughput time
= 7 / 24
= 0.29
or = 0.3 rounded off
Value added time = May 20 to May 26
Throughput time = May 3 to May 26
Add a comment
Know the answer?
Add Answer to:
If Toyota Motor Company receives an order on May 3, begins production on May 20, and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT