Question

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The compa
Evaluate the companys performance over the last four months. (Indicate the effect of each trend by selecting Favorable or
3-a. (Month 5) Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, p
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Ans. The Throughput time measure displays Favorable trends
The delivery cycle time - days measure displays Favorable trends
Manufacturing cycle efficiency - days measure displays Unfavorable trends
*Throughput time & Delivery are increasing every month so, theses are favorable trends.
*Manufacturing cycle time is decreasing every month so, this is an unfavorable trend.
(i) Throughput time = Move time + Process time + Queue time + Inspection time
Months
Particulars 1 2 3 4
Move time per unit 0.9 0.6 0.7 0.7
Process time per unit 2.3 2.2 2.1 2
Inspection time per unit 0.9 1.1 1.1 0.9
Queue time 4.8 5.4 6.1 6.9
Total (Throughput Time) 8.9 days 9.3 days 10 days 10.5 days
(ii) Manufacturing cycle efficiency = Process time or value added time / Throughput time * 100
Months
1 2.3 / 8.9 * 100 25.8%
2 2.2 / 9.3 * 100 23.7%
3 2.1 / 10 * 100 21.0%
4 2 / 10.5 * 100 19.0%
(iii) Delivery cycle time = Throughput time + Wait time per order before start of production
Months
1 8.9 + 18 26.9 days
2 9.3 + 19.7 29 days
3 10 + 22 32 days
4 10.5 + 23.8 34.3 days
Ans. 3 Month 5 Month 6
Throughput time 3.6 days 2.7 days
Manufacturing cycle efficiency (MCE) 55.6% 74.1%
*Calculations:
Ans. 3 a Month 5 :
Throughput time:
Move time per unit 0.7
Process time per unit 2
Inspection time per unit 0.9
Total 3.6 days
MCE (manufacturing cycle efficiency) = Process time / Throughput time * 100
2 / 3.6 * 100
55.6%
Ans. 3 b Month 6 :
Throughput time:
Move time per unit 0.7
Process time per unit 2
Total 2.7 days
MCE (manufacturing cycle efficiency) = Process time / Throughput time * 100
2 / 2.7 * 100
74.1%
Add a comment
Know the answer?
Add Answer to:
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 1 Throughput time (days) Delivery cycle time...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 ? Throughput time (days) Delivery...

  • DataSpan, Inc., automated Its plant at the start of the current year and Installed a flexible...

    DataSpan, Inc., automated Its plant at the start of the current year and Installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountere relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing cycle efficiency...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Problem 10-14 Measures of Internal Business Process Performance (LO10-3]...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month ? Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 3 2 ? 4 ? ? ? Throughput...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT