Question

Requirement 1. Complete the performance evaluation report for this subunit Enter the variance percent as a percentage of the
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Requirement 1)
(A) (B) (C ) (D )=(C )/(B)
Subunit X Actual Result Flexible Budget Flexible Budget Variance(F )/(U) % of variance (F )/(U)
Direct Material $           28,900.00 $             26,800.00 $                                                2,100.00 (U) 7.84%
Direct Labor $           13,900.00 $             14,600.00 $                                                   700.00 (F) 4.79%
Indirect Labor $           26,000.00 $             22,900.00 $                                                3,100.00 (U) 13.54%
Utilities $           12,000.00 $             11,200.00 $                                                   800.00 (U) 7.14%
Depreciation $           27,000.00 $             27,000.00 $                                                             -   0.00%
Repair & Maintenance $             4,700.00 $               5,700.00 $                                                1,000.00 (F) 17.54%
$       1,12,500.00 $         1,08,200.00 $                                                4,300.00 (U) 3.97%
Requirement 2)
This performance report includes only cost data ,therfore Subunit is a cost centre.
Requirement 3)
Management first investigate all unfavorable variances.
1) Indirect Labor
2) Direct Material
3) Utilities
Requirement 4)
No,Favorable variance should be investigated.
Add a comment
Know the answer?
Add Answer to:
Requirement 1. Complete the performance evaluation report for this subunit Enter the variance percent as a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please open enlarge and view. The blue box data table is included. Options for requirement 3...

    Please open enlarge and view. The blue box data table is included. Options for requirement 3 are Depreciation, direct labor, direct materials, indirect labor, repairs and maintenance, utilities Options for req 4 Yes or no And (never need to be investigated because they increase net income, should be investigated to make sure the variance does not happen again, should be investigated to make sure they are not hurting the business in the long run. Х Data Table Flexible Budget Variance...

  • . One subunit of Extreme Sports Company had the following financial results last month: (Click the...

    . One subunit of Extreme Sports Company had the following financial results last month: (Click the icon to view the financial results.) Read the requirements Requirement 1. Complete the performance evaluation report for this subunit. Enter the variance percent as a percentage of the budgeted amount rounded to two places. (Enter a variance for each account as a positive number, and select whether the variance is favorable [F] or unfavorable [U]. For any zero variances, enter a 0 in the...

  • %E24-22 (similar to) One subunit of Extreme Sports Company had the following financial results last month:...

    %E24-22 (similar to) One subunit of Extreme Sports Company had the following financial results last month: ES: (Click the icon to view the financial results.) Read the requirements Requirement 1. Complete the performance evaluation report for this subunit. Enter the variance percent as a percentage of the b places. (Enter a variance for each account as a positive number and select whether the variance is favorable [F] or unfavorable in the variance column and then leave the For U box...

  • all information is shown One subunit of Winter Sports Manufacturing Company had the following financial results...

    all information is shown One subunit of Winter Sports Manufacturing Company had the following financial results last month HE (Click the icon to view the financial results) Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunt? 1. Which items should be investigated if part of management's decision criteria is to investigate al variancesceng $3,200 of 10%? 4. Should only unfavorable variances be investigated? Explain Requirement...

  • One subunit of All Season Sports Manufacturing Company had the following financial results last month: Click...

    One subunit of All Season Sports Manufacturing Company had the following financial results last month: Click the icon to view the financial results.) Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunit? 3. Which items should be investigated if part of management's decision criteria is to investigate all variances exceeding $3,200 or 11.5%? 4. Should only unfavorable variances be investigated? Explain. Requirement 1. Complete the...

  • E24-22 (similar to) One subunit of Extreme Sports Company had the following financial results last month:...

    E24-22 (similar to) One subunit of Extreme Sports Company had the following financial results last month: (Click the icon to view the financial results.) Read the requirements Requirement 1. Complete the performance evaluation report for this subunit. Enter the variance percent as a percentage of for each account as a positive number, and select whether the variance is favorable [F] or unfavorable [U]. For any zero van U box blank. Enter the variance percent as a percentage rounded to two...

  • One subunit of Winter Sports Manufacturing Company had the following financial results last month: : (Click...

    One subunit of Winter Sports Manufacturing Company had the following financial results last month: : (Click the icon to view the financial results.) Requirements 1. Complete the performance evaluation report for this subunit. 2. Based on the data presented, what type of responsibility center is the subunit? 3. Which items should be investigated if part of management's decision criteria is to investigate all variances exceeding $3,100 or 13%? 4. Should only unfavorable variances be investigated? Explain. X Reqi varia Data...

  • Tully Company's production performance report for April includes the information shown below. LOADING... Requirement Prepare a...

    Tully Company's production performance report for April includes the information shown below. LOADING... Requirement Prepare a flexible budget for the items shown and compute the flexible budget cost variances and planning cost variances for each item. Indicate whether the variances are favorable or unfavorable for each item. Begin with the master​ budget, then complete the flexible budget columns and the actual results columns. Label each variance as favorable​ (F) or unfavorable​ (U).​ (For variances with a​ $0 balance, make sure...

  • One subunit of Field Sports Company had the following financial results last month: (Click the icon...

    One subunit of Field Sports Company had the following financial results last month: (Click the icon to view the financial results.) Read the requirements Requirement 1. Complete the performance evaluation report for the subunit. (Enter a variance for each account as a positive number and select whether the variance is favorable or unfavorable. Enter the variance percent as a percentage rounded to two decimal places, X.XX%) Actual Flexible Flexible Budget % Variance Subunit x Results Budget Variance (For U) (For...

  • Requirement 1: Complete the following flexible budget performance report using the numbers from the Business Assignment...

    Requirement 1: Complete the following flexible budget performance report using the numbers from the Business Assignment 2 Instructions file. The Board Company Flexible Budget Performance Report for the month ended August 31 Budgeted units of production: Actual units of production: Units of production variance в (A-B) F/U (A-C) FIU Α Actual Costs Incurred for 9.480 units Flexible Budget Based on 9.480 units Flexible Budget Variance Static Budget Based on 9.000 units Static Budget Variances Variable Costs: Direct materials Direct labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT