Given that the maker has a learning rate of 78%
and he takes 6 hours on 3rd table,
time taken on 1st table would be = 6/(0.782) = 9.8612 =9.9
So we have our time to make 1st table, we will find the time to complete 1st and 2nd and rest 97 table will take of 6hour each
The total time is = 9.9 + 9.9(0.78) + 9.9(0.78)2 + 9.9(0.78)3 + 97*6
= 9.9 + 7.7 + 6 + 4.7 + 582
= 610.3 hours
Question 4 1 pts A furniture maker has an order for 88 identical tables. If the...
Question4 1 pts A furniture maker has an order for 90 identical tables. If the furniture maker estimates his learning curve at 78% and can reach steady production of 6 hours per table on the 4th table how long should it take to make all the tables? Express your answer in hours to the nearest whole hour.
Question 4 1 pts A furniture maker has an order for 58 identical tables. If the furniture maker estimates his learning curve at 84% and can reach steady production of 7 hours per table on the 4th table, how long should it take to make all the tables? Express your answer in hours to the nearest whole hour.
A furniture maker has an order for 93 identical tables. If the furniture maker estimates his learning curve at 78% and can reach steady production of 9 hours per table on the 6th table, how long should it take to make all the tables? Express your answer in hours to the nearest whole hour
Question4 1 pts A furniture maker has an order for 85 identical tables. If the furniture maker estimates his learning curve at 92% and can reach steady production of 5 hours per table on the 6th table, how long should it take to make all the tables? Express your answer in hours to the nearest whole hour
A furniture maker has an order for 37 identical tables. If the furniture maker estimates his learning curve at 85% and can reach steady production of 5 hours per table on the 6th table, how long should it take to make all the tables? Express your answer in hours to the nearest whole hour.
A furniture maker has an order for 85 identical tables. If the furniture maker estimates his learning curve at 79% and can reach steady production of 9 hours per table on the 4th table, how long should it take to make all the tables? Express your answer in hours to the nearest whole hour.
A furniture maker has an order for 63 identical tables. If the furniture maker estimates his learning curve at 93% and can reach steady production of 6 hours per table on the 5th table, how long should it take to make all the tables? Express your answer in hours to the nearest whole hour.
D Question 5 1 pts A tailor must make 4 of the same size suits for a client. The first suit took 12.5 hours to make and the last suit took 8.6 hours to make, what was the tailor's learning curve % of this run of suits assuming a steady state of production is never reached? Express your answer in % to the nearest 0.1%
Question 5 1 pts A tailor must make 6 of the same size suits for a client. The first suit took 13.2 hours to make and the last suit took 7.6 hours to make what was the tailor's learning curve % of this run of suits assuming a steady state of production is never reached? Express your answer in 96 to the nearest 0.1%
D Question 5 1 pts A tailor must make 7 of the same size suits for a client. The first suit took 13.5 hours to make and the last suit took 6.9 hours to make. What was the tailor's learning curve % of this run of suits assuming a steady state of production is never reached? Express your answer in 96 to the nearest 0.1%