Conversion Cost blank: Cost per table/chair= (Total cost/Total no.of units)
T-12: 35.92
C-10: 31.425
T-12 tables costs:
Transferred out: (18700*35.92)= 671,704
WIP
Material {3300*19(418000/22000)}= 62700
Conversion: 55836
Total: 790,240
C-10 Chairs costs:
Transferred out: (17050*31.425)= 535,796.25
WIP
Material {550*18(316800/17600)}= 9900
Conversion: 7383.75
Total: 553,080
T-12 costs
Equivalent units
Particulars | Physical Units | Material | Conversion cost |
Transferred out | 18700 | 9603 | 9097 |
WIP July 31 | 3300 | 1695 | 1605 |
Total | 22000 | 11298 | 10702 |
Unit Costs:
Conversion Cost: 372240; Equivalent Units: 22000. Unit cost 18. Total Cost: 790240
Cost reconciliation:
Transferred out: 671,704
WIP july 31
Material: 62700
Conversion cost: 55836
Total cost: 790240
need help filling in the blanks Problem 16-3A Thalen Industries Inc. manufactures dorm fumiture in parte...
Need help for part (b) Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conver Cutting Department Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July 17,600 Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300 550 Cost Data-July Work in process, July 1 Materials Labor Overhead Total 418,000 257,840 114,400 $790,240...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 25,000 20,000 Work in process units, July 31 3,750...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300...
Problem 16-3A Thakin industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first processin products in two different manufacturing plants are as follows. Cutting Department g two T12-Tabes CIO-Chairs Production Date -July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 17,600 22,000 3,300 Cost Date-July Work in...
Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 24,600 19,680 Work in process units, July 31 3,690...
FULL SCREEN PRINTER VERSION BACK NEXT Problem 17-3A Thakin Industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 Plant 2 Production Data-July T12-Tables C10-Chairs Work in process units, July 1 0 0 Units started into production 20,600 16,480 Work in process units,...
Thakin Industries Inc. manufactures dorm furniture in separate processes Production and cost data for the first process in making two products in tw Cutting Department Plant 1 Plant 2 Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete T12-Tables c10-Chairs 0 17,500 700 80 G. 19,500 3,100 60 Cost Data-July Work in process, July1 s0 390,000 234, 700 112,240 $0 Materials 280,000 113,000 112,680 Labor Overhead...
Problem 16-3A (Part Level Submission) Seagren Industries Inc. manufactures in separate processes furniture for homes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 plant 2 T12-Tables C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300 17,600 550 80 Cost Data-July...