Question
need help filling in the blanks
Problem 16-3A Thalen Industries Inc. manufactures dorm fumiture in parte processes the process, materials are entered at the

Kimmel, Accounting, 6e lice Assignment Gradebook ORION Downloadable eTextbook ment Your answer is correct. For each plant com
Be Practice Assignment Gradebook ORION Downloadable eTextbook ssignment DES T12 Tables Costs accounted for: Transferred out 6
Prepare the production cost report for Plant 1 for July 2017. THAKIN INDUSTRIES INC. Cutting Department-Plant 1 Production Co
Costs Materials Conversion Costs Total Unit costs Total Costs 418000 Equivalent units 22000 Unit costs 19.00 18.00 37.00 Cost
Cost Reconciliation Schedule Costs accounted for Transferred out Work in process, July 31 Materials Conversion costs Total co
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Conversion Cost blank: Cost per table/chair= (Total cost/Total no.of units)

T-12: 35.92

C-10: 31.425

T-12 tables costs:

Transferred out: (18700*35.92)= 671,704

WIP

Material {3300*19(418000/22000)}= 62700

Conversion: 55836

Total: 790,240

C-10 Chairs costs:

Transferred out: (17050*31.425)= 535,796.25

WIP

Material {550*18(316800/17600)}= 9900

Conversion: 7383.75

Total: 553,080

T-12 costs

Equivalent units

Particulars Physical Units Material Conversion cost
Transferred out 18700 9603 9097
WIP July 31 3300 1695 1605
Total 22000 11298 10702

Unit Costs:

Conversion Cost: 372240; Equivalent Units: 22000. Unit cost 18. Total Cost: 790240

Cost reconciliation:

Transferred out: 671,704

WIP july 31

Material: 62700

Conversion cost: 55836

Total cost: 790240

Add a comment
Know the answer?
Add Answer to:
need help filling in the blanks Problem 16-3A Thalen Industries Inc. manufactures dorm fumiture in parte...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Need help for part (b) Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture...

    Need help for part (b) Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conver Cutting Department Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July 17,600 Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300 550 Cost Data-July Work in process, July 1 Materials Labor Overhead Total 418,000 257,840 114,400 $790,240...

  • Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...

    Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300...

  • Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...

    Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 25,000 20,000 Work in process units, July 31 3,750...

  • Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...

    Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300...

  • Problem 16-3A Thakin industries Inc, manufactures dorm furniture in separate processes. In each process, materials are...

    Problem 16-3A Thakin industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first processin products in two different manufacturing plants are as follows. Cutting Department g two T12-Tabes CIO-Chairs Production Date -July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 17,600 22,000 3,300 Cost Date-July Work in...

  • Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each...

    Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 24,600 19,680 Work in process units, July 31 3,690...

  • FULL SCREEN PRINTER VERSION BACK NEXT Problem 17-3A Thakin Industries Inc, manufactures dorm furniture in separate...

    FULL SCREEN PRINTER VERSION BACK NEXT Problem 17-3A Thakin Industries Inc, manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 Plant 2 Production Data-July T12-Tables C10-Chairs Work in process units, July 1 0 0 Units started into production 20,600 16,480 Work in process units,...

  • Thakin Industries Inc. manufactures dorm furniture in separate processes Production and cost data...

    Thakin Industries Inc. manufactures dorm furniture in separate processes Production and cost data for the first process in making two products in tw Cutting Department Plant 1 Plant 2 Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete T12-Tables c10-Chairs 0 17,500 700 80 G. 19,500 3,100 60 Cost Data-July Work in process, July1 s0 390,000 234, 700 112,240 $0 Materials 280,000 113,000 112,680 Labor Overhead...

  • Problem 16-3A (Part Level Submission) Seagren Industries Inc. manufactures in separate processes furniture for homes. In...

    Problem 16-3A (Part Level Submission) Seagren Industries Inc. manufactures in separate processes furniture for homes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 plant 2 T12-Tables C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent...

  • Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...

    Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Plant 1 T12-Tables Plant 2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 22,000 3,300 17,600 550 80 Cost Data-July...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT