Solution 15:
Spending variance for shipping expenses = Budgeted shipping expense for actual activity - Actual shipping expense
= (30000*$3) - $115,000 = $25,000 U
You received partial credit in the previous attempt. Required information The Foundational 15 [LO9-1, LO9-2, LO9-4,...
Required information The Foundational 15 [LO9-1, LO9-2, LO9-4, LO9-5, LO9-6] The following information applies to the questions displayed below. Preble Company manufactures one product Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $8.00 per pound Direct labor: 2 hours at $14 per hour Variable overheadı 2 hours at 55 per hour Total standard variable cost per unit $40.00 28.00 10.00 $78.00...
* You received no credit for this question in the previous attempt Required information The Foundational 15 (LO9-1, LO9-2, L09-4, LO9-5, LO9-6] The following information applies to the questions displayed below. Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor hours and its standard cost card per unit is as follows: Direct ateriat 5 pounds at 58.00 per pound Direct labori 2 hours at 514 per hour Variable overhead 2 hours at...
Required information The Foundational 15 [LO9-1, LO9-2, LO9-4, LO9-5, LO9-6] [The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $8.00 per pound $ 40.00 Direct labor: 2 hours at $14 per hour 28.00 Variable overhead: 2 hours at $5 per hour 10.00 Total standard variable cost per unit...
The Foundational 15 [LO9-1, LO9-2, LO9-4, LO9-5, LO9-6] [The
following information applies to the questions displayed below.]
Preble Company manufactures one product. Its variable manufacturing
overhead is applied to production based on direct labor-hours and
its standard cost card per unit is as follows: Direct material: 5
pounds at $8.00 per pound $ 40.00 Direct labor: 2 hours at $14 per
hour 28.00 Variable overhead: 2 hours at $5 per hour 10.00 Total
standard variable cost per unit $ 78.00...
Required information The Foundational 15 [LO9-1, LO9-2, LO9-4, LO9-5, LO9-6] [The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $8.00 per pound $ 40.00 Direct labor: 2 hours at $14 per hour 28.00 Variable overhead: 2 hours at $5 per hour 10.00 Total standard variable cost per unit...
The Foundational 15 [LO9-1, LO9-2, LO9-4, LO9-5, LO9-6] [The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $8.00 per pound $ 40.00 Direct labor: 2 hours at $14 per hour 28.00 Variable overhead: 2 hours at $5 per hour 10.00 Total standard variable cost per unit $ 78.00...
The Foundational 15 [L09-1, LO9-2, L09-4, LO9-5, L09-6) [The following information applies to the questions displayed below.) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $8.00 per pound Direct labor: 2 hours at $14 per hour 28.00 Variable overhead: 2 hours at $5 per 10.00 hour Total standard variable cost per unit $78.00 The company also...
preble company manufactures one product. it’s variable
manufacturing overhead is applied to production based on direct
labor hours and its standard cost card per unit is as follows
40.00
Required information The Foundational 15 (LO9-1, LO9-2, L09-4, LO9-5, LO9-6] The following information applies to the questions displayed below) Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at 58.00 per pound $40.00 Direct labor: 2 hours at $14 per hour 28.00 Variable overhead: 2 hours at 5 per hour 10.00 Total standard variable cost per unit $78.00 The company also established the following cost formulas for its selling expenses: Advertising Sales salaries and commissions Shipping expenses...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct material: 5 pounds at $8.00 per pound Direct labor: 2 hours at $14 per hour Variable overhead: 2 hours at $5 per hour Total standard variable cost per unit $40.00 28.00 19.00 $78.00 The company also established the following cost formulas for its selling expenses: Variable Cost per Unit Sold Fixed Cost...