Solution
(a) For making an assignment with an object of minimization, we have to go through the following steps,
Step-1: First we have to draw a table as follows,
Consultant |
Project (Hours) |
|||
A |
B |
C |
D |
|
Charlie |
13 |
16 |
11 |
13 |
Betty |
11 |
15 |
14 |
18 |
Johnny |
15 |
22 |
12 |
15 |
Rick |
17 |
17 |
12 |
22 |
Step-2: We have to make Row operations first, i.e. deduct each row value with the minimum-most value in every row. For example, in the first row “Charlie”, the lowest value is 11. Here we have to deduct 11 from each value. This operation will be followed in every row as given below,
Consultant |
Project (Hours) |
|||
A |
B |
C |
D |
|
Charlie |
13-11 = 2 |
16-11 = 5 |
11-11 = 0 |
13-11 = 2 |
Betty |
11-11 = 0 |
15-11 = 4 |
14-11 = 3 |
18-11 = 7 |
Johnny |
15-12 = 3 |
22-12 = 10 |
12-12 = 0 |
15-12 = 3 |
Rick |
17-12 = 5 |
17-12 = 5 |
12-12 = 0 |
22-12 = 10 |
Or,
Consultant |
Project (Hours) |
|||
A |
B |
C |
D |
|
Charlie |
2 |
5 |
0 |
2 |
Betty |
0 |
4 |
3 |
7 |
Johnny |
3 |
10 |
0 |
3 |
Rick |
5 |
5 |
0 |
10 |
Step-3: Now we have to make column operations, i.e. deduct each column value with the minimum-most value in every column. For example, in the first column “A”, the lowest value is 0. Here we have to deduct 0 from each value. This operation will be followed in every column as given below,
Consultant |
Project (Hours) |
|||
A |
B |
C |
D |
|
Charlie |
2-0 = 2 |
5-4 = 1 |
0-0 = 0 |
2-2 = 0 |
Betty |
0-0 = 0 |
4-4 = 0 |
3-0 = 3 |
7-2 = 5 |
Johnny |
3-0 = 3 |
10-4 = 6 |
0-0 = 0 |
3-2 = 1 |
Rick |
5-0 = 5 |
5-4 = 1 |
0-0 = 0 |
10-2 = 8 |
Or,
Consultant |
Project (Hours) |
|||
A |
B |
C |
D |
|
Charlie |
2 |
1 |
0 |
0 |
Betty |
0 |
0 |
3 |
5 |
Johnny |
3 |
6 |
0 |
1 |
Rick |
5 |
1 |
0 |
8 |
Step-4: Here we have to draw lines over the respective rows and columns, starting from the row or column having the more number of “0” given as below,
Now, for an optimal assignment, number of lines will be equal to the matrix. Here the matrix is of 4x4. So the lines drawn should be also 4. But as number of lines are 3, we need to modify the matrix values. Here the matrix values will be modified as follows,
(1) Choose the minimum-most value from the matrix over which no line has been passed. Here the value is 1. Now, 1 will be deducted from the values in the matrix over which no line has been passed, and 1 will be added with the values at the intersection points. The values under line drawn will not be modified. Table redrafted as below,
Consultant |
Project (Hours) |
|||
A |
B |
C |
D |
|
Charlie |
2-1 = 1 |
1-1 = 0 |
0 |
0 |
Betty |
0 |
0 |
3+1 = 4 |
5+1 = 6 |
Johnny |
3-1 = 2 |
6-1 = 5 |
0 |
1 |
Rick |
5-1 = 4 |
1-1 = 0 |
0 |
8 |
Or,
Consultant |
Project (Hours) |
|||
A |
B |
C |
D |
|
Charlie |
1 |
0 |
0 |
0 |
Betty |
0 |
0 |
4 |
6 |
Johnny |
2 |
5 |
0 |
1 |
Rick |
4 |
0 |
0 |
8 |
(2) Now again we have to make row and column operations once again as mentioned in Step-2 and Step-3 above. Here we are not making this once again as all the rows and columns in the matrix consists one or more “0”. Therefore, if we draw the lines once again,
Now, as the number of lines drawn has been equated with the matrix, we can draw an optimal assignment as follows,
Consultant |
Project (Hours) |
|||
A |
B |
C |
D |
|
Charlie |
1 |
0 |
0 |
0 |
Betty |
0 |
0 |
4 |
6 |
Johnny |
2 |
5 |
0 |
1 |
Rick |
4 |
0 |
0 |
8 |
The assignment will be made in such a way that for each consultant once a value has been chosen, no other values could be chosen in that same row and column of the value which is selected. For Example, we have chosen “Project A” for “Betty” as it will be optimum. We will be unable to make any assignment in either “Project A” column, or “Betty” row. Therefore, the remaining assignments will be done in the same way.
So,
Optimal Assignment:
Charlie = D
Betty = A
Johnny = C
Rick = B
(b) Referring back to the original table,
Consultant |
Project (Hours) |
|||
A |
B |
C |
D |
|
Charlie |
13 |
16 |
11 |
13 |
Betty |
11 |
15 |
14 |
18 |
Johnny |
15 |
22 |
12 |
15 |
Rick |
17 |
17 |
12 |
22 |
The optimal time will be as follows,
Consultant |
Project (Hours) |
Values |
Charlie |
D |
13 |
Betty |
A |
11 |
Johnny |
C |
12 |
Rick |
B |
17 |
Total |
53 |
Therefore, the total rate for the optimal time of 53 hours will be the optimal cost.
Printed (Chinese) Name: THU ID: Class: Problem 8 (10 points) The president of a consulting firm...
4. The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald, Johnny, and Rick -- to complete any of the four projects, as indicated in the table below. Press hours! Consultan ABCD Charlie 1516 EUR Gerald 13151GE Johnny US 2120 LS Rick 0719 1222 (a) Find the...
4. The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald, Johnny, and Rick -- to complete any of the four projects, as indicated in the table below. Press hours! Consultan ABCD Charlie 1516 EUR Gerald 13151GE Johnny US 2120 LS Rick 0719 1222 (a) Find the...
The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald, Johnny, and Rick -- to complete any of the four projects, as indicated in the table below. (a) Find the optimal assignment such that the total number of hours is minimized. (Show your table in each step)...
4. The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald. Johnny, and Rick -- to complete any of the four projects, as indicated in the table below. Consultant Charlie Gerald Johnny Rick Project (hours) A B 15 16 13 15 15 21 17 19 с 12...
4. The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald, Johnny, and Rick - to complete any of the four projects, as indicated in the table below. Consultant Charlie Gerald Johnny Rick Project Chours) A B 15 16 13 15 15 21 17 19 с 12...
4. The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald, Johnny, and Rick -- to complete any of the four projects, as indicated in the table below. Consultant Charlie Gerald Johnny Rick Project (hours) А B 15 16 13 15 15 21 17 19 с 12...
Problem 5 (10 points) Give the following diagram. Printed (Chinese) Name: THU ID: Class: 15 units/hr 17 units/hr 17 units/hr 0 0 0 What is the capacity of this system? 1553 R 4tk If the capacity of one operation could be increased in order to increase the output of the system, which operation should it be, and what amount of increase? 1 3 : 4. * to thol ) lb capado cai-ty 1
Printed (Chinese) Name: THỨ ID: Problem 6 (10 points) Class: A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be 3.50 per load per meter moved. An analyst has prepared the following distances and flow matrices: Distances (meters) X = I Y I From/To IX IN III X= I Y=0 - 10 - 20 I...