Solution:
Customer-Response Time is the period between placement of order by customer and the delivery of the goods or services by customer.
Calculation of Total Customer-Response Time | |
Particulars | No. of Days |
Order received by manufacturing department | 10 |
Order is put into production (15-10) | 5 |
Processing/ Manufacturing time | 20 |
Shipping Time | 10 |
Total | 45 |
Total Customer-Response Time is 45 Days.
Note:
1) Order is put into production after 15 days from the date of order received from customer. Those 15 days includes 10 days of time taken to place order with manufacturing department. i.e., time for put into production is 15 Days - 10 Days= 5 Days.
2) No information is provided about when the customer received the product . so we are considering shipping time includes time taken to reach the product to customer.
A customer places an order on January 1, 2016. Ten days later that order is received...
On January 4th, Stevens Manufacturing received an order for 30 uniforms. The following information pertained to that order. Hours Required Receive and process order 0.25 Waiting for production to begin 1.25 Cutting 50.00 Sewing and lettering 300.00 Moving materials from one station to another 20.00 Waiting for an operation to begin 95.00 Packaging 35.00 Loading to be shipped 0.50 In transit to customer 5.00 Calculate the manufacturing cycle time. A. 500 Hours B. 507 Hours C. 502 Hours D. 505...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: 0.3 days Inspection time Wait time (from order to start of production) Process time Move time Queue time 15.6 days 2.6 days 0.6 days 4.2 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.4 days 17.0 days 3.0 days 1.3 days 4.5 days Required: 1. Compute the throughput time. (Round your answer to...
a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...
a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...
manufacturing process
1) A customer order of 50 pieces one carat LGDs is to be processed through plant 1. Seed materials are supplied by the customer. The total time for processing the LGDs (including setup and other direct labor) is 500 hr. Direct labor cost is $25.00/hr. The factory overhead is 250% and the corporate overhead rate is 600%. Computer the cost of the job assumes the company's markup (profit) is 60%. 2) the following data are given: direct labor...
Dillon Products manufactures various machined parts to customer
specifications. The company uses a job-order costing system and
applies overhead costs to jobs on the basis of machine-hours. At
the beginning of the year, the company used a cost formula to
estimate that it would incur $4,170,000 in manufacturing overhead
cost at an activity level of 556,000 machine-hours. The company
spent the entire month of January working on a large order for
8,900 custom made machined parts. The company had no...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead costs to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,177,500 in manufacturing overhead cost at an activity level of 557,000 machine-hours. The company spent the entire month of January working on a large order for 8,400 custom made machined parts. The company had no...
Y our firm just received an order from a customer for $50,000 of widgets. You have been tasked with evaluating the effect of time value of money on your firm’s cash flows (on a transaction-bytransaction basis). To fulfill this order your firm will need to produce and transport the widgets. T his will take 50 days. Assume that the widgets will cost $30,000 in COGS; your firm is given 20 days to pay for the raw materials. Once the widgets...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time 0.2 days 16.2 days 3.2 days 1.4 days 4.1 days 09 Move time Queue time Required: 1. Compute the throughput time. (Round your answer...