Question

1. A machine costs $800,000 to purchase. It will produce a cash inflow of $200,000 in...

1. A machine costs $800,000 to purchase. It will produce a cash inflow of $200,000 in year 1, $400,000 in year 2, and $600,000 in year 3. The required return is 12 percent. Calculate the NPV

0 0
Add a comment Improve this question Transcribed image text
Answer #1

On your calculator, punch these figures

CF0 = (800,000)

C01 = 200,000

C02 = 400,000

C03 = 600,000

I = 12

CPT NPV = 124,517.1

Add a comment
Know the answer?
Add Answer to:
1. A machine costs $800,000 to purchase. It will produce a cash inflow of $200,000 in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 74. Rambus Inc. would like to purchase a production machine for $325.000, The machine is expected...

    74. Rambus Inc. would like to purchase a production machine for $325.000, The machine is expected to have a life of three years, and a salvage value of $50,000. Annual maintenance costs will total $12.500. Annual savings are predicted to be $112.50X). The company's required rate of return is 12 percent. (12 Points) Factors: Present Value of $1 ir=12%) Year 0 1.0XXX) Year! 0.8929 Year 2 0.7972 Year 3 0.7118 Required: (1) Using the Present Value Factors for SI, calculate...

  • you are operating an old machine that is expected to produce a cash inflow of $5100...

    you are operating an old machine that is expected to produce a cash inflow of $5100 in each of the next 3 years before it fails. You can replace it now with a new machine that costs $20,100 but is more efficient and will provide a cash flow of $10,150 a year for 4 years. Calculate the equivilant annual cost of the new machine if the discount rate is 14%.

  • You are operating an old machine that is expected to produce a cash inflow of $5,000...

    You are operating an old machine that is expected to produce a cash inflow of $5,000 in each of the next 3 years before it fails. You can replace it now with a new machine that costs $20,000 but is much more efficient and will provide a cash flow of $10,000 a year for 4 years. Calculate the equivalent annual cost of the new machine if the discount rate is 15%. (Do not round intermediate calculations. Round your answer to...

  • MKM International is seeking to purchase a new CNC machine in order to reduce costs. Two...

    MKM International is seeking to purchase a new CNC machine in order to reduce costs. Two alternative machines are in consideration Machine 1 costs $500,000 but yields a 10 percent savings (net benefit) over the current machine used. Machine 2 costs $900,000 but yields a 20 percent savings (net benefit) over the current machine used. In order to meet demand, the following forecasted cost information for the current machine is also provided. Year 1 2 3 4 5 Projected Cost...

  • MKM International is seeking to purchase a new CNC machine in order to reduce costs. Two...

    MKM International is seeking to purchase a new CNC machine in order to reduce costs. Two alternative machines are in consideration Machine 1 costs $500,000 but yields a 10 percent savings (net benefit) over the current machine used. Machine 2 costs $900,000 but yields a 20 percent savings (net benefit) over the current machine used. In order to meet demand, the following forecasted cost information for the current machine is also provided. Year 1 2 3 4 5 Projected Cost...

  • Table 2: Cash flows B Borehole Landfill $300,000 Inflow year 1 $450,000 $300,000 Inflow year 2...

    Table 2: Cash flows B Borehole Landfill $300,000 Inflow year 1 $450,000 $300,000 Inflow year 2 $450,000 $300,000 Inflow year 3 $450,000 Inflow year 4 $450,000 $450, 000 Inflow year 5 -$1 500, 000 Inflow year 6 Question 3 [20 marks] Environ Ltd has revised its estimates of expected after-tax cash flows as shown in Table 2. The initial outlays are $800,000 for the landfill and $250, 000 for the borehole. Environ Ltd maintains the required rate of return at...

  • Newton Inc. is evaluating the purchase of a new machine. The cost of the machine is...

    Newton Inc. is evaluating the purchase of a new machine. The cost of the machine is $800,000. The incremental cash flows due to the machine are expected to be as follows: Year 1              $150,000 Year 2              $250,000 Year 3              $350,000 Year 4              $480,000 The cost of capital for Newton, Inc. is 11%. 1. Calculate the NPV and IRR for this project. 2. Should you accept this project? Explain. Mention both NPV and IRR in your explanation. 3. At what costs...

  • Henrie’s Drapery Service is investigating the purchase of a new machine for cleaning and blocking drapes....

    Henrie’s Drapery Service is investigating the purchase of a new machine for cleaning and blocking drapes. The machine would cost $126,175, including freight and installation. Henrie’s has estimated that the new machine would increase the company’s cash inflows, net of expenses, by $35,000 per year. The machine would have a five-year useful life and no salvage value.    Click here to view Exhibit 13B-1 and Exhibit 13B-2, to determine the appropriate discount factor(s) using table.    Required: 1. Compute the...

  • A company is considering two projects. Project A Project B Initial investment $200,000 $200,000 Cash inflow...

    A company is considering two projects. Project A Project B Initial investment $200,000 $200,000 Cash inflow Year 1 $60,000 $90,000 Cash inflow Year 2 $60,000 $90,000 Cash inflow Year 3 $60,000 $40,000 Cash inflow Year 4 $60,000 $50,000 Cash inflow Year 5 $60,000 $70,000 What is the payback period for Project B? a. 4.5 years b. 3.5 years c. 2.5 years d. 2 years e. 3 years

  • MKM International is seeking to purchase a new CNC machine in order to reduce costs. Two...

    MKM International is seeking to purchase a new CNC machine in order to reduce costs. Two alternative machines are in consideration. Machine 1 costs $550,000, but yields a 15 percent savings over the current machine used. Machine 2 costs $850,000, but yields a 25 percent savings over the current machine used. In order to meet demand, the following forecasted cost information for the current machine is also provided. Year 1 2 3 4 Project Cost 1,000,000 1,350,000 1,450,000 1,500,000 2,400,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT