Question

Which one of the following is not generally regarded as part of the budgetary process? Select...

Which one of the following is not generally regarded as part of the budgetary process?

Select one:

Preparation of master budget.

Communication of objectives.

Designing an absorption costing system.

On-going review of budgets.

-

A company's budgeted variable overheads for a period amounted to £24,000. During this period, the company spent £23,760 on variable overheads.

The company’s level of production was expected to require 12,000 labour hours but the actual amount of labour hours used was only 10,800 hours.

What was the variable overhead expenditure variance for the period?

Calculate your answer to the nearest whole £ and enter it in the blank space provided.

Indicate an adverse variance (if appropriate) by placing a minus sign in front of the value (e.g., -500).

Answer the question by providing the appropriate number in the box below (e.g., 123456). Do not enter a dot, commas, spaces, letters, words or symbols (such as £). Failure to follow these instructions will result in the answer being marked as incorrect.

-

A company uses a standard costing system and the standard materials cost per unit of their product is £20. The actual level of production of this product for a period was 3,200 units. The company recorded the following variances during the period:

Material price variance: £500 favourable

Material usage variance: £1,500 favourable

What was the actual cost of the materials for the period?

Calculate your answer to the nearest whole £ and enter it in the blank space provided.

Answer the question by providing the appropriate number in the box below (e.g., 123456). Do not enter a dot, commas, spaces, letters, words or symbols (such as £). Failure to follow these instructions will result in the answer being marked as incorrect.

-

Which one of the following is not generally regarded as a functional budget?

Select one:

Cash budget

Selling and administration budget

Sales budget

Production budget

-

The following extract has been provided from a company’s performance report:

£
Sales volume variance 2,500 Adverse
Sales price variance 5,000 Favourable
Material usage variance 750 Favourable
Material price variance 1,000 Adverse

Which of the following statements could explain the performance? (Select one option only).

Select one:

More units have been sold than expected

The material wastage rate has been lower than expected

Material purchased is of poorer quality than expected.

Contribution per unit is lower than expected.

-

What is the main difference between a fixed and flexible budget?

Select one:

A flexible budget considers only variable costs, but a fixed budget considers all costs.

A fixed budget is produced for an entire organisation, but a flexible budget is applicable only to a single department.

Flexible budgets can provide less realistic control information than fixed budgets.

A fixed budget is based on a specific level of production/sales and a flexible budget can be prepared for any production level.

-

Which of the following statements is incorrect?

Select one:

A normal distribution curve is a frequency distribution that is symmetrical and bell shaped.

The following indicate how data is dispersed: standard deviation, mean, range, and variance.

A disadvantage of the arithmetic mean of a grouped frequency distribution is that its value may not correspond to any actual value in the frequency distribution.

A histogram is a pictorial representation of a grouped frequency distribution.

-

Which of the following statements are incorrect? (Select one option only).

Select one:

The median is a useful measure of the centre of a distribution because it is not affected by unusually high or low values.

A scatter chart is useful to identify whether there is correlation between two sets of data.

A pie chart is a useful method of illustrating the trend of profit over time.

A distribution with values clustered around the mean will have a smaller standard deviation than a distribution with values which are evenly spread.

-

Complete the following sentence using one of the four options below.


A scatter graph on which the points tend to  blank indicates positive correlation.

'Drag and drop' the correct option into the box

   

Match the statistical measure with its description by filling the blanks with the phrases below. You can do this by dragging and dropping, using your mouse.

The  blank measures the proportion of the total variation in the value of one variable that can be explained by the variations in the value of the other.
The  blank describes how two variables move together.
The  blank compares the dispersion of two distributions.
The  blank describes short-term fluctuations in recorded values.

1 seasonal variation, 2 co-effecient of determination 3 coorlation co-effecient 4 co-effecient of variation

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

Designing an absorption costing system is not generally regarded as part of the budgetary process.

2.

Variable overhead standard rate = £24,000 / 12,000 = £2 per hour

Variable overhead expenditure variance = Actual labour hours*Standard rate - Actual variable overhead

Variable overhead expenditure variance = 10,800*£2 - £23,760

Variable overhead expenditure variance = £21,600 - £23,760 = -£2,160 Adverse

3.

Let actual cost of material be x

Material price variance = Actual quantity*Standard price - Actual quantiy*Actual price

£500 = 3,200*£20 - x

x = £64,000 - 500 = £63,500

Hence, actual cost of material is £63,500

4.

Cash budget is not generally regarded as a functional budget.

Add a comment
Know the answer?
Add Answer to:
Which one of the following is not generally regarded as part of the budgetary process? Select...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following extract has been provided from a company’s performance report: £ Sales volume variance 2,500...

    The following extract has been provided from a company’s performance report: £ Sales volume variance 2,500 Adverse Sales price variance 5,000 Favourable Material usage variance 750 Favourable Material price variance 1,000 Adverse Which of the following statements could explain the performance? (Select one option only). Select one: More units have been sold than expected The material wastage rate has been lower than expected Material purchased is of poorer quality than expected. Contribution per unit is lower than expected. - What...

  • Using marginal cost format, prepare a flexible budget for 17,200 units and show all the variances...

    Using marginal cost format, prepare a flexible budget for 17,200 units and show all the variances indicating which are favourable and which are adverse. Suggest a possible reason for each variance. [14 marks] b) Flexible budgets have been prepared for two output levels as follows; Production and sales 15000 20000 Sales revenue £ 150000 200000 Direct materials Direct labour Depreciation Maintenance 105000 15000 1500 2000 140000 20000 1500 2400 Total costs 123500 163900 Profit 26500 36100 Actual production and sales...

  • 24. Standard costing can be used to apply costs for which of the following? Select one...

    24. Standard costing can be used to apply costs for which of the following? Select one Direct Materials b. Direct Labor Indirect Materials and Indirect Labor c d. Factory Utilities All of the above can be applied using standard costing a. Tab e 25. Reasons for using standard costing include their usefulness in: Select one: Caps L a. Preparing flexible budgets b. Preparing master budgets c Establishing selling prices d. Preparing performance reports e All of the above Shift 1...

  • Question 3 Not yet answered Marked out of 1.00 Flag question A company uses a standard...

    Question 3 Not yet answered Marked out of 1.00 Flag question A company uses a standard costing system and the standard materials cost per unit of their product is £20. The actual level of production of this product for a period was 3.200 units. The company recorded the following variances during the period: Material price variance: £500 favourable Material usage variance: £1.500 favourable What was the actual cost of the materials for the period? Calculate your answer to the nearest...

  • Q3. (a) Distinguish between 'budgetary planning' and 'budgetary control (4 marks) (b) Why should organisations ensure...

    Q3. (a) Distinguish between 'budgetary planning' and 'budgetary control (4 marks) (b) Why should organisations ensure that they have robust budgeting processes? (4 marks) (c) Flexible budgets have been prepared for two output levels as follows Production and sales (units) 25000 40000 Sales revenue 500000 800000 Direct materials Direct labour Depreciation Maintenance 200000 150000 3500 3000 320000 240000 3500 3600 Total costs 356500 567100 Profit 143500 232900 Actual production and sales were 36000 units and actual costs and revenues were...

  • 25. Reasons for using standard costing include their usefulness in: Select one: a. Preparing flexible budgets...

    25. Reasons for using standard costing include their usefulness in: Select one: a. Preparing flexible budgets b. Preparing master budgets C. Establishing selling prices d. Preparing performance reports e. All of the above 26. The standard direct material cost is equal to: Select one: a. Standard quantity * Actual price b. Actual quantity Standard price c. Actual quantity - Actual price d. Standard quantity Standard price e. None of the above 27. Which of the following accurately represents the "split...

  • Mark: 19 (1 point for each question) 1) The unemployment rate is high in the city...

    Mark: 19 (1 point for each question) 1) The unemployment rate is high in the city in which a company has a factory. The company finds that they are able to pay new employees a lower wage per hour than when the unemployment rate was lower a year ago. Which variance is directly impacted? A) Materials price variance B) Materials efficiency variance C) Labour price variance D) Labour efficiency variance 2) Thomas Corporation produces stopwatches. According to company standards, it...

  • Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0...

    Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) $ 24.00 Direct labor (1.9 hrs. @ $13.00 per hr.) 24.70 Overhead (1.9 hrs. @ $18.50 per hr.) 35.15 Total standard cost $ 83.85 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per month...

  • Part 1 of 2 Required information The following information applies to the questions displayed below) Brodrick...

    Part 1 of 2 Required information The following information applies to the questions displayed below) Brodrick Company expects to produce 20100 units for the year ending December 31. A flexible budget for 20,100 units of production reflects sales of $582.900: variable costs of $60,300; and fixed costs of $143,000. If the company instead expects to produce and sell 26,600 units for the year, calculate the expected level of income from operations Flexible Budget Flexible Budget at Total Fixed Variable Amount...

  • Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib....

    Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib.) Direct labor (1.8 hrs. @ $11.00 per hr.) Overhead (1.8 hrs. @ $18.50 per hr.) Total standard cost $20.00 19.80 33.30 $73.10 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT