The following extract has been provided from a company’s performance report: £ Sales volume variance 2,500...

The following extract has been provided from a company’s performance report:

£
Sales volume variance 2,500 Adverse
Sales price variance 5,000 Favourable
Material usage variance 750 Favourable
Material price variance 1,000 Adverse

Which of the following statements could explain the performance? (Select one option only).

Select one:

More units have been sold than expected

The material wastage rate has been lower than expected

Material purchased is of poorer quality than expected.

Contribution per unit is lower than expected.

-

What is the main difference between a fixed and flexible budget?

Select one:

A flexible budget considers only variable costs, but a fixed budget considers all costs.

A fixed budget is produced for an entire organisation, but a flexible budget is applicable only to a single department.

Flexible budgets can provide less realistic control information than fixed budgets.

A fixed budget is based on a specific level of production/sales and a flexible budget can be prepared for any production level.

-

Which of the following statements is incorrect?

Select one:

A normal distribution curve is a frequency distribution that is symmetrical and bell shaped.

The following indicate how data is dispersed: standard deviation, mean, range, and variance.

A disadvantage of the arithmetic mean of a grouped frequency distribution is that its value may not correspond to any actual value in the frequency distribution.

A histogram is a pictorial representation of a grouped frequency distribution.

-

Which of the following statements are incorrect? (Select one option only).

Select one:

The median is a useful measure of the centre of a distribution because it is not affected by unusually high or low values.

A scatter chart is useful to identify whether there is correlation between two sets of data.

A pie chart is a useful method of illustrating the trend of profit over time.

A distribution with values clustered around the mean will have a smaller standard deviation than a distribution with values which are evenly spread.

-

Complete the following sentence using one of the four options below.


A scatter graph on which the points tend to  blank indicates positive correlation.

'Drag and drop' the correct option into the box

   

Match the statistical measure with its description by filling the blanks with the phrases below. You can do this by dragging and dropping, using your mouse.

The  blank measures the proportion of the total variation in the value of one variable that can be explained by the variations in the value of the other.
The  blank describes how two variables move together.
The  blank compares the dispersion of two distributions.
The  blank describes short-term fluctuations in recorded values.

1 seasonal variation, 2 co-effecient of determination 3 coorlation co-effecient 4 co-effecient of variation

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Which of the following statements could explain the performance? (Select one option only).
The material wastage rate has been lower than expected
What is the main difference between a fixed and flexible budget?
A fixed budget is based on a specific level of production/sales and a flexible budget can be prepared for any production level.
Which of the following statements is incorrect?
A histogram is a pictorial representation of a grouped frequency distribution.
Because it is a graphical representation and not pictorial representation.
Which of the following statements are incorrect?
A distribution with values clustered around the mean will have a smaller standard deviation than a distribution with values which are evenly spread.
Complete the following sentence using one of the four options below.
A scatter graph on which the points tend to blank indicates positive correlation.
The blank measures the proportion of the total variation in the value of one variable that can be explained by the variations in the value of the other.
Add a comment
Know the answer?
Add Answer to:
The following extract has been provided from a company’s performance report: £ Sales volume variance 2,500...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Which one of the following is not generally regarded as part of the budgetary process? Select...

    Which one of the following is not generally regarded as part of the budgetary process? Select one: Preparation of master budget. Communication of objectives. Designing an absorption costing system. On-going review of budgets. - A company's budgeted variable overheads for a period amounted to £24,000. During this period, the company spent £23,760 on variable overheads. The company’s level of production was expected to require 12,000 labour hours but the actual amount of labour hours used was only 10,800 hours. What...

  • Question 9 The sales volume variance is the difference between the Not yet answered Select one:...

    Question 9 The sales volume variance is the difference between the Not yet answered Select one: Marked out of 2.00 Flag question O A. expected results in the flexible budget for the actual units sold and the static budget B. static budget and actual amounts due to differences in sales price O C. actual results and the expected results in the flexible budget for the actual units sold OD. flexible budget and static budget due to differences in fixed costs...

  • Roland Company's managers received the following incomplete performance report FR (Click the icon to view the...

    Roland Company's managers received the following incomplete performance report FR (Click the icon to view the incomplete performance report.) Cd Data Table performance report Identity the employee group that may deserve praise and the group that may be subject to criticism Give your reasons. Complete the performance report (For accounts with a zero balance, make sure to enter "o" in the appropriate cell. Label each variance as favourable (F or unfavourable (U). If the variance is zero, do not select...

  • 1. Prepare a flexible budget. 2. Compute the sales volume variance and the variable cost volume...

    1. Prepare a flexible budget. 2. Compute the sales volume variance and the variable cost volume variances based on a comparison between the master budget and the flexible budget 3.Compute flexible budget variances by comparing the flexible budget with the actual results. 4.Summarize the results of the sales volume and variable cost volume variances computations based on the comparison between the master budget and the flexible budget. 5.Summarize the results of the flexible budget variances computations based on the comparison...

  • Question 17 )The sales volume variance is the differernc between the ? A) Actual results and the expected results in t...

    Question 17 )The sales volume variance is the differernc between the ? A) Actual results and the expected results in the flexible budget for the actual units sold B)Expected results in the flexible budget for the actual units sold and the static budget c)Static budget and actual amounts due to differences in sales price d)flexible budget and static budget due to differences in fixed costs Question 18 )Generals Co.can further process Product B to Product product A. product B currently...

  • The following data were drawn from the records of Solomon Corporation. Planned volume for year (static...

    The following data were drawn from the records of Solomon Corporation. Planned volume for year (static budget) Standard direct materials cost per unit Standard direct labor cost per unit Total expected fixed overhead costs Actual volume for the year (flexible budget) Actual direct materials cost per unit Actual direct labor cost per unit Total actual fixed overhead costs 4,100 units 4.00 pounds @ $1.60 per pound 2.10 hours @ $5.00 per hour $ 18,450 4,500 units 3.60 pounds @ $2.00...

  • The following data were drawn from the records of Perez Corporation. Planned volume for year (static budget) Standard d...

    The following data were drawn from the records of Perez Corporation. Planned volume for year (static budget) Standard direct materials cost per unit Standard direct labor cost per unit Total expected fixed overhead costs Actual volume for the year (flexible budget) Actual direct materials cost per unit Actual direct labor cost per unit Total actual fixed overhead costs 3,400 units 3.50 pounds @ $1.50 per pound 2.30 hours @ $3.30 per hour $14,620 3,900 units 3.10 pounds @ $2.00 per...

  • One subunit of Field Sports Company had the following financial results last month: (Click the icon...

    One subunit of Field Sports Company had the following financial results last month: (Click the icon to view the financial results.) Read the requirements Requirement 1. Complete the performance evaluation report for the subunit. (Enter a variance for each account as a positive number and select whether the variance is favorable or unfavorable. Enter the variance percent as a percentage rounded to two decimal places, X.XX%) Actual Flexible Flexible Budget % Variance Subunit x Results Budget Variance (For U) (For...

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

  • Problem 1 Tallahassee Clinic projected the following budget information for 2018: Total FFS Visit Volume 90,000...

    Problem 1 Tallahassee Clinic projected the following budget information for 2018: Total FFS Visit Volume 90,000 visits Payer Mix:      Blue Cross 40%      Celtic Insurance Company 60% Reimbursement Rates:      Blue Cross $25 per visit      Celtic Insurance Company $20 per visit Variable Costs – Resource Inputs:       Labor 48,000 total hours       Supplies 100,000 total units Variable Costs – Input Prices:        Labor $25 per hour        Supplies $1.50 per unit Fixed Costs (overhead, plant, and equipment) $500,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT