24)
The correct answer is e) All of the above can be applied using standard costing
Supporting explanations:
Standard costing system is used to Direct Materials, Direct Labor, indirect materials & labor, (variable and fixed overheads) and factory supplies to compare with the actual results in order to calculate the variances in terms of favorable and unfavorable.
Therefore, standard costing is used for all of the categories mentioned, hence, the correct answer is e.
24. Standard costing can be used to apply costs for which of the following? Select one...
25. Reasons for using standard costing include their usefulness in: Select one: a. Preparing flexible budgets b. Preparing master budgets C. Establishing selling prices d. Preparing performance reports e. All of the above 26. The standard direct material cost is equal to: Select one: a. Standard quantity * Actual price b. Actual quantity Standard price c. Actual quantity - Actual price d. Standard quantity Standard price e. None of the above 27. Which of the following accurately represents the "split...
Caps L Shift 29. The difference between the split cost and the standard cost for direct materials is called the Select one a Materials Price Variance b Materials Usage Variance eMaterials Eficiency Variance d. Materials Budget Variance e None of the above 30. Which of the following could cause a variable overhead flexible budget variance? a Varlable overhead costs being greater than expected for the given driver usage Select one: b. Variable overhead costs being less than expected for the...
Tab - erhead can be calculated as 3. The Standard Cost Driverage for vare Select one: a Split Cost Actual Application Mate b. Split Cost/Standard Application Rate Actual Cost / Standard Application rate d Standard Cost/Actual Application Rate e None of the above Caps Loch ht SS. Under estimating production levels will likely lead to Select one: a. Unfavorable flexible budget variances b. Favorable flexible budget variances C Unfavorable static budget variances d. Favorable static budget variances e. None of...
Antuan Company set the following standard costs for one unit of its product. Direct materials (3.0 Ibs. @ $6.00 per Ib.) $18.00 Direct labor (1.8 hrs. @ $11.00 per hr.) 19.80 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $71.10 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at the...
Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...
Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib.) Direct labor (1.6 hrs. @ $13.00 per hr.) Overhead (1.6 hrs. @ $18.50 per hr.) Total standard cost $20.00 20.80 29.60 $ 70.40 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at...
Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...
Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) $ 24.00 Direct labor (1.9 hrs. @ $13.00 per hr.) 24.70 Overhead (1.9 hrs. @ $18.50 per hr.) 35.15 Total standard cost $ 83.85 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per month...
1 Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor- hours and its standard cost card per unit is as follows: 2 3 4. 5 6 7 (1) (2) Standard Standard Quantity Price or Hours or Rate 5 pounds $8.00 per pound 2 hours $14 per hour 2 hours $5 per hour 8 Inputs Direct materials Direct labor Variable overhead Total standard cost per unit Standard Cost (1) (2) $40.00 28.00 10.00...
The following data were drawn from the records of Perez Corporation. Planned volume for year (static budget) Standard direct materials cost per unit Standard direct labor cost per unit Total expected fixed overhead costs Actual volume for the year (flexible budget) Actual direct materials cost per unit Actual direct labor cost per unit Total actual fixed overhead costs 3,400 units 3.50 pounds @ $1.50 per pound 2.30 hours @ $3.30 per hour $14,620 3,900 units 3.10 pounds @ $2.00 per...