Question

We are evaluating a project that costs $744,000, has a six-year life, and has no salvage value. Assume that depreciation is s

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Best case

Time line 0 1 2 3 4 5 6
Cost of new machine -744000
=Initial Investment outlay -744000
100.00%
Unit sales 49500 49500 49500 49500 49500 49500
Profits =no. of units sold * (sales price - variable cost) 2376000 2376000 2376000 2376000 2376000 2376000
Fixed cost -666000 -666000 -666000 -666000 -666000 -666000
-Depreciation Cost of equipment/no. of years -124000 -124000 -124000 -124000 -124000 -124000 0 =Salvage Value
=Pretax cash flows 1586000 1586000 1586000 1586000 1586000 1586000
-taxes =(Pretax cash flows)*(1-tax) 1030900 1030900 1030900 1030900 1030900 1030900
+Depreciation 124000 124000 124000 124000 124000 124000
=after tax operating cash flow 1154900 1154900 1154900 1154900 1154900 1154900
+Tax shield on salvage book value =Salvage value * tax rate 0
=Terminal year after tax cash flows 0
Total Cash flow for the period -744000 1154900 1154900 1154900 1154900 1154900 1154900
Discount factor= (1+discount rate)^corresponding period 1 1.18 1.3924 1.643032 1.9387778 2.2877578 2.6995542
Discounted CF= Cashflow/discount factor -744000 978728.8136 829431.1979 702907.7949 595684.57 504817.43 427811.38
NPV= Sum of discounted CF= 3295381.20

Worst case

Time line 0 1 2 3 4 5 6
Cost of new machine -744000
=Initial Investment outlay -744000
100.00%
Unit sales 40500 40500 40500 40500 40500 40500
Profits =no. of units sold * (sales price - variable cost) 1296000 1296000 1296000 1296000 1296000 1296000
Fixed cost -814000 -814000 -814000 -814000 -814000 -814000
-Depreciation Cost of equipment/no. of years -124000 -124000 -124000 -124000 -124000 -124000 0 =Salvage Value
=Pretax cash flows 358000 358000 358000 358000 358000 358000
-taxes =(Pretax cash flows)*(1-tax) 232700 232700 232700 232700 232700 232700
+Depreciation 124000 124000 124000 124000 124000 124000
=after tax operating cash flow 356700 356700 356700 356700 356700 356700
+Tax shield on salvage book value =Salvage value * tax rate 0
=Terminal year after tax cash flows 0
Total Cash flow for the period -744000 356700 356700 356700 356700 356700 356700
Discount factor= (1+discount rate)^corresponding period 1 1.18 1.3924 1.643032 1.9387778 2.2877578 2.6995542
Discounted CF= Cashflow/discount factor -744000 302288.1356 256176.3861 217098.6323 183981.89 155916.86 132132.93
NPV= Sum of discounted CF= 503594.83
Add a comment
Know the answer?
Add Answer to:
We are evaluating a project that costs $744,000, has a six-year life, and has no salvage...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage...

    We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 75,000 units per year. Price per unit is $52, variable cost per unit is $36, and fixed costs are $750,000 per year. The tax rate is 21 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $2,070,000, has a 7-year life, and has no salvage...

    We are evaluating a project that costs $2,070,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 93,400 units per year. Price per unit is $38.73, variable cost per unit is $23.85, and fixed costs are $854,000 per year. The tax rate is 23 percent and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $2,010,000, has a 7-year life, and has no salvage...

    We are evaluating a project that costs $2,010,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 89,400 units per year. Price per unit is $38.61, variable cost per unit is $23.75, and fixed costs are $848,000 per year. The tax rate is 21 percent and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $2.130,000, has a 8-year life, and has no salvage...

    We are evaluating a project that costs $2.130,000, has a 8-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90,600 units per year. Price per unit is $38.85, variable cost per unit is $23.95, and fixed costs are $860,000 per year. The tax rate is 25 percent and we require a return of 11 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $2,040,000, has a 7-year life, and has no salvage...

    We are evaluating a project that costs $2,040,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 89,700 units per year. Price per unit is $38.67, variable cost per unit is $23.80, and fixed costs are $851,000 per year. The tax rate is 22 percent and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage...

    We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 39,000 units per year. Price per unit is $41, variable cost per unit is $20, and fixed costs are $645,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $1,120,000, has a ten-year life, and has no salvage...

    We are evaluating a project that costs $1,120,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight- line to zero over the life of the project. Sales are projected at 64,000 units per year. Price per unit is $50, variable cost per unit is $25, and fixed costs are $620,000 per year. The tax rate is 35 percent, and we require a return of 12 percent on this project. Suppose the projections given for price,...

  • We are evaluating a project that costs $569,100, has a six-year life, and has no salvage...

    We are evaluating a project that costs $569,100, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 85,000 units per year. Price per unit is $40, variable cost per unit is $26, and fixed costs are $690,000 per year. The tax rate is 24 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage...

    We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 75,000 units per year. Price per unit is $52, variable cost per unit is $36, and fixed costs are $750,000 per year. The tax rate is 21 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $924,000, has an eight-year life, and has no salvage...

    We are evaluating a project that costs $924,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 75,000 units per year. Price per unit is $46, variable cost per unit is $31, and fixed costs are $825,000 per year. The tax rate is 35 percent, and we require a 15 percent return on this project. Suppose the projections given for price, quantity, variable...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT