Question

We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage...

We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 75,000 units per year. Price per unit is $52, variable cost per unit is $36, and fixed costs are $750,000 per year. The tax rate is 21 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±15 percent.

  

Calculate the best-case and worst-case NPV figures. (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

Best Case:?

Worst Case: -3569554.68

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Here, we need to find best-case and worst-case NPV figures
Sales are projected at 75000 units per year
The projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±15 percent
Let's case other two cases as +15% from projected sales and -15% from projected sales
Sales projections would be as follows:
75000-15% of 75000=63750 units
75000+15% of 75000=86250 units
NPV=Present value of cash inflows-Initial investment
63750
units
75000
units
86250
units
Sales revenue ($52 per unit) 3315000 3900000 4485000
Less: variable cost ($36 per unit) 2295000 2700000 3105000
Contribution margin 1020000 1200000 1380000
Less:
Fixed cost 750000 750000 750000
Depreciation (788400/9) 87600 87600 87600
Income before taxes 182400 362400 542400
Less: Tax at 21% 38304 76104 113904
Net income 144096 286296 428496
Add: Depreciation 87600 87600 87600
Cash inflow 231696 373896 516096
Present value @12% for 9 years 5.3283 5.3283 5.3283
Present value of cash inflow 1234546 1992230 2749914
Less: Initial investment 788400 788400 788400
NPV 446146 1203830 1961514
Worst Best
case case
Add a comment
Know the answer?
Add Answer to:
We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage...

    We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 75,000 units per year. Price per unit is $52, variable cost per unit is $36, and fixed costs are $750,000 per year. The tax rate is 21 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $924,000, has an eight-year life, and has no salvage...

    We are evaluating a project that costs $924,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 75,000 units per year. Price per unit is $46, variable cost per unit is $31, and fixed costs are $825,000 per year. The tax rate is 35 percent, and we require a 15 percent return on this project. Suppose the projections given for price, quantity, variable...

  • We are evaluating a project that costs $2,070,000, has a 7-year life, and has no salvage...

    We are evaluating a project that costs $2,070,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 93,400 units per year. Price per unit is $38.73, variable cost per unit is $23.85, and fixed costs are $854,000 per year. The tax rate is 23 percent and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $2,010,000, has a 7-year life, and has no salvage...

    We are evaluating a project that costs $2,010,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 89,400 units per year. Price per unit is $38.61, variable cost per unit is $23.75, and fixed costs are $848,000 per year. The tax rate is 21 percent and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $2.130,000, has a 8-year life, and has no salvage...

    We are evaluating a project that costs $2.130,000, has a 8-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90,600 units per year. Price per unit is $38.85, variable cost per unit is $23.95, and fixed costs are $860,000 per year. The tax rate is 25 percent and we require a return of 11 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $2,040,000, has a 7-year life, and has no salvage...

    We are evaluating a project that costs $2,040,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 89,700 units per year. Price per unit is $38.67, variable cost per unit is $23.80, and fixed costs are $851,000 per year. The tax rate is 22 percent and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $744,000, has a six-year life, and has no salvage...

    We are evaluating a project that costs $744,000, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 45,000 units per year. Price per unit is $60, variable cost per unit is $20, and fixed costs are $740,000 per year. The tax rate is 35 percent, and we require a return of 18 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage...

    We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 39,000 units per year. Price per unit is $41, variable cost per unit is $20, and fixed costs are $645,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project. Suppose the projections given for price, quantity,...

  • We are evaluating a project that costs $1,120,000, has a ten-year life, and has no salvage...

    We are evaluating a project that costs $1,120,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight- line to zero over the life of the project. Sales are projected at 64,000 units per year. Price per unit is $50, variable cost per unit is $25, and fixed costs are $620,000 per year. The tax rate is 35 percent, and we require a return of 12 percent on this project. Suppose the projections given for price,...

  • We are evaluating a project that costs $1,140,000, has a ten-year life, and has no salvage...

    We are evaluating a project that costs $1,140,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 51,000 units per year. Price per unit is $42, variable cost per unit is $20, and fixed costs are $720,000 per year. The tax rate is 35 percent, and we require a return of 18 percent on this project. Suppose the projections given for price, quantity,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT