Question

The developer and owner of a shopping mall is planning to install solar PV panels on...

The developer and owner of a shopping mall is planning to install solar PV panels on the roof top. Project Costs: The 100-kw system will cost $225,000 to install on 600 m2 of space available on the roof top. It will have a useful life 20 years and a salvage value of $2,000. Annual operations and maintenance cost will be $1,500. Energy output: Based on Singapore weather conditions, the system is capable of producing 170,000 kwh of electricity in the first year of operation. However, this output will degrade at a rate of 2% per year through its useful life. The electricity produced will be sold to either the shopping mall’s tenants or to the power grid at 18 cents per kwh. Project Financing: 60% of the initial system cost will be financed via a 5-year bank loan at an interest rate of 5% per year. The loan will be repaid with 5 equal end-of-year payments starting at the end of the first year. The other 40% of the initial project cost will be financed with company’s equity capital. The company computes the WACC and determines that MARR should be10% for the purpose of evaluating the feasibility of this project

(a) What is the annual repayment amount for the bank loan?

(b) What is the Present Worth of the project? Is the project financially feasible?

(c) What is the IRR of the project?

(d) The Levelized Cost of Energy (LCOE) is the “average” equivalent cost of installing and operating an energy generation asset, per unit of total energy generated over the useful life. Equivalently, LCOE is the constant sale price of electricity generated that makes PW = 0. Determine the LCOE of the proposed solar PV project in cents/kwh.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
a) Working
Financed by Bank Loan= $             1,35,000 225,000*60%
PVAF=                         4.33 PV(5%,5,-1,,0)
EMI= $          31,181.60
Annual repayment amount for the bank loan $          31,181.60
b)
EMI $                31,182
PVAF @10%                         3.79
PV of Bank Loan repaid $             1,18,203
Add: Balance 40% cost $                90,000 225000*40%
PV of outflows $             2,08,203
Year Output Rate ($) Inflows Maintence cost PV @10%
1                 1,70,000 $              0.18 $          30,600 $                        1,500 $            26,455
2                 1,66,600 $              0.18 $          29,988 $                        1,500 $            23,544
3                 1,63,268 $              0.18 $          29,388 $                        1,500 $            20,953
4                 1,60,003 $              0.18 $          28,800 $                        1,500 $            18,647
5                 1,56,803 $              0.18 $          28,224 $                        1,500 $            16,594
6                 1,53,667 $              0.18 $          27,660 $                        1,500 $            14,767
7                 1,50,593 $              0.18 $          27,107 $                        1,500 $            13,140
8                 1,47,581 $              0.18 $          26,565 $                        1,500 $            11,693
9                 1,44,630 $              0.18 $          26,033 $                        1,500 $            10,405
10                 1,41,737 $              0.18 $          25,513 $                        1,500 $              9,258
11                 1,38,902 $              0.18 $          25,002 $                        1,500 $              8,237
12                 1,36,124 $              0.18 $          24,502 $                        1,500 $              7,329
13                 1,33,402 $              0.18 $          24,012 $                        1,500 $              6,521
14                 1,30,734 $              0.18 $          23,532 $                        1,500 $              5,802
15                 1,28,119 $              0.18 $          23,061 $                        1,500 $              5,162
16                 1,25,557 $              0.18 $          22,600 $                        1,500 $              4,592
17                 1,23,046 $              0.18 $          22,148 $                        1,500 $              4,085
18                 1,20,585 $              0.18 $          21,705 $                        1,500 $              3,634
19                 1,18,173 $              0.18 $          21,271 $                        1,500 $              3,233
20                 1,15,810 $              0.18 $          20,846 $                        1,500 $              2,876
$         2,16,925
Add: Salvage value at PV $                  297
PV of Inflows $         2,17,222
PV of Outflows $         2,08,203
Present worth of Project $              9,019
Yes, Project is financially feasible
c)
At 11% discounting above figures
PV of Inflows $         2,04,196
PV of Outflows $         2,08,203
Present worth of Project $                       -4,006
PV at 10%= $                  9,019
PV at 10.50%= $                 -4,006
IRR= R1+ (NPV1*(R2-R1))/(NPV1-NPV2)
IRR= 10+ (9019*(11-10))/(9019+4006)
IRR= 10+                   0.69
IRR= 10.69%
d)
LCOE= Sum of costs over Lifetime/sum of electrical energy produced over lifetime
LCOE= (225000+1500*20-2000)/(2825332)
LCOE= $                    0.09

Please Like the solution if satisfied with the answer and if any query please mention it in comments...thanks

Add a comment
Know the answer?
Add Answer to:
The developer and owner of a shopping mall is planning to install solar PV panels on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question The developer and owner of a shopping mall is planning to install solar PV panels...

    Question The developer and owner of a shopping mall is planning to install solar PV panels on the roof top. Project Costs: The 100-kw system will cost $225,000 to install on 600 m2 of space available on the roof top. It will have a useful life 20 years and a salvage value of $2,000. Annual operations and maintenance cost will be $1,500. Energy output: Based on Singapore weather conditions, the system is capable of producing 170,000 kwh of electricity in...

  • A university spent $1.8 million to install solar panels atop a parking garage. These panels will...

    A university spent $1.8 million to install solar panels atop a parking garage. These panels will have a capacity of 500kw, have a life expectancy of 20 years and suppose the discount rate is 10%. a. If electricity can be purchased for costs of $0.10 per kwh, how many hours per year will the solar panels have to operate to make this project break even? b. If efficient systems operate for 2400 hours per year, would the project break even?...

  • A university spent $2 million to install solar panels atop a parking garage. These panels will...

    A university spent $2 million to install solar panels atop a parking garage. These panels will have a capacity of 800 kilowatts (kW) and have a life expectancy of 20 years. Suppose that the discount rate is 10%, that electricity can be purchased at $0.30 per kilowatt-hour (kWh), and that the marginal cost of electricity production using the solar panels is zero. Hint: It may be easier to think of the present value of operating the solar panels for 1...

  • A university spent $1.9 million to install solar panels atop a parking garage. These panels will...

    A university spent $1.9 million to install solar panels atop a parking garage. These panels will have a capacity of 300 kilowatts (kW) and have a life expectancy of 20 years. Suppose that the discount rate is 20%, that electricity can be purchased at $0.10 per kilowatt-hour (kWh), and that the marginal cost of electricity production using the solar panels is zero. Hint: It may be easier to think of the present value of operating the solar panels for 1...

  • Need helps on parts B, C, E,and F Costs of installing rooftop solar PV : Calculate...

    Need helps on parts B, C, E,and F Costs of installing rooftop solar PV : Calculate out-of-pocket costs and payback time for a rooftop solar installation. Assume that this PV system measures 6 m x 5 m and that the panels are 20% efficient. (a) Peak power rating: The solar industry describes the “peak wattage” of a PV system as its power output at a hypothetical, industry-standard irradiance of 1000 W/m2. What would be the peak wattage (in W) of...

  • 4. For an energy source with constant energy production and no operating cost, the levelized cost...

    4. For an energy source with constant energy production and no operating cost, the levelized cost of energy (LCOE) per kilowatt hour (kWh) can be calculated as: annualized capital cost annual kWh production The annualized capital cost is like a mortgage payment, an annual cost that includes paying both the principle and interest (or opportunity cost of capital) over the life of a project. This can be calculated as: Annualized capital cost = K where K is the capital cost,...

  • 4. Individual Problems 5-4 A university spent $1.6 million to install solar panels atop a parking...

    4. Individual Problems 5-4 A university spent $1.6 million to install solar panels atop a parking garage. These panels will have a capacity of 400 kilowatts (kW) and have a life expectancy of 20 years. Suppose that the discount rate is 10%, that electricity can be purchased at $0.10 per kilowatt-hour (kWh), and that the marginal cost of electricity production using the solar panels is zero. Hint: It may be easier to think of the present value of operating the...

  • Should you install solar panels on your home? The cost of the panels is $20,000 today...

    Should you install solar panels on your home? The cost of the panels is $20,000 today and will save $1,500 per year on average for 25 years. In addition, assume you are eligible for a 30% tax credit on installation cost (assume received in one year). What is the NPV, IRR and payback of the solar panels for 25 years (useful life). Hint: Treat the savings as a cash inflow. Cost Today (T=0) $20,000 No loan Annual Savings (T=1-25) $1,500...

  • A medium scale (125 kW installed capacity) PV solar project costs $450,000 and has 200 MWh...

    A medium scale (125 kW installed capacity) PV solar project costs $450,000 and has 200 MWh estiamted annual energy production value in Charlotte NC. The electricity is sold to the grid at $ 0.15 / kWh, paid at the location of solar system (no transmission cost). The project has a 20 year time horizon with salvage value of $ 22 thousand, and the MARR is 6 %. 1. a. Calculate the NPV of the project. b. Indicate if the project...

  • (7 pts) You are installing a 6-kW photovoltalc system that is expected to generate an average of 12,000 kWh per year fo...

    (7 pts) You are installing a 6-kW photovoltalc system that is expected to generate an average of 12,000 kWh per year for 25 years. The system will cost $3.80/Watt to install, then you receive a Federal Residential Renewable Energy Tax Credit for 30% of the installation cost. Your only additional cost over the system life will be to replace the inverter once for $2.500. How much will the solar-generated electricity cost over the life of the system measured in S/kWh?...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT