Question

Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

a. Using the tax shield approach, the OCF is

OCF = [(P-VC)Qc - FC (1 – t) ++*D

OCF = [(308 - 205) (27,000) - 1,100,000] (1 - 0.23)] + 0.23 (4,600,000/5)

OCF = 1,371,490

To calculate the sensitivity to changes in quantity sold, we will choose a quantity of 28,000. The OCF at this level of sale is

OCF = [(P-VC)Qc - FC (1 – t) ++*D

OCF = [(308 - 205) (28,000) - 1,100,000] (1 - 0.23)] + 0.23 (4,600,000/5)

OCF = 1,442,560

The sensitivity of changes in quantity sold is

AOCFAQ = (1,371,490 - 1,442,560)/(27,000 - 28,000)

AOCFAQ = +71.07

----------------------------------------------------------------------------------------------------------------------------------------------------

b. The NPV is calculated using the following equation

NPV = -Initial Investment – NWC + (P-VC)Q(PVIFAQI, n) + NWC + SV (1 – t)(PVIFOin)

NPV = -4,600,000 - 440,000 + [(308 - 205) (27,000)] (PVIFA @ 12%, 5) + [440,000 + (475,000) (1 - 0.23)] (PVIF @ 12%, 5)

NPV = -5,040,000 + 2,781,000 (PVIFA @ 12%, 5) + 805,750 (PVIF @ 12%, 5)

NPV = -5,040,000 + 2,781,000 (3.60478) + 805,750 (0.56743)

NPV = $5,442,087

At Q = 28,000, the NPV is

NPV = -4,600,000 - 440,000 + [(308 - 205) (28,000)] (PVIFA @ 12%, 5) + [440,000 + (475,000) (1 - 0.23)] (PVIF @ 12%, 5)

NPV = -5,040,000 + 2,884,000 (PVIFA @ 12%, 5) + 805,750 (PVIF @ 12%, 5)

NPV = -5,040,000 + 2,884,000 (3.60478) + 805,750 (0.56743)

NPV = $5,813,379

The sensitivity of NPV to changes in quantity sold is

ΔNPV/ΔΟ = (5,442,087 - 5,813,379)/(27,000 - 28,000)

ΔNPV/ΔΟ = + 371.29

----------------------------------------------------------------------------------------------------------------------------------------------------

c. We know that quantity will not fall below the point where NPV is zero. Therefore,

5,442,087 = 371.29 Q

Q = 14,657

For zero, we need to decrease the sales by 14,657

Minimum level of output = 27,000 - 14,657 = 12,343

Add a comment
Know the answer?
Add Answer to:
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $6,000,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,450,000 and that variable costs should be $275 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,250,000 and that variable costs should be $235 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,600,000 Investment in threading equipment to get the project started, the project will last for 4 years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset Investment straight-line to zero over the 4-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production. You will need an initial $5,900,000 investment in threading equipment to get the project started, the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,425,000 and that variable costs should be $270 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started: the project will last for 5 vears. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Chapter 11 Problemsi Saved 10 Consider a project to supply Detroit with 27,000 tons of machine...

    Chapter 11 Problemsi Saved 10 Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,000,000 investment in threading equipment to get the project started, the project Will last for 5 years. The accounting department estimates that annual fixed costs willl be $1,200,000 and that variable costs should be $225 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,700,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,375,000 and that variable costs should be $260 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT