Question

Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) Change in OCF/Change in Q

This ratio measures the Change in Operating Cash flow for every unit change in Quantity.

Based on 27000 tons of screws to be manufactured, the operating cash flow will be worked out as below:

Operating Cash Flow = (Quantity(Price-Variable Costs) - Annual FIxed Costs)*(1-tax rate) + Tax rate (Initial Investment/Useful life i.e tax benefit on Depreciation)

= ((27,000*(308-205)-1,100,000))*(1-0.23)+(0.23*(4,600,000/5))

= ((27000*(103)-1,100,000))*(0.77))+0.23*(920,000)

= (2,781,000 - 1,100,000)*0.77+0.23*(920,000)

=(1,681,000)*0.77+0.23*(920,000)

= (1,294,370+211,600)

= 1,505,970

Assuming that instead of 27000 tons of screws, 26000 tons of screws are to be manufactured, the operating cash flow would be

((26,000*(308-205)-1,100,000))*(1-0.23)+(0.23*(4,600,000/5))

= ((26000*(103)-1,100,000))*(0.77))+0.23*(920,000)

= (2,678,000 - 1,100,000)*0.77+0.23*(920,000)

=(1,578,000)*0.77+0.23*(920,000)

= (1,215,060+211,600)

= 1,426,660

Change in OCF/Change in Quantity = (1,505,970-1,426,660)/(27,000-26,000) = 79,310/1000 =79.31

2) Sensitivity of NPV to Change in Quantity

Based on 27000 tons of Screws to be manufactured, the NPV would be as below

NPV = - Initial Investment cost - Net Working Capital + PV of all Operating Cash flows till year 5+ PV of Salvage Value at end of year 5+ PV of Net Working capital at end of year 5

= -4,600,000- 440,000 + 1,505,970(1-((1+12%)^-5/0.12))+475,000/1.12^5+440,000/1.12^5

= -5,040,000+5,428,685+2,69,527.76+249,667.82

= 907,880.58.

Assuming that instead of 27000 tons of screw, 26000 tons of screw is manufactured the NPV would be

=-4,600,000- 440,000 + 1,426,660(1-((1+12%)^-5/0.12))+475,000/1.12^5+440,000/1.12^5

= -5,040,000+5,142,790+2,69,527.76+249,667.82

= 621,985.59

Change in NPV/Change in Quantity = (907,880.58-621,985.59)/(27,000-26,000) = 285,895/1000 = 285.90

c) Minimum output

The minimum level of output below which i would not operate is worked out as below:

The NPV of the project for 27000 tons of screws is 907,880.58. Dividing this by the Change in NPV/Change in Quantity factor will give the number of tons of screws required to make this NPV.

i.e 907,880.58 / 285.90 = 3175.52

This means 3176 tons are required to make this NPV. Reducing this from 27000 tons will give the quantity at which NPV will be zero.

i,e 27000-3176 = 23,824 tons of screws, below which I would not operate.

Add a comment
Know the answer?
Add Answer to:
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $6,000,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,450,000 and that variable costs should be $275 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,250,000 and that variable costs should be $235 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,600,000 Investment in threading equipment to get the project started, the project will last for 4 years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset Investment straight-line to zero over the 4-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production. You will need an initial $5,900,000 investment in threading equipment to get the project started, the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,425,000 and that variable costs should be $270 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started: the project will last for 5 vears. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Chapter 11 Problemsi Saved 10 Consider a project to supply Detroit with 27,000 tons of machine...

    Chapter 11 Problemsi Saved 10 Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,000,000 investment in threading equipment to get the project started, the project Will last for 5 years. The accounting department estimates that annual fixed costs willl be $1,200,000 and that variable costs should be $225 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,700,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,375,000 and that variable costs should be $260 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT