Question

On January 1, Sturdy Machines Inc. entered into a formal contract to construct a multipurpose warehouse...

On January 1, Sturdy Machines Inc. entered into a formal contract to construct a multipurpose warehouse for $15,000,000. To finance the construction project, the company immediately received an $8,000,000 construction loan from a local bank that included four $2,000,000 annual payments plus interest at 5%, with the remainder of the project financed with the company’s general debt facilities at a 7% weighted average interest rate. Assuming average accumulated expenses were $10,000,000 for the year and that actual interest costs incurred on all related borrowings was $890,000, what is the amount of capitalized interest costs recorded by the company?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

All the interest cost amounting $8,90,000 will be capitalized.

This is because the project is not completed yet.

Calculations

Interest on loan taken by the company = $8,00,0000 * 5% = $4,00,000

Remaining $70000000 = $70,00,000 *7% = $4,90,000

Total = $8,90,0000

Add a comment
Know the answer?
Add Answer to:
On January 1, Sturdy Machines Inc. entered into a formal contract to construct a multipurpose warehouse...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Situation On January 1, 2020, Crane, Inc. signed a fixed-price contract to have Builder Associates construct...

    Situation On January 1, 2020, Crane, Inc. signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,160,000. It was estimated that it would take 3 years to complete the project. Also on January 1, 2020, to finance the construction cost, Crane borrowed $4,160,000 payable in 10 annual installments of $416,000, plus interest at the rate of 10%. During 2020, Crane made deposit and progress payments totaling $1,560,000 under the contract; the weighted...

  • Situation I On January 1, 2020, Kingbird, Inc. signed a fixed-price contract to have Builder Associates...

    Situation I On January 1, 2020, Kingbird, Inc. signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,471,000. It was estimated that it would take 3 years to complete the project. Also on January 1, 2020, to finance the construction cost, Kingbird borrowed $4,471,000 payable in 10 annual installments of $447,100, plus interest at the rate of 10%. During 2020, Kingbird made deposit and progress payments totaling $1,676,625 under the contract; the...

  • Question Three: In 2016, the Westgate Construction Company entered into a contract to construct a road...

    Question Three: In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara Countyfor $10,000,000. The road was completed in 201 contract is as follows: 8. Information related to the 2018 2016 2,400,000 3,600,000 2,200,00 5,600,000 2,000,000 4,000,000 4,000,000 ,800,000 3,600,000 4,600,000 2017 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2,000,000 Westgate recognizes revenue over time according to percentage of...

  • Situation I On January 1, 2017, Tamarisk, Inc. signed a fixed-price contract to have Builder Associates...

    Situation I On January 1, 2017, Tamarisk, Inc. signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,215,000. It was estimated that it would take 3 years to complete the project. Also on January 1, 2017, to finance the construction cost, Tamansk borrowed $4,215 000 Payable in 10 annual installments of $421 500 plus interest at the rate of 10% During 2017 Tamarisk made deposit and progress Payments totaling S1 580,625 under...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 34 bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 340,000 690,000 690,000 630,000 The company's fiscal year-end is December 31. Required: Calculate...

  • Situation I On January 1, 2017, Tamarisk, Inc signed a fixed-price contract to have Builder Associates...

    Situation I On January 1, 2017, Tamarisk, Inc signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,215,000. It was estimated that it would take 3 years to complete the project, Also on January 1, 2017, to finance the construction cost Tamarisk borrowed $4,215,000 payable in 10 annual stallments of $421,500, plus interest at the rate of 10%. Dunng 2017 Tar ansk made deposit and progress payments totaling $1,580,625 under the contract;...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,500,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $8,000,000, 15% bonds $2,000,000, 10% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 660,000 March 31 1,260,000 June 30 872,000 September 30 660,000...

  • A company constructs a building for its own use. Construction began on January 1 and ended...

    A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $500,000; March 31, $600,000; June 30, $400,000; October 30, $600,000. To help finance construction, the company arranged a 7% construction loan on January 1 for $700,000. The company's other borrowings, outstanding for the whole year, consisted of a $3 million loan and a $5 million note with interest rates of 8% and...

  • A company constructs a building for its own use. Construction began on January 1 and ended...

    A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $540,000; March 31, $640,000; June 30, $440,000; October 30, $720,000. To help finance construction, the company arranged a 7% construction loan on January 1 for $780,000. The company’s other borrowings, outstanding for the whole year, consisted of a $5 million loan and a $7 million note with interest rates of 9% and...

  • Question 11 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse....

    Question 11 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $300,000 September 1, 2018 $450,000 December 31, 2018 $450,000 March 31, 2019 $450,000 September 30, 2019 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was: $1,950,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT