On January 1, Sturdy Machines Inc. entered into a formal contract to construct a multipurpose warehouse for $15,000,000. To finance the construction project, the company immediately received an $8,000,000 construction loan from a local bank that included four $2,000,000 annual payments plus interest at 5%, with the remainder of the project financed with the company’s general debt facilities at a 7% weighted average interest rate. Assuming average accumulated expenses were $10,000,000 for the year and that actual interest costs incurred on all related borrowings was $890,000, what is the amount of capitalized interest costs recorded by the company?
All the interest cost amounting $8,90,000 will be capitalized.
This is because the project is not completed yet.
Calculations
Interest on loan taken by the company = $8,00,0000 * 5% = $4,00,000
Remaining $70000000 = $70,00,000 *7% = $4,90,000
Total = $8,90,0000
On January 1, Sturdy Machines Inc. entered into a formal contract to construct a multipurpose warehouse...
Situation On January 1, 2020, Crane, Inc. signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,160,000. It was estimated that it would take 3 years to complete the project. Also on January 1, 2020, to finance the construction cost, Crane borrowed $4,160,000 payable in 10 annual installments of $416,000, plus interest at the rate of 10%. During 2020, Crane made deposit and progress payments totaling $1,560,000 under the contract; the weighted...
Situation I On January 1, 2020, Kingbird, Inc. signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,471,000. It was estimated that it would take 3 years to complete the project. Also on January 1, 2020, to finance the construction cost, Kingbird borrowed $4,471,000 payable in 10 annual installments of $447,100, plus interest at the rate of 10%. During 2020, Kingbird made deposit and progress payments totaling $1,676,625 under the contract; the...
Question Three: In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara Countyfor $10,000,000. The road was completed in 201 contract is as follows: 8. Information related to the 2018 2016 2,400,000 3,600,000 2,200,00 5,600,000 2,000,000 4,000,000 4,000,000 ,800,000 3,600,000 4,600,000 2017 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2,000,000 Westgate recognizes revenue over time according to percentage of...
Situation I On January 1, 2017, Tamarisk, Inc. signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,215,000. It was estimated that it would take 3 years to complete the project. Also on January 1, 2017, to finance the construction cost, Tamansk borrowed $4,215 000 Payable in 10 annual installments of $421 500 plus interest at the rate of 10% During 2017 Tamarisk made deposit and progress Payments totaling S1 580,625 under...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 34 bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 340,000 690,000 690,000 630,000 The company's fiscal year-end is December 31. Required: Calculate...
Situation I On January 1, 2017, Tamarisk, Inc signed a fixed-price contract to have Builder Associates construct a major plant facility at a cost of $4,215,000. It was estimated that it would take 3 years to complete the project, Also on January 1, 2017, to finance the construction cost Tamarisk borrowed $4,215,000 payable in 10 annual stallments of $421,500, plus interest at the rate of 10%. Dunng 2017 Tar ansk made deposit and progress payments totaling $1,580,625 under the contract;...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,500,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $8,000,000, 15% bonds $2,000,000, 10% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 660,000 March 31 1,260,000 June 30 872,000 September 30 660,000...
A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $500,000; March 31, $600,000; June 30, $400,000; October 30, $600,000. To help finance construction, the company arranged a 7% construction loan on January 1 for $700,000. The company's other borrowings, outstanding for the whole year, consisted of a $3 million loan and a $5 million note with interest rates of 8% and...
A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $540,000; March 31, $640,000; June 30, $440,000; October 30, $720,000. To help finance construction, the company arranged a 7% construction loan on January 1 for $780,000. The company’s other borrowings, outstanding for the whole year, consisted of a $5 million loan and a $7 million note with interest rates of 9% and...
Question 11 (1 point) On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $300,000 September 1, 2018 $450,000 December 31, 2018 $450,000 March 31, 2019 $450,000 September 30, 2019 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was: $1,950,000...