Question

2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very well since the project is well ahead of schedule

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer -

As per given information :

Activity Expected Cost Expected % Complete Actual % Complete Actual Cost to Date
Activity 1 $1415000 100% 100% $1295000
Activity 2 $10495000 100% 100% $8995000
Activity 3 $8495000 58% 65% $4995000
Total $20405000 $15285000

Budgeted Cost of Work Scheduled (BCWS)

Activity 1 100% of $1415000 $1415000
Activity 2 100% of $10495000 $10495000
Activity 3 58% of $8495000 $4927100
Total $16837100

Budgeted Cost of Work Performed (BCWP)

Activity 1 100% of $1415000 $1415000
Activity 2 100% of $10495000 $10495000
Activity 3 65% of $8495000 $5521750
Total $17431750

So,

Scheduled Variance = Total BCWP - Total BCWS

Scheduled Variance = $17431750 - $16837100

Scheduled Variance = $594650

Then,

Schedule Performance Index = Total BCWP / Total BCWS

Schedule Performance Index = $17431750 / $16837100

Schedule Performance Index = 1.035

And

Cost Variance = Total BCWP - Total actual cost to date

Cost Variance = $17431750 - $15285000

Cost Variance = $2146750

Then,

Cost Performance Index = Total BCWP / Total actual cost to date

Cost Performance Index = $17431750 / $15285000

Cost Performance Index = 1.140

So,

Scheduled Variance $594650
Schedule Performance Index 1.035
Cost Performance Index 1.140
Add a comment
Know the answer?
Add Answer to:
2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the...

    Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were only expecting to be 57% through the third activity at this time. The first activity involves prepping the site for the bridge. It was...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • NO EXPLANATION NEEDED, JUST ANSWER. A senior manager is in the process of selecting a project...

    NO EXPLANATION NEEDED, JUST ANSWER. A senior manager is in the process of selecting a project manager for a new initiative that is very important for the company’s future. What is the key factor in choosing a project manager? The project manager should be the most technically competent person on the team The PM works well with various levels of management The project manager should be the functional manager of the most people on the team The project manager must...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT