Answer -
As per given information :
Activity | Expected Cost | Expected % Complete | Actual % Complete | Actual Cost to Date |
Activity 1 | $1415000 | 100% | 100% | $1295000 |
Activity 2 | $10495000 | 100% | 100% | $8995000 |
Activity 3 | $8495000 | 58% | 65% | $4995000 |
Total | $20405000 | $15285000 |
Budgeted Cost of Work Scheduled (BCWS)
Activity 1 | 100% of $1415000 | $1415000 |
Activity 2 | 100% of $10495000 | $10495000 |
Activity 3 | 58% of $8495000 | $4927100 |
Total | $16837100 |
Budgeted Cost of Work Performed (BCWP)
Activity 1 | 100% of $1415000 | $1415000 |
Activity 2 | 100% of $10495000 | $10495000 |
Activity 3 | 65% of $8495000 | $5521750 |
Total | $17431750 |
So,
Scheduled Variance = Total BCWP - Total BCWS
Scheduled Variance = $17431750 - $16837100
Scheduled Variance = $594650
Then,
Schedule Performance Index = Total BCWP / Total BCWS
Schedule Performance Index = $17431750 / $16837100
Schedule Performance Index = 1.035
And
Cost Variance = Total BCWP - Total actual cost to date
Cost Variance = $17431750 - $15285000
Cost Variance = $2146750
Then,
Cost Performance Index = Total BCWP / Total actual cost to date
Cost Performance Index = $17431750 / $15285000
Cost Performance Index = 1.140
So,
Scheduled Variance | $594650 |
Schedule Performance Index | 1.035 |
Cost Performance Index | 1.140 |
2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very...
Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were only expecting to be 57% through the third activity at this time. The first activity involves prepping the site for the bridge. It was...
2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...
NO EXPLANATION NEEDED, JUST ANSWER. A senior manager is in the process of selecting a project manager for a new initiative that is very important for the company’s future. What is the key factor in choosing a project manager? The project manager should be the most technically competent person on the team The PM works well with various levels of management The project manager should be the functional manager of the most people on the team The project manager must...
How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...