A local financial consulting firm employs 20 full-time staff. The estimated compensation per employee is $50838 for 2049 hours. All direct labour costs are charged to clients. Any other costs are included in a single indirect-cost pool, allocated according to labour-hours.
If the total cost of a job that will take 23 hours is $2447 using a job order cost system, what is the budgeted indirect costs for the coming year?
Select one:
a. $1876
b. $3343156
c. $3997143
d. $104167062
Data regarding Lager Ltd.’s production for the year is given below:
Per unit information:
Direct labour |
$13 |
|
Direct material |
9 |
|
Applied manufacturing overhead |
8 |
|
Unit production (budget) |
31184 |
|
Unit production (actual) |
23971 |
|
Actual overhead costs incurred |
$132674 |
Lager Ltd.’s manufacturing overhead for the year was:
Select one:
a. Under-applied by $59094
b. Under-applied by $116798
c. Over-applied by $116798
d. Over-applied by $59094
Please provide rating...
Answer 1 | |||||
Total cost = | 2447 | ||||
Direct cost per hr = | 24.81 | ||||
=50838/2049 | |||||
Direct cost of the job | 571 | ||||
=24.81*23 | |||||
Indirect cost = | 1876 | ||||
=2447-571 | |||||
Correct answer is option a. > 1876 | |||||
Answer 2 | |||||
Direct labour | $13 | ||||
Direct material | 9 | ||||
Applied manufacturing overhead | 8 | ||||
Unit production (budget) | 31184 | ||||
Unit production (actual) | 23971 | ||||
Actual overhead costs incurred | $132,674 | ||||
Applied overhead = | 191768 | ||||
=23971*8 | |||||
Actual overhead cost = | $132,674 | ||||
Over applied - overhead | $59,094 | ||||
=191768-132674 | |||||
Correct answer is option d. | Overapplied by 59094 |
A local financial consulting firm employs 20 full-time staff. The estimated compensation per employee is $50838...
A firm uses direct labour-hours to apply overhead to products. Overhead was under-applied for the year by $36899. The actual manufacturing overhead for the year was $111493. The budgeted manufacturing overhead was $138421 and budgeted labour-hours were 6779. Direct labour is paid at the rate of $21 per hour. What was the total direct labour cost for the year? Select one: a. $76716 b. $114665 c. $152614 d. $142359 Lager Ltd.’s production volume and per unit information for the year...
Question 3 Not yet answered Marked out of 1.00 P Flag question Data regarding Lager Ltd.'s production for the year is given below: Per unit information: $13 Direct labour Direct material Applied manufacturing overhead Unit production (budget) 27358 23422 Unit production (actual) Actual overhead costs incurred $132749 Lager Ltd.'s manufacturing overhead for the year was: Select one: 0 a. over-applied by $58757 O b. Under-applied by $31205 c. Over-applied by $31 205 d. Under-applied by $58757 O
A local accounting firm employs 24 full-time professionals. The budgeted annual compensation per employee is $45,000. The average chargeable time is 420 hours per client annually. All professional labor costs are included in a single direct-cost category and are allocated to jobs on a per-hour basis. Other costs are included in a single indirect-cost pool, allocated according to professional labor-hours. Budgeted indirect costs for the year are $790,000, and the firm expects to have 90 clients during the coming year....
Lager Ltd.’s production volume and per unit information for the year is given below: Per unit information: Direct labour $15 Direct material 12 Applied manufacturing overhead 5 Unit production (budget) 23046 Unit production (actual) 32427 For Lager’s total units produced this year, how much were the conversion costs? Select one: a. $1037664 b. $648540 c. $460920 d. $875529
Wojtek Co. has a job order cost system. The following debits (credits) appeared in the work in process account for the month of August: Date Description Amount Aug 1 Opening balance $10205 Aug 31 Direct materials 61133 Aug 31 Direct labour 44893 Aug 31 Manufacturing Overhead 35914.4 Aug 31 To finished goods (124894) Job # 910, the only job still in process at the end of August has been charged with direct materials of $4043. What was the amount of...
Edney Company employs a standard cost system for product costing. The per-unit standard cost of its product is: Raw materials $ 14.50 Direct labor (2 direct labor hours × $8.00 per hour) 16.00 Manufacturing overhead (2 direct labor hours × $11.00 per hour) 22.00 Total standard cost per unit $ 52.50 The manufacturing overhead rate is based on a normal capacity level of 600,000 direct labor hours. (Normal capacity is defined as the level of capacity needed to satisfy average...
Question 4 Not vet answered Marked out of 1.00 P Flag question Lager Ltd.'s production volume and per unit information for the year is given below: Per unit information Direct labour Direct material Applied manufacturing overhead $13 10 Unit production (budget) Unit production (actual) For Lager's total units produced this year, how much were the conversion costs? 22967 34512 Select one a. $621216 b. $793776 c. $413406 d. $966336
A company uses a job order cost system and applies manufacturing overhead costs to jobs using a predetermined overhead rate based on direct labour-hours. The following data were extracted from the company's accounting records for the previous year: Manufacturing overhead: estimated: $50,000 actual: $55,000 Direct labour hours: estimated: #20,000 hrs actual: #24,000 hrs A job completed during the year incurred the following costs: Direct Materials $4,000 Direct labour $1,500 (at $5 per DLH) What was the under applied or over...
2 Kahn & Associates is a low firm sp i n d l ated work employs 25 professionals partners and 18 associates) who work direct with clients Them e budete total compensation per professional or 2017 is $110.000. Each professionalisbudpated to havn 2000 hab hours to clients in 2017. All professionals work for Clients to their maximum 2.000 billable hours available. All professional labor costs are included in a single direct-cost category and are traced to jobs on a per...
Brighton Services repairs locomotive engines. It employs 100 full-time workers at $14 per hour. Despite operating at capacity, last year's performance was a great disappointment to the managers. In total, 10 jobs were accepted and completed, incurring the following total costs. Direct materials $ 1,045,400 Direct labor 4,200,000 Manufacturing overhead 975,000 Of the $975,000 manufacturing overhead, 40 percent was variable overhead and 60 percent was fixed. This year, Brighton Services expects to operate at the same activity level as last...