14-17 Saved Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing over
0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Assembly department overhead rate = Manufacturing overhead costs / Direct labor hours

= 1228200 / 12300

= $99.85 per Direct labor hour

Add a comment
Know the answer?
Add Answer to:
14-17 Saved Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Rafner Manufacturing identified the following budgeted data in its two production departments Assembly $1,181,700 Finishing $580,000...

    Rafner Manufacturing identified the following budgeted data in its two production departments Assembly $1,181,700 Finishing $580,000 19,800 DLH 15,800 MH Manufacturing overhead costs Direct labor hours Machine hours 11,800 DLH 5,800 MH Required: What are the company's departmental overhead rates if the assembly department assigns overhead based on direct labor hours and the finishing department assigns overhead based on machine hours? 05 The departmental overhead rate for Assembly The departmental overhead rate for Finishing

  • QS 17-5 Computing departmental overhead rates LO P2 Rafner Manufacturing identified the following budgeted data in...

    QS 17-5 Computing departmental overhead rates LO P2 Rafner Manufacturing identified the following budgeted data in its two production departments, Manufacturing overhead coats Direct labor hours Machine hours Assembly $1,146,300 11,400 DLH 5.400 MH Finishing $540,000 19.400 DLH 15, 400 M Required: What are the company's departmental overhead rates if the assembly department assigns overhead based on direct labor hours and the finishing department assigns overhead based on machine hours? The departmental overhead rate for Assembly The departmental overhead rate...

  • Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead costs Direct...

    Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead costs Direct labor hours Machine hours Assembly $1,247,500 12,500 DLH 6,500 MH Finishing $ 650,000 20,500 DLH 16,500 MH points Required: 1. What is the company's single plantwide overhead rate based on direct labor hours? 2. What is the company's single plantwide overhead rate based on machine hours?

  • QS 17-5 Computing departmental overhead rates LO P2 Rafner Manufacturing identified the following budgeted data in...

    QS 17-5 Computing departmental overhead rates LO P2 Rafner Manufacturing identified the following budgeted data in its two production departments. Assembly $1,218,700 12,200 DLH 6,200 MH Manufacturing overhead costs Direct labor hours Machine hours Finishing $620,000 20,200 DLH 16,200 MH points (8 03:15:46 Required: What are the company's departmental overhead rates if the assembly department assigns overhead based on direct labor hours and the finishing department assigns overhead based on machine hours? Hint The departmental overhead rate for Assembly G...

  • QS 17-4 Computing plantwide overhead rates LO P1 Rafner Manufacturing identified the following budgeted data in...

    QS 17-4 Computing plantwide overhead rates LO P1 Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead costs Direct labor hours Machine hours Assembly $1,120, 800 11,100 DLH 5,100 MH Finishing $ 510,000 19,100 DLH 15,100 MH Required: 1. What is the company's single plantwide overhead rate based on direct labor hours? 2. What is the company's single plantwide overhead rate based on machine hours?

  • Saved Help Se QS 17-4 Computing plantwide overhead rates LO P1 Rafner Manufacturing identified the following...

    Saved Help Se QS 17-4 Computing plantwide overhead rates LO P1 Rafner Manufacturing identified the following budgeted data in its two production departments. Assembly $1,267,200 12,700 DLH 6,700 MH Finishing $670,eee Manufacturing overhead costs Direct labor hours Machine hours 28,700 DLH 16,700 MH Required: ces 1. What is the company's single plantwide overhead rate based on direct labor hours? <Prev 2 of 7 Next> se bere to search 7 O T K M N V Z X 166 S

  • What is the company’s Finishing department overhead rate using machine hours? Check my work Rafner Manufacturing...

    What is the company’s Finishing department overhead rate using machine hours? Check my work Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead costs Direct labor hours Machine hours Assembly $1,267,200 12,700 DLH 6,700 MH Finishing $ 670,000 20,700 DLH 16,700 MH points eBook Required: What is the company's Finishing department overhead rate using machine hours? Print References The departmental overhead rate for Finishing Estimated overhead costs Estimated machine hours

  • PT 1 & 2 Rafner Manufacturing identified the following budgeted data in its two production departments....

    PT 1 & 2 Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead costs Direct labor hours Machine hours Assembly $1,257,300 12,600 DLH 6,600 MH Finishing $ 660,000 20,600 DLH 16,600 MH Required: What is the company's assembly department overhead rate using direct labor hours? The departmental overhead rate for Assembly Smythe Co. makes furniture. The following data are taken from its production plans for the year. Direct labor costs Hazardous waste disposal costs $5,890,000...

  • Student Ch 15/17 job order and ABC cturer reports the following budgeted data for its two...

    Student Ch 15/17 job order and ABC cturer reports the following budgeted data for its two production departments: Machining Assembly Manufacturing overhead costs $600,000 $300,000 Machine hours (MH) to be used 20,000 Direct Labor hours (DLH) to be used 20,000 5,000 a) What is the company's single plant-wide overhead rate based on DLH?. b) Using the overhead rate computed in (a), how much overhead should be assigned to job 22 that uses 20 DLH in Machining and 5 DLH in...

  • Exercise 17-6 Assigning overhead costs using the plantwide rate and departmental rate methods LO P1, P2...

    Exercise 17-6 Assigning overhead costs using the plantwide rate and departmental rate methods LO P1, P2 Laval produces lamps and home lighting fixtures. Its most popular product is a brushed aluminum desk lamp. This lamp is made from components shaped in the fabricating department and assembled in the assembly department. Information related to the 25,000 desk lamps produced annually follows. $265,000 Direct materials Direct labor Fabricating department (9,000 DLH * $28 per DLH) Assembly department (15,400 DLH * $23 per...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT