Question

Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead costs D

1 2
Add a comment Improve this question Transcribed image text
Answer #1

1)

Estimated overhead costs 1,247,500 99.8 per direct labor hour
Estimated direct labor hours 12,500

2)

Estimated overhead costs 650,000 39.4 per machine hour
Estimated machine hours 16,500

Comment if you face any issues

Add a comment
Know the answer?
Add Answer to:
Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead costs Direct...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 14-17 Saved Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead...

    14-17 Saved Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead costs Direct labor hours Machine hours ! Assembly $1,228,200 12,300 DLH 6,300 MH Finishing $630,000 20, 300 DLH 16,300 MH Required: What is the company's assembly department overhead rate using direct labor hours? The departmental overhead rate for Assembly

  • Rafner Manufacturing identified the following budgeted data in its two production departments Assembly $1,181,700 Finishing $580,000...

    Rafner Manufacturing identified the following budgeted data in its two production departments Assembly $1,181,700 Finishing $580,000 19,800 DLH 15,800 MH Manufacturing overhead costs Direct labor hours Machine hours 11,800 DLH 5,800 MH Required: What are the company's departmental overhead rates if the assembly department assigns overhead based on direct labor hours and the finishing department assigns overhead based on machine hours? 05 The departmental overhead rate for Assembly The departmental overhead rate for Finishing

  • QS 17-4 Computing plantwide overhead rates LO P1 Rafner Manufacturing identified the following budgeted data in...

    QS 17-4 Computing plantwide overhead rates LO P1 Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead costs Direct labor hours Machine hours Assembly $1,120, 800 11,100 DLH 5,100 MH Finishing $ 510,000 19,100 DLH 15,100 MH Required: 1. What is the company's single plantwide overhead rate based on direct labor hours? 2. What is the company's single plantwide overhead rate based on machine hours?

  • QS 17-5 Computing departmental overhead rates LO P2 Rafner Manufacturing identified the following budgeted data in...

    QS 17-5 Computing departmental overhead rates LO P2 Rafner Manufacturing identified the following budgeted data in its two production departments, Manufacturing overhead coats Direct labor hours Machine hours Assembly $1,146,300 11,400 DLH 5.400 MH Finishing $540,000 19.400 DLH 15, 400 M Required: What are the company's departmental overhead rates if the assembly department assigns overhead based on direct labor hours and the finishing department assigns overhead based on machine hours? The departmental overhead rate for Assembly The departmental overhead rate...

  • PT 1 & 2 Rafner Manufacturing identified the following budgeted data in its two production departments....

    PT 1 & 2 Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead costs Direct labor hours Machine hours Assembly $1,257,300 12,600 DLH 6,600 MH Finishing $ 660,000 20,600 DLH 16,600 MH Required: What is the company's assembly department overhead rate using direct labor hours? The departmental overhead rate for Assembly Smythe Co. makes furniture. The following data are taken from its production plans for the year. Direct labor costs Hazardous waste disposal costs $5,890,000...

  • Saved Help Se QS 17-4 Computing plantwide overhead rates LO P1 Rafner Manufacturing identified the following...

    Saved Help Se QS 17-4 Computing plantwide overhead rates LO P1 Rafner Manufacturing identified the following budgeted data in its two production departments. Assembly $1,267,200 12,700 DLH 6,700 MH Finishing $670,eee Manufacturing overhead costs Direct labor hours Machine hours 28,700 DLH 16,700 MH Required: ces 1. What is the company's single plantwide overhead rate based on direct labor hours? <Prev 2 of 7 Next> se bere to search 7 O T K M N V Z X 166 S

  • QS 17-5 Computing departmental overhead rates LO P2 Rafner Manufacturing identified the following budgeted data in...

    QS 17-5 Computing departmental overhead rates LO P2 Rafner Manufacturing identified the following budgeted data in its two production departments. Assembly $1,218,700 12,200 DLH 6,200 MH Manufacturing overhead costs Direct labor hours Machine hours Finishing $620,000 20,200 DLH 16,200 MH points (8 03:15:46 Required: What are the company's departmental overhead rates if the assembly department assigns overhead based on direct labor hours and the finishing department assigns overhead based on machine hours? Hint The departmental overhead rate for Assembly G...

  • What is the company’s Finishing department overhead rate using machine hours? Check my work Rafner Manufacturing...

    What is the company’s Finishing department overhead rate using machine hours? Check my work Rafner Manufacturing identified the following budgeted data in its two production departments. Manufacturing overhead costs Direct labor hours Machine hours Assembly $1,267,200 12,700 DLH 6,700 MH Finishing $ 670,000 20,700 DLH 16,700 MH points eBook Required: What is the company's Finishing department overhead rate using machine hours? Print References The departmental overhead rate for Finishing Estimated overhead costs Estimated machine hours

  • Student Ch 15/17 job order and ABC cturer reports the following budgeted data for its two...

    Student Ch 15/17 job order and ABC cturer reports the following budgeted data for its two production departments: Machining Assembly Manufacturing overhead costs $600,000 $300,000 Machine hours (MH) to be used 20,000 Direct Labor hours (DLH) to be used 20,000 5,000 a) What is the company's single plant-wide overhead rate based on DLH?. b) Using the overhead rate computed in (a), how much overhead should be assigned to job 22 that uses 20 DLH in Machining and 5 DLH in...

  • DATA FOR GRAPHS: 1) Est. Overhead costs by Department a) Finishing: $3,000,000 b) assembly: $5,000,000 2)Estimated...

    DATA FOR GRAPHS: 1) Est. Overhead costs by Department a) Finishing: $3,000,000 b) assembly: $5,000,000 2)Estimated Direct Labor Hours & Machine Hours by Department a) Direct labor hours: Finishing=25,000 hr , Assembly=100,000 hr b) Machine hours: finishing =30,000 hr , assembly = 70,000 hr 3) Est. Overhead costs by activity a) supervision : $2,000,000 b) maintenace : $6,000,000 Cost Driver & Exp. Usage by Activity a) Supervison: 125,000 direct labor hours b) Maintance: 100,000 machine hours Chrom Co. manufactures two...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT