Consider two mutually exclusive projects with the following cash flows: Project A is a 6 year project with initial (time 0) cash outflow of 40,000 and time 1 through 6 cash inflows of 8000,14000,13000,12000,11000,and 10000 respectively. Project B is a 3 year project with initial (time 0) cash outflow of 20,000 and time 1 through 3 cash inflows of 7000,13000, and 12000 respectively. Assuming a 11.5% cost of capital compute the NPV for project A.
a 7,165.11
b 5,391.49
c 12,000
d 28,000
NPV = -initial investment + PV of future cash flows
Present value = Future value/(1+i)^n
i = interest rate per period
=>
NPV = -40000 + 8000/1.115 + 14000/1.115^2 + 13000/1.115^3 + 12000/1.115^4 + 11000/1.115^5 + 10000/1.115^6
= 7165.11
choose a)
Consider two mutually exclusive projects with the following cash flows: Project A is a 6 year...
Consider two mutually exclusive projects with the following cash flows: Project A is a 6 year project with initial (time 0) cash outflow of 40,000 and time 1 through 6 cash inflows of 8000,14000,13000,12000,11000,and 10000 respectively. Project B is a 3 year project with initial (time 0) cash outflow of 20,000 and time 1 through 3 cash inflows of 7000,13000, and 12000 respectively. Assuming a 11.5% cost of capital compute the NPV for project B. Group of answer choices a...
Consider two mutually exclusive projects with the following cash flows: Project A is a 6 year project with initial (time 0) cash outflow of 40,000 and time 1 through 6 cash inflows of 8000,14000,13000,12000,11000,and 10000 respectively. Project B is a 3 year project with initial (time 0) cash outflow of 20,000 and time 1 through 3 cash inflows of 7000,13000, and 12000 respectively. Assuming a 11.5% cost of capital compute the NPV for project A.
Consider two mutually exclusive projects with the following cash flows: Project S is a 4 year project with initial (time 0) cash outflow of 3000 and time 1 through 4 cash inflows of 1500, 1200, 800 and 300 respectively. Project L is a 4 year project with initial (time 0) cash outflow of 3000 and time 1 through 4 cash inflows of 400, 900, 1300, and 1500 respectively. Assuming a 5% cost of capital, compute the IRR for project S.
2. Two projects being considered are mutually exclusive and have the following projected cash flows:. If the required rate of return on these projects is 11 percent, which would be chosen and why? Project A Project B Year Cash Flow Cash Flow 0 -40,000 -40,000 1 15,625 0 2 15,625 0 3 15,625 0 4 15,625 0 5 15,625 99,500 3. Two projects being considered are mutually exclusive and have the following projected cash flows:. If the required rate of...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0 1 2 3 Project A Cash Flow -30,000 20,000 40,000 11,000 Project B Cash Flow -40,000 20,000 30,000 60,000 Use the NPV decision rule to evaluate these...
You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project A Project B 0 -28 -43 1 30 45 2 40 50 Part 1 What is the crossover rate, i.e., the discount rate at which both projects have the same NPV?
(Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project A Project B Cash Flow Cash Flow $(102,000) $(102,000) 40,000 40.000 40.000 40,000 0 40,000 215,000 If the appropriate discount rate on these projects is 9 percent, which would be chosen and why? The NPV of Project Ass (Round to the nearest cont.)
Canfly Airlines is considering two mutually exclusive projects, Project A and Project B. The projects have the following cash flows (in millions of dollars):YearProject A Cash FlowProject B Cash Flow0-$4.0-$4.512.01.723.03.235.0?The crossover rate of the two projects’ NPV profiles is 9 percent. What is the cash flow for Project B at t = 3?
NPV and IRR analysis of projects Thomas Company is considering two mutually exclusive projects. The firm, which has a cost of capital of 14%, has estimated its cash flows as shown in the following table: a. Calculate the NPV of each project, and assess its acceptability. b. Calculate the IRR for each project, and assess its acceptability. a. The NPV of project A is $ (Round to the nearest cent.) Х i Data Table (Click on the icon located on...
A FBO is evaluating two projects that are mutually exclusive with initial investments and cash flows as follows: Year Cash Flows (A) Cash Flows (B) 0 1 2 3 4 5 -$11,000 3,000 3,000 3,000 3,000 3,000 -$8,000 2,500 2,500 2,500 2,500 2,500 Discount rate = 3.52% What is the NPV of project (A)? 2,539 2,739 3,449 4,000