The sanding department of Hanninen Furniture Company has the following production and manufacturing cost data for March 2020,Total units 15860 15860 12740 Costs Unit costs Costs in March Equivalent units Unit costs Costs to be accounted for Work in pUnit costs $ Costs to be accounted for Work in process, March 1 Started into production Total costs Cost Reconciliation Sched

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Hannien Furniture company
Sanding Department
Production Cost report
For the month ended march 31, 2020
Particulars Physical Units Equivalent units
Material Conversion
Work in Process, beginning 0
Started during the current period 15860
Total units to account for 15860
Units accounted for:
Unit completed & Transferred out 11700 11700 11700
Closing WIP: 4160
Material (100%) 4160
Conversion (25%) 1040
Equivalent units of production 15860 15860 12740
Hannien Furniture company
Sanding Department
Computation of Cost per equivalent unit of Production
Particulars Material Conversion
Opening WIP $0.00 $0.00
Cost Added during Period $53,924.00 $78,988.00
Total cost to be accounted for $53,924.00 $78,988.00
Equivalent units of production 15860 12740
Cost per Equivalent unit $3.40 $6.20
Hannien Furniture company
Sanding Department
Computation of Cost of ending WIP and units completed & transferred out
Particulars Material Conversion Total
Equivalent unit of Ending WIP 4160 1040
Cost per equivalent unit $3.40 $6.20
Cost of Ending WIP (Equivalent unit * Cost per equivalent unit) $14,144 $6,448 $20,592
Units completed and transferred 11700 11700
Cost of units completed & Transferred (Unit completed * cost per equivalent unit) $39,780 $72,540 $112,320
Hannien Furniture company
Sanding Department
Cost reconcilaition
Particulars Amount
Costs to be accounted for:
Cost of beginning WIP inventory $0.00
Cost added to production $132,912.00
Total Cost to be accounted for $132,912.00
Costs accounted for as follows:
Cost of unit transferred out $112,320
Ending WIP $20,592
Total cost accounted for $132,912.00
Add a comment
Know the answer?
Add Answer to:
The sanding department of Hanninen Furniture Company has the following production and manufacturing cost data for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for...

    The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2017, the first month of operation. Production: 7,330 units finished and transferred out; 3,000 units started that are 100% complie e as to mater as and 20% tomplete as to conversion costs. Manufacturing costs: Materials $36,981; labor $21,100; overhead $42,102. Prepare a production cost report. (Round unit costs to 2 decimal places, e.g. 2.25.) QUIK FURNITURE COMPANY Sanding Department Production Cost Report For...

  • The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for...

    The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2017, the first month of operation Production: 6,810 units finished and transferred out: 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $32,079; labor $20,600; overhead $35,271. Prepare a production cost report. (Round unit costs to 2 decimal places, e-s. 2.25.) QUIK FURNITURE COMPANY Sanding Department Production Cost Report For the Month...

  • The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for...

    The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation. Production: 7,140 units finished and transferred out: 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs Manufacturing costs: Materials $35,490; labor $20,700: overhead $42,768. Prepare a production cost report. (Round unit costs to 2 decimal places, eg. 2.25 and other answers to decimal places, eg, 125.) QUIK FURNITURE COMPANY...

  • The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for...

    The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation. Production: 6,520 units finished and transferred out: 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $36,176; labor $21,400; overhead $34,848. Prepare a production cost report. (Round unit costs to 2 decimal places, eg. 2.25 and other answers to decimal places, eg. 125.) QUIK FURNITURE COMPANY...

  • The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for...

    The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation. Production: 6,060 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $28,992; labor $21,300; overhead $34,311. Prepare a production cost report. (Round unit costs to 2 decimal places, eg. 2.25 and other answers to O decimal places, e-g. 125.) QUIK FURNITURE...

  • The Sanding Department of Bramble Furniture Company has the following production and manufacturing cost data for...

    The Sanding Department of Bramble Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation. Production: 6,600 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. osh Manufacturing costs: Materials $31,6B0; labor $20,700; overhead $35,460. Prepare a production cost report. (Round unlt costs to 2 decimal places, eg. 2.25 and other answers to decimal places. e.s. 125.) BRAMBLE FURNITURE...

  • Exercise 16-7 The Sanding Department of Quik Furniture Company has the following production and manufacturing cost...

    Exercise 16-7 The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2017, the first month of operation. Production: 7,330 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $36,981; labor $21,100; overhead $42,102. CALCULATOR QUIK FURNITURE COMPANY Sanding Department Production Cost Report For the Month Ended March 31, 2017 Equivalent Units Physical Conversion Units Materials Costs...

  • Exercise 21-7 The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data...

    Exercise 21-7 The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2017, the first month of operation. Production: 6,230 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $36,735; labor $21,400; overhead $30,235 Prepare a production cost report. (Round unit costs to 2 decimal places, e.g. 2.25.) QUIK FURNITURE COMPANY Production Cost Renort For the Month...

  • Exercise 16-0/ (Video) The Sanding Department of Crane Furniture Company has the following production and manufacturing...

    Exercise 16-0/ (Video) The Sanding Department of Crane Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation. Production: 6,240 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $36,960; labor $21,400; overhead $30,242. Prepare a production cost report. (Round unit costs to 2 decimal places, e.g. 2.25 and other answers to decimal places, e.g. 125.)...

  • The Sanding Department of Bonita Furniture Company has the following production and manufacturing cost data for...

    The Sanding Department of Bonita Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation. Production: 7,420 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $35,428; labor $21,000; overhead $39,150. Prepare a production cost report. (Round unit costs to 2 decimal places, e.g. 2.25 and other answers to decimal places, e.g. 125.) BONITA FURNITURE COMPANY...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT