Question

If customer demand is 207,000 units per month, and available manufacturing capacity is 6,000 hours per...

If customer demand is 207,000 units per month, and available manufacturing capacity is 6,000 hours per week, what is the Takt time for this firm? (Round your answer to 2 decimal places.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Takt time

= (6,000*4 weeks) / 207,000

= 24,000/207,000

= 0.12 hours

Comment if you face any issues. Note that I gave given answer in hours, not minutes
Add a comment
Know the answer?
Add Answer to:
If customer demand is 207,000 units per month, and available manufacturing capacity is 6,000 hours per...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following...

    Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units Actual run time this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) 5.696 minutes 6,400 minutes 1.68 units per minute 2.00 units per minute 12,670 units 18,100 units Required: 1. Compute...

  • Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following...

    Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units actual run time this week! Machine time available per week Actual run rate this wook Ideal run rate Defect-free output this week Total output this week (including defects 4,900 minutes 7.003 minutes 3.8 units per minute 4.0 units per minute 15.827 units 18,620 units Book Required: 1....

  • Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company provided...

    Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units points Skipped Actual run time this wook Machine time available per week Actual run note this week Ideal run rate Defect-free output this week Total output this week (including defects) 6,600 minutes 11,000 minutes 5.1 units per minute 6 units per minute 23,562 units 33,660...

  • 00 Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company...

    00 Kilmer Company has demand for its only product that exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units points Skipood Actual run time this week Machine time available per week Actual run rate this wook Ideal run rate Defect-free output this week Total output this week (includine defects 7.500 minutes 12.see minutes 6.30 units per minute 7 units per minute 37,800 units...

  • What cycle time would match capacity and demand if demand is 167 units a day, there...

    What cycle time would match capacity and demand if demand is 167 units a day, there are 1 shift(s) of 452 minutes each, and workers are given three 45 minute breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.) Cycle time             minutes per cycle

  • Johnson Electronics manufactures a power supply used in a variety of electronics products, including printers, modems,...

    Johnson Electronics manufactures a power supply used in a variety of electronics products, including printers, modems, and routers. The demand for the part is 7,700 units per week. The production of the power supply requires six different manufacturing operations, each in sequence and each having the following processing times. The net available time to work is 48 hours per week, using two shifts. Processing Time (seconds) Operation Operation 1 Operation 2 Operation 3 Operation 4 Operation 5 Operation 6 Required:...

  • World Company expects to operate at 60% of its productive capacity of 28,000 units per month....

    World Company expects to operate at 60% of its productive capacity of 28,000 units per month. At this planned level, the company expects to use 7,560 standard hours of direct labor. Overhead is allocated to products using a predetermined standard rate of 0.450 direct labor hour per unit. At the 60% capacity level, the total budgeted cost includes $22,680 fixed overhead cost and $60,480 variable overhead cost. In the current month, the company incurred $63,920 actual overhead and 7,130 actual...

  • A) B) C) Hickory Company manufactures two products-14,000 units of Product Y and 6,000 units of...

    A) B) C) Hickory Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $614,400 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Estimated Expected Overhead Cost Activity $ 198,000 10,000 MHs $ a 86,400...

  • Marge Manufacturing has the following information available for the month: • Budgeted production is 400,000 units...

    Marge Manufacturing has the following information available for the month: • Budgeted production is 400,000 units and the firm’s selling price per unit is $25. • Each unit produced is budgeted to require 2 ounces of material B at a cost of $2 per ounce and 0.25 direct labor hours at a cost of $30 per hour Instead of just giving an answer, it would be great if you can explain how to do it/why b. How many ounces of...

  • Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per...

    Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: TTT Task A B Time (seconds) 10 21 20 Predecessors A A 28 E 12 D 10 D G 40 E,F b. What is the takt time? (Round your answer to the nearest whole number.) Takt time seconds per unit c. What is the theoretical number of workstations? (Round...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT